Reports and guidance documents; availability, etc.: Maintenance rule baseline inspections; lessons learned,
FR, November 19, 1999 › Notices › Nuclear Regulatory Commission
Linked as:FR, November 19, 1999 › Notices › Nuclear Regulatory Commission
Linked as:Text
Federal Register: November 19, 1999 (Volume 64, Number 223)NoticesPage 63348From the Federal Register Online via GPO Access [wais.access.gpo.gov]
DOCID:fr19no99-104
NUCLEAR REGULATORY COMMISSION
Lessons Learned From Maintenance Rule Baseline Inspections
Availability of NUREG-1648
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of Availability. SUMMARY: The Nuclear Regulatory Commission announces the completion and availability of NUREG-1648, ``Lessons Learned From Maintenance Rule Baseline Inspections,'' dated October, 1999.
ADDRESSES: Copies of NUREG-1648 may be obtained from the Reproduction and Distribution Services Section, Office of the Chief Information Officer, U.S. Nuclear Regulatory Commission, Washington DC 20555-0001. Copies are also available electronically. See ``Electronic Access.'' which follows. A copy of the document is also available for inspection and/or copying for a fee in the NRC Public Document Room, 2120 L Street, NW. (Lower Level), Washington, DC 20555-0001.
FOR FURTHER INFORMATION CONTACT: Richard Correia, Division of Inspection Program Management, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001. Telephone: 301-415-1009.
SUPPLEMENTARY INFORMATION: On November 1, 1999, the NRC announced the availability of NUREG-1648, ``Lessons Learned From Maintenance Rule Baseline Inspections,'' dated October 1999. This NUREG report provides details concerning lessons learned from implementing the NRC's first risk-informed performance-based regulation, the maintenance rule,
NUREG-1648 is now available for use by licensees and other NRC staff. It supplements the lessons learned information previously found in NUREG-1526, ``Lessons Learned From Early Implementation of the Maintenance Rule at Nine Nuclear Power Plants,'' dated June, 1995.
The risk-informed, performance-based approach of implementing
Electronic Access
NUREG-1648 is also available electronically by visiting NRC's Public Web Site at (http://www.nrc.gov), choose the ``Nuclear Reactors'' page of the site and then choose the ``Maintenance Rule.'' The Maintenance Rule Home Page may also be accessed directly by using the uniform resource locator (URL) at (http://www.nrc.gov/NRR/mrule/ mrhome.htm). The user must ensure that the URL is typed exactly as shown because the Web server file name convention is case sensitive.
Small Business Regulatory Enforcement Fairness Act
In accordance with the Small Business Regulatory Enforcement Act of 1996, the NRC has determined that this action is not a major rule and has verified this determination with the Office of Information and Regulatory Affairs of the Office of Management and Budget.
Dated at Rockville, Maryland, this 1st day of November, 1999.
For the Nuclear Regulatory Commission. Bruce A. Boger, Director, Division of Inspection Program Management, Office of Nuclear Reactor Regulation.
FR Doc. 99-30227Filed11-18-99; 8:45 amBILLING CODE 7590-01-P
Sponsored links
ver las páginas en versión mobile | web
ver las páginas en versión mobile | web
© Copyright 2012, vLex. All Rights Reserved.
Contents in vLex United States
Explore vLex
For Professionals
For Partners
Company
Other documents:
Mike Golay Lets Guitar Do Talking and It s Quite Eloquent Indeed | Nhl Roundup | briefs | corps awards $49m contract to mandeville-based b&k construction | decreto 937 - sin titulo | sentencia nº 4254 de consiglio di stato, september 15, 2010 | Sentencia nº 1608 de Consiglio di Stato, March 28, 2008 | Sentencia nº 248019 de Corte de Apelaciones de Santiago Sala Segunda December 21 2009