Federal Acquisition Regulation; Improvement in Design-Build Construction Process

Federal Register, Volume 80 Issue 195 (Thursday, October 8, 2015)

Federal Register Volume 80, Number 195 (Thursday, October 8, 2015)

Proposed Rules

Pages 60833-60834

From the Federal Register Online via the Government Publishing Office www.gpo.gov

FR Doc No: 2015-25613

-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

GENERAL SERVICES ADMINISTRATION

NATIONAL AERONAUTICS AND SPACE ADMINISTRATION

48 CFR Part 36

FAR Case 2015-018; Docket No. 2015-0018; Sequence No. 1

RIN 9000-AN10

Federal Acquisition Regulation; Improvement in Design-Build Construction Process

AGENCIES: Department of Defense (DoD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA).

ACTION: Proposed rule.

-----------------------------------------------------------------------

SUMMARY: DoD, GSA, and NASA are proposing to amend the Federal Acquisition Regulation (FAR) to implement section 814 of the Carl Levin and Howard P. `Buck' McKeon National Defense Authorization Act for Fiscal Year 2015 that requires the head of the contracting activity to approve any determinations to select more than five offerors to submit phase-two proposals for a two-phase design-build construction acquisition that is valued at greater than $4 million.

DATES: Interested parties should submit written comments to the Regulatory Secretariat at one of the addresses shown below on or before December 7, 2015 to be considered in the formulation of a final rule.

ADDRESSES: Submit comments in response to FAR Case 2015-018 by any of the following methods:

Regulations.gov: http://www.regulations.gov. Submit comments via the Federal eRulemaking portal by searching for ``FAR Case 2015-018.'' Select the link ``Comment Now'' that corresponds with FAR Case 2015-018. Follow the instructions provided at the ``Comment Now'' screen. Please include your name, company name (if any), and ``FAR Case 2015-018'' on your attached document.

Mail: General Services Administration, Regulatory Secretariat (MVCB), ATTN: Ms. Flowers, 1800 F Street NW., 2nd Floor, Washington, DC 20405.

Instructions: Please submit comments only and cite FAR Case 2015-

018, in all correspondence related to this case. Comments received generally will be posted without change to http://www.regulations.gov, including any personal and/or business confidential information provided. To confirm receipt of your comment(s), please check www.regulations.gov, approximately two to three days after submission to verify posting (except allow 30 days for posting of comments submitted by mail).

FOR FURTHER INFORMATION CONTACT: Mr. Curtis E. Glover, Sr., Procurement Analyst, at 202-501-1448, for clarification of content. For information pertaining to status or publication schedules, contact the Regulatory Secretariat at 202-501-4755. Please cite FAR case 2015-018.

SUPPLEMENTARY INFORMATION:

  1. Background

    DoD, GSA, and NASA are proposing to amend the FAR to implement section 814 of the Carl Levin and Howard P. `Buck' McKeon National Defense Authorization Act for Fiscal Year 2015. Section 814 is entitled Improvement in Defense Design-Build Construction Process. Section 814 requires the head of the contracting activity, delegable to a level no lower than the senior contracting official, to approve any determinations to select more than five offerors to submit phase-two proposals for a two-phase design build construction acquisition that is valued at greater than $4 million.

  2. Discussion and Analysis

    This proposed rule does not change the maximum number of offerors, currently five, that may be selected to submit phase-two proposals without a contracting officer determination. However, for acquisitions valued above

    Page 60834

    $4 million, the determination must now have a higher level of approval for the contracting officer to select more than five offerors. A potential offeror may be more inclined to invest their pre-award efforts on solicitations where they have an increased chance of award.

  3. Executive Orders 12866 and 13563

    Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This is not a significant regulatory action and, therefore, was not subject to review under section 6(b) of E.O. 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.

  4. Regulatory Flexibility Act

    This change is not expected to have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq. Nevertheless, an Initial Regulatory Flexibility Analysis (IRFA) has been prepared, and is summarized as follows:

    This rule implements section 814 of the Carl Levin and Howard P. `Buck' McKeon National Defense Authorization Act for Fiscal Year 2015. Section 814 is entitled Improvement in Defense Design-Build Construction Process. Section 814 requires the head of the contracting activity, delegable to a level no lower than the senior contracting official, to approve any determinations to select more than five offerors to submit phase-two proposals for a two-phase design build construction acquisition that is valued at greater than $4 million.

    The number of design-build construction awards is not currently tracked by the Federal government's business systems. In Fiscal Year 2014, the Federal government awarded 3,666 construction awards to 2,239 unique small business vendors. It is unknown what percentage of these contracts involved design-build construction services.

    This rule does not impose new recordkeeping or reporting requirements. The new approval requirement for advancing more than five contractors to phase two of a two-phase design-build selection procedure only affects the internal procedures of the Government. For acquisitions valued over $4M, the head of the contracting activity (HCA) is required to now make a determination that it is in the best interest of the Government to select more than five offerors to proceed to phase two. Any burden caused by this rule is expected to be minimal and will not be any greater on small businesses than it is on large businesses.

    The rule does not duplicate, overlap, or conflict with any other Federal rules. No alternative approaches were considered. It is not anticipated that the proposed rule will have a significant economic impact on small entities.

    The Regulatory Secretariat has submitted a copy of the IRFA to the Chief Counsel for Advocacy of the Small Business Administration. A copy of the IRFA may be obtained from the Regulatory Secretariat. DoD, GSA, and NASA invite comments from small business concerns and other interested parties on the expected impact of this rule on small entities.

    DoD, GSA, and NASA will also consider comments from small entities concerning the existing regulations in subparts affected by the rule in accordance with 5 U.S.C. 610. Interested parties must submit such comments separately and should cite 5 U.S.C. 610 (FAR Case 2015-018), in correspondence.

  5. Paperwork Reduction Act

    The rule does not contain any information collection requirements that require the approval of the Office of Management and Budget under the Paperwork Reduction Act (44 U.S.C. chapter 35).

    List of Subject in 48 CFR Part 36

    Government procurement.

    William Clark,

    Director, Office of Government-wide Acquisition Policy, Office of Acquisition Policy, Office of Government-wide Policy.

    Therefore, DoD, GSA, and NASA propose amending 48 CFR part 36 as set forth below:

    PART 36--CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS

    0

    1. The authority citation for 48 CFR part 36 continues to read as follows:

      Authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 137; and 51 U.S.C. 20113.

      0

    2. Amend section 36.303-1 by revising paragraph (a)(4) to read as follows:

      36.303-1 Phase One.

      (a) * * *

      (4) A statement of the maximum number of offerors that will be selected to submit phase-two proposals. The maximum number specified in the solicitation shall not exceed five unless the contracting officer determines, for that particular solicitation, that a number greater than five is in the Government's interest and is consistent with the purposes and objectives of the two-phase design-build selection procedures. The contracting officer shall document this determination in the contract file. For acquisitions greater than $4 million, the determination shall be approved by the head of the contracting activity, delegable to a level no lower than the senior contracting official within the contracting activity.

      * * * * *

      FR Doc. 2015-25613 Filed 10-7-15; 8:45 am

      BILLING CODE 6820-EP-P