Preliminary Permit Applications, etc.:
FR, November 23, 2010 › Notices › Federal Energy Regulatory Commission
Linked as:FR, November 23, 2010 › Notices › Federal Energy Regulatory Commission
Linked as:Text
Federal Register: November 23, 2010 (Volume 75, Number 225)
Notices
Page 71427-71428
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
DOCID:fr23no10-52
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Project No. 13867-000
Clean River Power 11, LLC; Notice of Preliminary Permit
Application Accepted for Filing and Soliciting Comments, Motions To
Intervene, and Competing Applications
November 16, 2010.
On October 15, 2010, Clean River Power 11, LLC filed an application for
Page 71428
a preliminary permit, pursuant to section 4(f) of the Federal Power Act
(FPA), proposing to study the feasibility of the Swamp Creek
Hydroelectric Project (Swamp Creek project) to be located on Swamp
Creek in the vicinity of Glacier, in Whatcom County, Washington. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners' express permission.
The proposed project will consist of the following: (1) A 50-foot- long, 8-foot-high reinforced concrete diversion weir on Swamp Creek;
(2) a 45-foot-long, 15-foot-wide, 12-foot-high reinforced concrete intake structure adjacent to the weir with a trash rack, fish screen, and closure gate; (3) a 0.15-acre impoundment created by the weir; (4) a 5,200-foot-long, 3-foot-diameter steel penstock from the intake structure to the powerhouse; (5) a 60-foot-long, 40-foot-wide reinforced concrete powerhouse containing one horizontal impulse turbine with a capacity of 3.5 megawatts (MW); (6) a 40-foot-long, concrete and rip-rap-lined tailrace channel to return flows to Swamp
Creek; (7) a 4.6/55 kilovolt (kV) three stage step up transformer; (8) an approximately 6.75-mile-long, 55-kV transmission line which will tie into an undetermined interconnection; and (9) appurtenant facilities.
The estimated annual generation of the Swamp Creek project would be 15.0 gigawatt-hours.
Applicant Contact: Ramya Swaminthan, Clean River Power 11, LLC, 33
Commercial St., Gloucester, MA 01930; phone: (978) 283-2822.
FERC Contact: Ryan Hansen, (202) 502-8074.
Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet.
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's
Web site http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at http://www.ferc.gov/docs- filing/ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online
Support. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE., Washington, DC 20426.
More information about this project, including a copy of the application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-13867-000) in the docket number field to access the document. For assistance, contact FERC Online Support.
Kimberly D. Bose,
Secretary.
FR Doc. 2010-29443 Filed 11-22-10; 8:45 am
BILLING CODE 6717-01-P
Sponsored links
ver las páginas en versión mobile | web
ver las páginas en versión mobile | web
© Copyright 2012, vLex. All Rights Reserved.
Contents in vLex United States
Explore vLex
For Professionals
For Partners
Company
Other documents:
Coroner Organ Donations Help During Hard Time | Hound Hunting Equals Dog-Tired | Cd Reviews | Look Back in Feistiness | Sentencia nº 4252 de Consiglio di Stato July 29 2008 | Sentencia nº 451 de Consiglio di Stato, January 24, 2011 | Sentencia nº 4399 de Consiglio di Stato September 29 2010 | Sentencia nº 4667 de Consiglio di Stato, September 18, 2009