Applications, hearings, determinations, etc.: Duke Energy Corp.,

[Federal Register: August 15, 2001 (Volume 66, Number 158)]

[Notices]

[Page 42893-42894]

From the Federal Register Online via GPO Access [wais.access.gpo.gov]

[DOCID:fr15au01-116]

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-369, 370, 413, and 414]

Duke Energy Corporation, McGuire Units 1 and 2, and Catawba, Units 1 and 2; Notice of Acceptance for Docketing of the Application and Notice of Opportunity for a Hearing Regarding Renewal of Facility Operating License Nos. NPF-9, NPF-17, NPF-35, and NPF-52 for an Additional 20-Year Period

The U.S. Nuclear Regulatory Commission (the Commission) is considering an application for the renewal of Operating License Nos. NPF-9, NPF-17, NPF-35, and NPF-52, which authorize Duke Energy Corporation to operate McGuire Nuclear Station, Units 1 and 2, and Catawba Nuclear Station, Units 1 and 2, at 3411 megawatts thermal. The renewed licenses would authorize the applicant to operate McGuire Nuclear Station, Units 1 and 2, and Catawba Nuclear Station, Units 1 and 2, for an additional 20 years beyond the period specified in the current licenses. The current operating licenses for McGuire Nuclear Station, Units 1 and 2, expire on June 12, 2021, and March 3, 2023, respectively. The current operating licenses for Catawba Nuclear Station, Units 1 and 2, expire on December 6, 2024, and February 24, 2026, respectively.

Duke Energy Corporation submitted an application to renew the operating licenses for McGuire, Units 1 and 2, and Catawba, Units 1 and 2, on June 13, 2001. A Notice of Receipt of Application, ``Duke Energy Corporation, McGuire, Units 1 and 2, and Catawba, Units 1 and 2; Notice of Receipt of Application for Renewal of Facility Operating License Nos. NPF-9, NPF-17, NPF-35, and NPF-52 for an Additional 20-Year Period,'' was published in the Federal Register on July 16, 2001 (66 FR 37072).

The Commission's staff has determined that Duke Energy Corporation has submitted information in accordance with 10 CFR 54.19, 54.21, 54.22, 54.23, and 51.53(c) that is complete and acceptable for docketing. The current Docket Nos. 50-369, 370, 413, and 414 for Operating License Nos. NPF-9, NPF-17, DPR-35, and DPR-52, respectively, will be retained. The docketing of the renewal application does not preclude requesting additional information as the review proceeds, nor does it predict whether the Commission will grant or deny the application.

Before issuance of each requested renewed license, the NRC will have made the findings required by the Atomic Energy Act of 1954, as amended (the Act), and the NRC's rules and regulations. In accordance with 10 CFR 54.29, the NRC will issue a renewed license on the basis of its review if it finds that actions have been identified and have been or will be taken with respect to (1) managing the effects of aging during the period of extended operation on the functionality of structures and components that have been identified as requiring aging management review, and (2) time-limited aging analyses that have been identified as requiring review, such that there is reasonable assurance that the activities authorized by the renewed license will continue to be conducted in accordance with the current licensing basis (CLB) and that any changes made to the plant's CLB comply with the Act and the Commission's regulations.

Additionally, in accordance with 10 CFR 51.95(c), the NRC will prepare an environmental impact statement that is a supplement to the Commission's NUREG-1437, ``Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants'' (May 1996). Pursuant to 10 CFR 51.26, and as part of the environmental scoping process, the staff intends to hold a public scoping meeting. Detailed information regarding this meeting will be included in a future Federal Register notice. The Commission also intends to hold public meetings to discuss the license renewal process and the schedule for conducting the review. The Commission will provide prior notice of these meetings. As discussed further herein, in the event that a hearing is held, issues that may be litigated will be confined to those pertinent to the foregoing.

By September 14, 2001, the applicant may file a request for a hearing, and any person whose interest may be affected by this proceeding and who wishes to participate as a party in the proceeding must file a written request for a hearing and a petition for leave to intervene with respect to the renewal of the licenses in accordance with the provisions of 10 CFR 2.714. Interested persons should consult a current copy of 10 CFR 2.714, which is available at the Commission's Public Document Room, 11555 Rockville Pike (first floor) Rockville, Maryland, and on the NRC Web site at http://www.nrc.gov (the Electronic Reading Room). If a request for a hearing or a petition for leave to intervene is filedby the above date, the Commission or an Atomic Safety and Licensing Board designated by the Commission or by the Chairman of the Atomic Safety and Licensing Board Panel will rule on the request(s) and/or petition(s), and the Secretary or the designated Atomic Safety and Licensing Board will issue a notice of hearing or an appropriate order. In the event that no request for a hearing or petition for leave to intervene is filedby the above date, the NRC may, upon completion of its evaluations and upon making the findings required under 10 CFR parts 54 and 51, renew the licenses without further notice.

As required by 10 CFR 2.714, a petition for leave to intervene shall set forth with particularity the interest of the petitioner in the proceeding and how that interest may be affected by the results of the proceeding, taking into consideration the limited scope of matters that may be considered pursuant to 10 CFR parts 54 and 51. The petition must specifically explain the

[[Page 42894]]

reasons why intervention should be permitted with particular reference to the following factors: (1) The nature of the petitioner's right under the Act to be made a party to the proceeding; (2) the nature and extent of the petitioner's property, financial, or other interest in the proceeding; and (3) the possible effect of any order that may be entered in the proceeding on the petitioner's interest. The petition must also identify the specific aspect(s) of the subject matter of the proceeding as to which petitioner wishes to intervene. Any person who has fileda petition for leave to intervene or who has been admitted as a party may amend the petition without requesting leave of the board up to 15 days before the first prehearing conference scheduled in the proceeding, but such an amended petition must satisfy the specificity requirements described above.

Not later than 15 days before the first prehearing conference scheduled in the proceeding, a petitioner shall file a supplement to the petition to intervene that must include a list of the contentions that the petitioner seeks to have litigated in the hearing. Each contention must consist of a specific statement of the issue of law or fact to be raised or controverted. In addition, the petitioner shall provide a brief explanation of the bases of each contention and a concise statement of the alleged facts or the expert opinion that supports the contention and on which the petitioner intends to rely in proving the contention at the hearing. The petitioner must also provide references to those specific sources and documents of which the petitioner is aware and on which the petitioner intends to rely to establish those facts or expert opinion. The petitioner must provide sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact. Contentions shall be limited to matters within the scope of the action under consideration. The contention must be one that, if proven, would entitle the petitioner to relief. A petitioner who fails to file such a supplement that satisfies these requirements with respect to at least one contention will not be permitted to participate as a party.

Those permitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene, and have the opportunity to participate fully in the conduct of the hearing, including the opportunity to present evidence and cross- examine witnesses.

Requests for a hearing and petitions for leave to intervene must be filedwith the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington DC 20555-0001, Attention: Rulemakings and Adjudications Staff, or may be delivered to the Commission's Public Document Room, 11555 Rockville Pike (first floor), Rockville, Maryland, 20855-2738, by the above date. A copy of the request for a hearing and the petition to intervene should also be sent to the Office of the General Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, and to Mr. Michael S. Tuckman, Executive Vice President, Nuclear Generation, Duke Energy Corporation, 526 South Church Street, PO Box 1006, Charlotte, NC 28201-1006.

Nontimely filings of petitions for leave to intervene, amended petitions, supplemental petitions, and/or requests for a hearing will not be entertained absent a determination by the Commission, the presiding officer, or the Atomic Safety and Licensing Board that the petition and/or request should be granted based upon a balancing of the factors specified in 10 CFR 2.714(a)(1)(i)-(v) and 2.714(d).

Detailed information about the license renewal process can be found under the nuclear reactors' icon of the NRC's Web page at http:// www.nrc.gov.

A copy of the application to renew the operating licenses for McGuire Nuclear Station, Units 1 and 2, and Catawba Nuclear Station, Units 1 and 2, is available for public inspection at the Commission's Public Document Room, 11555 Rockville Pike (first floor), Rockville, Maryland, 20855-2738, and on the NRC's Web page at http://www.nrc.gov. The staff has also verified that copies of the license renewal application for the McGuire and Catawba nuclear stations have been provided to the J. Murrey Atkins Library at the University of North Carolina, Charlotte, in Charlotte, North Carolina, and to the Rock Hill Public Library in Rock Hill, South Carolina.

Dated at Rockville, Maryland, the 8th day of August 2001.

For the Nuclear Regulatory Commission. Christopher I. Grimes, Chief, License Renewal and Standardization Branch, Division of Regulatory Improvement Programs, Office of Nuclear Reactor Regulation.

[FR Doc. 01-20535Filed8-14-01; 8:45 am]

BILLING CODE 7590-01-P

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT