Electricity export and import authorizations, permits, etc.: Dominion Energy Marketing, Inc.,
FR, July 18, 2006 › Notices › Energy Department
Linked as:FR, July 18, 2006 › Notices › Energy Department
Linked as:Text
Federal Register: July 18, 2006 (Volume 71, Number 137)NoticesPage 40711From the Federal Register Online via GPO Access [wais.access.gpo.gov]
DOCID:fr18jy06-46
DEPARTMENT OF ENERGY
OE Docket No. EA-291-AApplication To Export Electric Energy; Dominion Energy Marketing, Inc.
AGENCY: Office of Electricity Delivery and Energy Reliability, DOE.
ACTION: Notice of application.
SUMMARY: Dominion Energy Marketing, Inc. (DEMI) has applied to renew its authority to transmit electric energy from the United States to Canada pursuant to section 202(e) of the Federal Power Act.
DATES: Comments, protests or requests to intervene must be submitted on or before August 17, 2006.
ADDRESSES: Comments, protests or requests to intervene should be addressed as follows: Office of Electricity Delivery and Energy Reliability, Mail Code: OE-20, U.S. Department of Energy, 1000 Independence Avenue, SW., Washington, DC 20585-0350 (FAX 202-586-5860).
FOR FURTHER INFORMATION CONTACT: Steven Mintz (Program Office) 202-586- 9506 or Michael Skinker (Program Attorney) 202-586-2793.
SUPPLEMENTARY INFORMATION: Exports of electricity from the United States to a foreign country are regulated and require authorization under section 202(e) of the Federal Power Act (FPA) (16 U.S.C. 824a(e)).
On June 25, 2004, the Department of Energy (DOE) issued Order No. EA-291 authorizing DEMI to transmit electric energy from the United States to Canada as a power marketer. That Order expired on June 25, 2006.
On June 23, 2006, DEMI filed an application with DOE for renewal of the export authority contained in Order No. EA-297 for an additional five-year term and requested that if accepted, the renewal be effective as of June 26, 2006. DEMI does not own or control any transmission or distribution assets, nor does it have a franchised service area. The electric energy which DEMI proposes to export to Canada would be purchased from electric utilities and Federal power marketing agencies within the U.S.
DEMI will arrange for the delivery of exports to Canada over the international transmission facilities currently owned by Basin Electric Power Cooperative, Bonneville Power Administration, Eastern Maine Electric Cooperative, International Transmission Co., Joint Owners of the Highgate Project, Long Sault, Inc., Maine Electric Power Company, Maine Public Service Company, Minnesota Power, Inc., Minnkota Power Cooperative, Inc., New York Power Authority, Niagara Mohawk Power Corp., Northern States Power Company, and Vermont Electric Transmission Co.
The construction, operation, maintenance, and connection of each of the international transmission facilities to be utilized by DEMI has previously been authorized by a Presidential permit issued pursuant to Executive Order 10485, as amended.
Procedural Matters: Any person desiring to become a party to this proceeding or to be heard by filing comments or protests to this application should file a petition to intervene, comment or protest at the address provided above in accordance with Sec. Sec. 385.211 or 385.214 of the Federal Energy Regulatory Commission's Rules of Practice and Procedures (18 CFR 385.211, 385.214). Fifteen copies of each petition and protest should be filed with DOE on or before the date listed above.
Comments on the DEMI application to export electric energy to Canada should be clearly marked with Docket EA-291-A. Additional copies are to be filed directly with Michael C. Regulinski, Esq., Dominion Resources Services, Inc., 120 Tredegar Street, Richmond, VA 23219 and David Martin Connelly, Esquire, Bruder, Gentile and Marcoux, L.L.P., 1701 Pennsylvania Avenue, NW., Suite 900, Washington, DC 20006-5807.
A final decision will be made on this application after the environmental impacts have been evaluated pursuant to the National Environmental Policy Act of 1969, and a determination is made by the DOE that the proposed action will not adversely impact on the reliability of the U.S. electric power supply system.
Copies of this application will be made available, upon request, for public inspection and copying at the address provided above or by contacting Odessa Hopkins at Odessa.hopkins@hq.doe.gov.
Issued in Washington, DC, on July 12, 2006. Ellen Russell, Acting Director, Permitting and Siting, Office of Electricity Delivery and Energy Reliability. [FR Doc. E6-11335 Filed 7-17-06; 8:45 am]
BILLING CODE 6450-01-P
Sponsored links
ver las páginas en versión mobile | web
ver las páginas en versión mobile | web
© Copyright 2012, vLex. All Rights Reserved.
Contents in vLex United States
Explore vLex
For Professionals
For Partners
Company
Other documents:
REMINDER/Special Olympics and the City of Sacramento Team Together for Fall Sports Classic. | a comprehensive coverage of shorter-term developments and prospects for the precious metals markets. | Thriving in unpredictable times despite economic threats the BE Industrial/Service 100 have found inventive ways to... | Allconnect and Kansas City Power and Light Form Partnership Innovative KCP&L Connections Help... | decisión de tribunal primero de primera instancia en funciones de control lopna de sucre (extensión cumaná), de septemb... | Decisión de Tribunal Segundo de Primera Instancia de Sustanciación, Mediación y Ejecución del Nuevo Régime... | Decisión nº PJ0162009000490 de Tribunal Primero de Primera Instancia de Mediación y Sustanciación del Nuevo... | Decisión nº 1C-041709-09 de Tribunal Primero de Control Extensión Barlovento de Miranda, de May 04, 2009