DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Docket No. EC99-54-000, et al.Power City Partners, L.P., et al.; Electric Rate and Corporate Regulation Filings
March 29, 1999.
Take notice that the following filings have been made with the Commission:
1. Power City Partners, L.P.
Docket No. EC99-54-000
Take notice that on March 23, 1999, Power City Partners, L.P. (Power City) tendered for filing with the Federal Energy Regulatory Commission an application for authorization to transfer facilities under Section 203 of the Federal Power Act, in connection with a sale- leaseback of facilities associated with Power City's generating facility in Massena, New York.
Comment date: April 22, 1999, in accordance with Standard Paragraph E at the end of this notice.
2. Citizens Power LLC and CL Power Sales Ten, L.L.C.
Docket No. EC99-56-000
Take notice that on March 23, 1999, Citizens Power LLC and CL Power Sales Ten, L.L.C. filedan application for an order authorizing the proposed sale of Citizens Power LLC's 25% equity interest in CL Power Sales Ten, L.L.C. to W. John Fair.
Comment date: April 22, 1999, in accordance with Standard Paragraph E at the end of this notice.
3. Pacific Gas and Electric Company
Docket No. EL98-46-002
Take notice that on March 22, 1999, Pacific Gas and Electric Company (PG&E) tendered for filing a form of Interconnection Agreement Between Pacific Gas and Electric Company and Laguna Irrigation District (Agreement), replacing in its entirety the form submitted to the Commission on December 1, 1998. This amended form of the Agreement revises some minor typographical errors in the draft form previously submitted. PG&E's December 1, 1998 filing was made pursuant to a ``Proposed Order Directing Interconnection and Establishing Further Procedures,'' issued in this case on September 16, 1998 (Proposed Order).
Copies of PG&E's filing have been served upon Laguna and all other parties to this proceeding.
Comment date: April 21, 1999, in accordance with Standard Paragraph E at the end of this notice.
4. Flathead Electric Cooperative, Inc.
Docket No. EL99-48-000
Take notice that on March 22, 1999, Flathead Electric Cooperative, Inc. tendered for filing a request for a disclaimer of jurisdiction that it is not a public utility under the Federal Power Act and a waiver of the reciprocity requirement, or in the alternative, a waiver of the requirements of Order Nos. 888 and 889 and certain regulations.
Comment date: April 21, 1999, in accordance with Standard Paragraph E at the end of this notice.
5. Advantage Energy, Inc.
Docket No. ER97-2758-005
Take notice that on March 24, 1999, the above-mentioned power marketer fileda quarterly report with the Commission in the above- mentioned proceeding for information only. This filing is available for public inspection and copying in the Public Reference Room or on the internet at www.ferc.fed.us/ online/rims.htm for viewing and downloading (call 202-208-2222 for assistance).
6. Avista Corporation
Docket No. ER99-55-000
Take notice that on March 24, 1999, Avista Corporation (Avista Corp.), refiled the Revised Ancillary Services Market Study, and explanatory letter, filedon March 15, 1999, in this docket, to reflect both public and confidential versions of the material.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
7. Western Resources, Inc.
Docket No. ER99-1399-000
Take notice that on March 24, 1999, Western Resources, Inc., (Western Resources), tendered for filing an unbundling of the demand and energy charges under the electric interconnection agreement with the City of McPherson, Kansas, Board of Public Utilities.
Western Resources requests waiver of the Commission's notice requirements to the extent necessary to permit the effective date of February 6, 1997.
Copies of the filing were served upon McPherson and the Kansas Corporation Commission.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
8. Tenaska Frontier Partners, Ltd.
Docket No. ER99-2219-000
Take notice that on March 22, 1999, the above-referenced public utility filedtheir quarterly transaction report for the quarter ending December 31, 1998.
Comment date: April 12, 1999, in accordance with Standard Paragraph E at the end of this notice.
9. Northeast Utilities Service
Docket No. ER99-2236-000
Take notice that on March 24, 1999, Northeast Utilities Service Company (NUSCO), tendered for filing a Service Agreement with Bangor Hydro-Electric Company (BHE) under the NU System Companies' System Power Sales/Exchange Tariff No. 6.
NUSCO states that a copy of this filing has been mailed to BHE.
NUSCO requests that the Service Agreement become effective February 25, 1999.
[Page 16439]
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
10. New England Power Company
Docket No. ER99-2237-000
Take notice that on March 24, 1999, New England Power Company (NEP), tendered for filing Service Agreements with Sithe Power Marketing, Inc., for service under NEP's FERC Electric Tariffs, Original Volumes Nos. 6, 10, and 11.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
11. Florida Power & Light Company
Docket No. ER99-2238-000
Take notice that on March 24, 1999, Florida Power & Light Company (FPL), tendered for filing proposed service agreements with Avista Energy, Inc., for Short-Term Firm and Non-Firm transmission service under FPL's Open Access Transmission Tariff.
FPL requests that the proposed service agreements be permitted to become effective on March 16, 1999.
FPL states that this filing is in accordance with Part 35 of the Commission's Regulations.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
12. Cambridge Electric Light Company; Commonwealth Electric Company
Docket No. ER99-2239-000
Take notice that on March 24, 1999, Cambridge Electric Light Company and Commonwealth Electric Company provided notice to the Commission that their open access transmission tariffs shall be considered modified by adopting the North American Electric Reliability Council Transmission Loading Relief Alternative Transmission Tariff Amendment.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
13. Florida Keys Electric Cooperative Association, Inc.
Docket No. ER99-2240-000
Take notice that on March 24, 1999, Florida Keys Electric Cooperative Association, Inc., tendered for filing a revised rate for non-firm transmission service provided to the City Electric System, Key West, Florida in accordance with the terms and conditions of the Long- Term Joint Investment Transmission Agreement between the Parties.
A copy of this filing has been served on CES and the Florida Public Service Commissioner.
FKEC respectfully requests an effective date for the revised non- firm transmission rate of April 1, 1999.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
14. California Independent System Operator Corporation
Docket No. ER99-2241-000
Take notice that on March 24, 1999, the California Independent System Operator Corporation (ISO), tendered for filing a Scheduling Coordinator Agreement (SCA) between the ISO and the Department of Water and Power of the City of Los Angeles for acceptance by the Commission.
The ISO is requesting a waiver of the 60-day prior notice requirement to allow the SCA to be made effective as of March 22, 1999.
The ISO states that this filing has been served on the Department of Water and Power of the City of Los Angeles and the California Public Utilities Commission.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
15. West Texas Utilities Company
Docket No. ER99-2242-000
Take notice that on March 24, 1999, West Texas Utilities Company (WTU), tendered for filing a Letter Agreement between WTU and the City of Coleman, Texas (Coleman). Under the agreement, WTU will make additional energy available to Coleman during the on-peak hours of the summer months of 1999, pursuant to a Supplemental Sales Agreement between WTU and Coleman, previously filedwith the Commission.
WTU requests an effective date of June 1, 1999.
WTU states that copies of this filing have been served on Coleman and the Public Utility Commission of Texas.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
16. Delmarva Power & Light Company
Docket No. ER99-2243-000
Take notice that on March 24, 1999, Delmarva Power & Light Company (Delmarva), tendered for filing an executed umbrella service agreement with PP&L EnergyPlus Co., under Delmarva's market rate sales tariff.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
17. Niagara Mohawk Power Corporation
Docket No. ER99-2244-000
Take notice that on March 24, 1999, Niagara Mohawk Power Corporation (Niagara Mohawk), tendered for filing an amendment to Niagara Mohawk's open access transmission tariff. The amendment consists of a new Attachment J--Form of Service Agreement For Retail Transmission Service.
Niagara Mohawk requests an effective date of April 2, 1999, for the amendment.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
18. Central Illinois Light Company
Docket No. ER99-2245-000
Take notice that on March 24, 1999, Central Illinois Light Company (CILCO), 300 Liberty Street, Peoria, Illinois 61202, tendered for filing with the Commission an Index of Customers under its Coordination Sales Tariff and one service agreement with one new customer, DukeSolutions, Inc. One customer has asked CILCO to terminate their service agreement, K N Energy, Inc.
CILCO requested an effective date of March 22, 1999.
Copies of the filing were served on the affected customers and the Illinois Commerce Commission.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
19. Central Illinois Light Company
Docket No. ER99-2246-000
Take notice that on March 24, 1999, Central Illinois Light Company (CILCO), 300 Liberty Street, Peoria, Illinois 61202, tendered for filing with the Commission an Index of Customers under its Market Rate Power Sales Tariff and one service agreement with one new customer, DukeSolutions, Inc.
CILCO requested an effective date of March 22, 1999.
Copies of the filing were served on the affected customer and the Illinois Commerce Commission.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
20. Avista Corporation
Docket No. ER99-2247-000
Take notice that on March 24, 1999, Avista Corporation, tendered for filing with the Federal Energy Regulatory Commission pursuant to 18 CFR Section 35.13, a Certificate of Concurrence in Puget Sound Energy, Inc.'s filing regarding the 1998-99Operating Procedures under the Pacific Northwest Coordination Agreement Docket No. ER99-2026-000, previously noticed on March 5, 1999.
[Page 16440]
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
21. Northern States Power Company (Minnesota); Northern States Power Company (Wisconsin)
Docket No. ER99-2248-000
Take notice that on March 24, 1999, Northern States Power Company (Minnesota) and Northern States Power Company (Wisconsin) (jointly NSP), tendered for filing a Firm Point-to-Point Transmission Service Agreement between NSP and Madison Gas & Electric Company.
NSP requests that the Commission accept both the agreements effective July 1, 1999, and requests waiver of the Commission's notice requirements in order for the agreements to be accepted for filing on the date requested.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
22. Central Power and Light Company; West Texas Utilities Company; Public Service Company of Oklahoma; Southwestern Electric Power Co.
Docket No. ER99-2249-000
Take notice that on March 24, 1999, Central Power and Light Company, West Texas Utilities Company, Public Service Company of Oklahoma and Southwestern Electric Power Company (collectively, the CSW Operating Companies) tendered for filing service agreements under which the CSW Operating Companies will provide transmission and ancillary services to Cargill-Alliant, LLC (Cargill) in accordance with the CSW Operating Companies' open access transmission service tariff.
The CSW Operating Companies state that a copy of the filing has been served on Cargill.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
23. Alliant Energy Corporate Services, Inc.
Docket No. ER99-2250-000
Take notice that on March 24, 1999, Alliant Energy Corporate Services, Inc., tendered for filing an executed Form of Service Agreement for Long-Term Firm Point-to-Point Transmission Service. The transmission customer is Wisconsin Power and Light Company an Alliant Energy subsidiary.
Alliant Energy Corporate Services, Inc., requests an effective date of January 1, 1999, and accordingly, seeks waiver of the Commission's notice requirements.
A copy of this filing has been served upon the Illinois Commerce Commission, the Minnesota Public Utilities Commission, the Iowa Department of Commerce, and the Public Service Commission of Wisconsin.
Comment date: April 13, 1999, in accordance with Standard Paragraph E at the end of this notice.
24. Consolidated Edison Company of New York, Inc.; Orange and Rockland Utilities, Inc.; Consolidated Edison Company of New York, Inc. and Orange and Rockland Utilities, Inc.
Docket No. ER99-2251-000, ER99-2252-000, EC98-62-000
Take notice that on March 22, 1999, Consolidated Edison Company of New York, Inc. and Orange and Rockland Utilities, Inc. tendered for filing proposed amendments to their existing market-based rate tariffs to enable them to sell power at cost-based rates in the wholesale market and to comply with mitigation measures approved by the Commission in Docket No. EC98-62-000.
Comment date: April 12, 1999, in accordance with Standard Paragraph E at the end of this notice.
Standard Paragraphs
E. Any person desiring to be heard or to protest such filing should file a motion to intervene or protest with the Federal Energy Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426, in accordance with Rules 211 and 214 of the Commission's Rules of Practice and Procedure (18 CFR 385.211 and 385.214). All such motions or protests should be filedon or before the comment date. Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a motion to intervene. Copies of these filings are on file with the Commission and are available for public inspection. This filing may also be viewed on the Internet at http://www.ferc.fed.us/online/rims.htm (call 202- 208-2222 for assistance). David P. Boergers, Secretary.
FR Doc. 99-8261Filed4-2-99; 8:45 amBILLING CODE 6717-01-P
Sponsored links
ver las páginas en versión mobile | web
ver las páginas en versión mobile | web
© Copyright 2012, vLex. All Rights Reserved.
Contents in vLex United States
Explore vLex
For Professionals
For Partners
Company
Other documents:
AML Communications Reports Third Quarter Results. | C&W inks two-property $104m New Jersey sale. | Tackling the minority achievement gap: New Jersey: Lawrence Township Public Schools. | News media incentives coverage of government and the growth of government. | decisión de tribunal segundo de control, audiencia y medidas con competencia en materia de violencia contra la mujer de monagas, de mar... | Decisión nº --- de Juzgado Cuarto de los Municipios Maracaibo Jesús Enrique Lossada y San Francisco de Zuli... | Decisión de Tribunal Segundo de Primera Instancia en Funciones de Control de Tachira (Extensión San Antoni... | decisión de tribunal segundo de control de monagas de september 16 2010