64194
Federal Register / Vol. 86, No. 219 / Wednesday, November 17, 2021 / Notices
the schedule will be made as
appropriate.
Issue Scoping Document 1 for
comments—December 2021
Request Additional Information (if
necessary)—February 2021
Issue Scoping Document 2—March 2021
Issue Notice of Ready for Environmental
Analysis—March 2021
Dated: November 10, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–25081 Filed 11–16–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–2289–012;
ER10–2564–012; ER10–2600–012.
Applicants: UNS Electric, Inc.,
Tucson Electric Power Company,
UniSource Energy Develop.m.ent
Company.
Description: Notice of Change in
Status to Reflect Participation in Energy
Imbalance Market of Tucson Electric
Power Company, et al.
Filed Date: 11/10/21.
Accession Number: 20211110–5199.
Comment Date: 5 p.m. ET 12/1/21.
Docket Numbers: ER21–2217–002.
Applicants: Lincoln Land Wind, LLC.
Description: Notice of Non-Material
Change in Status of Lincoln Land Wind,
LLC.
Filed Date: 11/10/21.
Accession Number: 20211110–5162.
Comment Date: 5 p.m. ET 12/1/21.
Docket Numbers: ER21–2348–001.
Applicants: Midcontinent
Independent System Operator, Inc.,
Michigan Public Power Agency.
Description: ALJ Settlement:
Midcontinent Independent System
Operator, Inc. submits tariff filing per
385.602: 2021–10–25_MPPA Revenue
Requirement Compliance Filing to be
effective N/A.
Filed Date: 10/25/21.
Accession Number: 20211025–5062.
Comment Date: 5 p.m. ET 12/1/21.
Docket Numbers: ER22–377–000.
Applicants: Florida Power & Light
Company.
Description: § 205(d) Rate Filing: FPL
& Alabama Power Facility Construction
Agreement for Affected System Project
to be effective 11/11/2021.
Filed Date: 11/10/21.
Accession Number: 20211110–5001.
Comment Date: 5 p.m. ET 12/1/21.
Docket Numbers: ER22–378–000.
Applicants: ISO New England Inc.,
New England Power Pool Participants
Committee.
Description: ISO New England Inc.
submits Installed Capacity Requirement,
Hydro Quebec Interconnection
Capability Credits and Related Values
for the 2025/2026 Capacity Commitment
Period.
Filed Date: 11/9/21.
Accession Number: 20211109–5227.
Comment Date: 5 p.m. ET 11/30/21.
Docket Numbers: ER22–379–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing:
Revisions to Implement Effective Load
Carrying Capability Methodology to be
effective 2/15/2022.
Filed Date: 11/10/21.
Accession Number: 20211110–5076.
Comment Date: 5 p.m. ET 12/1/21.
Docket Numbers: ER22–380–000.
Applicants: Avista Corporation.
Description: Tariff Amendment:
Avista Corp Cancellation of RS T1158
NorthernGrid Funding Agmt to be
effective 12/31/2021.
Filed Date: 11/10/21.
Accession Number: 20211110–5079.
Comment Date: 5 p.m. ET 12/1/21.
Docket Numbers: ER22–381–000.
Applicants: Dunns Bridge Solar
Center, LLC.
Description: Baseline eTariff Filing:
Dunns Bridge Solar Center, LLC
Application for MBR Authority to be
effective 1/10/2022.
Filed Date: 11/10/21.
Accession Number: 20211110–5090.
Comment Date: 5 p.m. ET 12/1/21.
Docket Numbers: ER22–382–000.
Applicants: American Electric Power
Service Corporation, Indiana Michigan
Power Company, PJM Interconnection,
L.L.C.
Description: §205(d) Rate Filing:
American Electric Power Service
Corporation submits tariff filing per
35.13(a)(2)(iii: AEP submits one FA with
IMPA re: SA No. 1436 to be effective 1/
10/2022.
Filed Date: 11/10/21.
Accession Number: 20211110–5099.
Comment Date: 5 p.m. ET 12/1/21.
Docket Numbers: ER22–383–000.
Applicants: Northern States Power
Company, a Minnesota corporation.
Description: § 205(d) Rate Filing:
2021–11–10 Huntley-Wilmarth-CMA–
657–0.1.0 to be effective 11/10/2021.
Filed Date: 11/10/21.
Accession Number: 20211110–5113.
Comment Date: 5 p.m. ET 12/1/21.
Take notice that the Commission
received the following electric securities
filings:
Docket Numbers: ES21–69–000.
Applicants: Allegheny Generating
Company.
Description: Supplement to
Application Under Section 204 of the
Federal Power Act for Authorization to
Issue Securities of Allegheny Generating
Company.
Filed Date: 11/9/21.
Accession Number: 20211109–5128.
Comment Date: 5 p.m. ET 11/30/21.
Docket Numbers: ES21–70–000.
Applicants: Jersey Central Power &
Light Company.
Description: Supplement to
Application Under Section 204 of the
Federal Power Act for Authorization to
Issue Securities of Jersey Central Power
& Light Company.
Filed Date: 11/9/21.
Accession Number: 20211109–5132.
Comment Date: 5 p.m. ET 11/30/21.
Docket Numbers: ES21–71–000.
Applicants: Mid-Atlantic Interstate
Transmission, LLC.
Description: Supplement to
Application Under Section 204 of the
Federal Power Act for Authorization to
Issue Securities of Mid-Atlantic
Interstate Transmission, LLC.
Filed Date: 11/9/21.
Accession Number: 20211109–5129.
Comment Date: 5 p.m. ET 11/30/21.
Docket Numbers: ES21–72–000.
Applicants: Metropolitan Edison
Company.
Description: Supplement to
Application Under Section 204 of the
Federal Power Act for Authorization to
Issue Securities of Metropolitan Edison
Company.
Filed Date: 11/9/21.
Accession Number: 20211109–5133.
Comment Date: 5 p.m. ET 11/30/21.
Docket Numbers: ES21–73–000.
Applicants: Monongahela Power
Company.
Description: Supplement to
Application Under Section 204 of the
Federal Power Act for Authorization to
Issue Securities of Monongahela Power
Company.
Filed Date: 11/9/21.
Accession Number: 20211109–5134.
Comment Date: 5 p.m. ET 11/30/21.
Docket Numbers: ES21–74–000.
Applicants: Pennsylvania Power
Company.
Description: Supplement to
Application Under Section 204 of the
Federal Power Act for Authorization to
Issue Securities of Pennsylvania Power
Company.
Filed Date: 11/9/21.
VerDate Sep<11>2014 17:11 Nov 16, 2021 Jkt 256001 PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 E:\FR\FM\17NON1.SGM 17NON1
khammond on DSKJM1Z7X2PROD with NOTICES
64195
Federal Register / Vol. 86, No. 219 / Wednesday, November 17, 2021 / Notices
Accession Number: 20211109–5141.
Comment Date: 5 p.m. ET 11/30/21.
Docket Numbers: ES21–75–000.
Applicants: Potomac Edison
Company.
Description: Supplement to
Application Under Section 204 of the
Federal Power Act for Authorization to
Issue Securities of Potomac Edison
Company.
Filed Date: 11/9/21.
Accession Number: 20211109–5144.
Comment Date: 5 p.m. ET 11/30/21.
Docket Numbers: ES21–76–000.
Applicants: West Penn Power
Company.
Description: Supplement to
Application Under Section 204 of the
Federal Power Act for Authorization to
Issue Securities of West Penn Power
Company.
Filed Date: 11/9/21.
Accession Number: 20211109–5147.
Comment Date: 5 p.m. ET 11/30/21.
Docket Numbers: ES21–77–000.
Applicants: Trans-Allegheny
Interstate Line Company.
Description: Supplement to
Application Under Section 204 of the
Federal Power Act for Authorization to
Issue Securities of Trans-Allegheny
Interstate Line Company.
Filed Date: 11/9/21.
Accession Number: 20211109–5162.
Comment Date: 5 p.m. ET 11/30/21.
Docket Numbers: ES21–78–000.
Applicants: Pennsylvania Electric
Company.
Description: Supplement to
Application Under Section 204 of the
Federal Power Act for Authorization to
Issue Securities of Pennsylvania Electric
Company.
Filed Date: 11/9/21.
Accession Number: 20211109–5161.
Comment Date: 5 p.m. ET 11/30/21.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: http://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: November 10, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021–25056 Filed 11–16–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP14–517–001]
Golden Pass Terminal, LLC; Notice of
Scoping Period Requesting Comments
on Environmental Issues for the
Proposed Golden Pass LNG Export
Variance Request No. 15 Amendment
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental document, that will
discuss the environmental impacts of
the Golden Pass LNG Export Variance
Request No. 15 Amendment
(Amendment), involving an increase to
traffic volumes and work week and
work hour limits by Golden Pass
Terminal, LLC (Golden Pass), in
Jefferson County, Texas. If authorized,
the Amendment would increase the
workforce numbers, amount of traffic
volume, and work week/hour limits that
were not reviewed during preparation of
the final Environmental Impact
Statement (EIS) for the Golden Pass LNG
Export Project (Docket Nos. CP14–517–
000 and CP14–518–000), which the
Commission authorized on December
21, 2016. Golden Pass proposed
Amendment would increase
construction to 24-hour-day and 7 days
a week at the Golden Pass LNG Export
Terminal. The Commission will use this
environmental document in its
decision-making process to determine
whether the project Amendment is in
the public convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies regarding the
Amendment. As part of the National
Environmental Policy Act (NEPA)
review process, the Commission takes
into account concerns the public may
have about proposals and the
environmental impacts that could result
from its action whenever it considers
the issuance of a Certificate of Public
Convenience and Necessity. This
gathering of public input is referred to
as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the environmental document on the
important environmental issues.
Additional information about the
Commission’s NEPA process is
described below in the NEPA Process
and Environmental Document section of
this notice.
By this notice, the Commission
requests public comments on the scope
of issues to address in the
environmental document. To ensure
that your comments are timely and
properly recorded, please submit your
comments so that the Commission
receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on
December 10, 2021. Comments may be
submitted in written form. Further
details on how to submit comments are
provided in the Public Participation
section of this notice.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
Your input will help the Commission
staff determine what issues they need to
evaluate in the environmental
document. Commission staff will
consider all written comments during
the preparation of the environmental
document.
If you submitted comments on this
project Amendment to the Commission
before the opening of this docket on
November 3, 2021, you will need to file
those comments in Docket No. CP14–
517–001 to ensure they are considered
as part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project Amendment.
State and local government
representatives should notify their
constituents of this proposed project
Amendment and encourage them to
comment on their areas of concern.
Public Participation
There are three methods you can use
to submit your comments to the
Commission. Please carefully follow
these instructions so that your
comments are properly recorded. The
Commission encourages electronic filing
of comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. Using
eComment is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. With
eFiling, you can provide comments in a
variety of formats by attaching them as
VerDate Sep<11>2014 17:11 Nov 16, 2021 Jkt 256001 PO 00000 Frm 00019 Fmt 4703 Sfmt 4703 E:\FR\FM\17NON1.SGM 17NON1
khammond on DSKJM1Z7X2PROD with NOTICES

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT