Drawbridge Operation Regulation; Willamette River, Portland, OR

Federal Register, Volume 80 Issue 95 (Monday, May 18, 2015)

Federal Register Volume 80, Number 95 (Monday, May 18, 2015)

Rules and Regulations

Pages 28185-28186

From the Federal Register Online via the Government Publishing Office www.gpo.gov

FR Doc No: 2015-11831

-----------------------------------------------------------------------

DEPARTMENT OF HOMELAND SECURITY

Coast Guard

33 CFR Part 117

Docket No. USCG-2015-0415

Drawbridge Operation Regulation; Willamette River, Portland, OR

AGENCY: Coast Guard, DHS.

ACTION: Notice of deviation from drawbridge regulation.

-----------------------------------------------------------------------

SUMMARY: The Coast Guard has issued a temporary deviation from the operating schedule that governs the upper deck of the Steel Bridge, mile 12.1, and the Burnside Bridge, mile 12.4, both crossing the Willamette River, at Portland, OR. The deviation is necessary to accommodate the route of the annual Rose Festival Parade event, which crosses the Steel Bridge and Burnside Bridge. This deviation allows the upper deck of the Steel Bridge and Burnside Bridge to remain in the closed-to-navigation position and need not open for marine traffic to allow for the safe movement of event participants and cleanup crew.

DATES: This deviation is effective from 7 a.m. to 2 p.m. on June 6, 2015.

ADDRESSES: The docket for this deviation, USCG-2015-0415 is

Page 28186

available at http://www.regulations.gov. Type the docket number in the ``SEARCH'' box and click ``SEARCH.'' Click on Open Docket Folder on the line associated with this deviation. You may also visit the Docket Management Facility in Room W12-140 on the ground floor of the Department of Transportation West Building, 1200 New Jersey Avenue SE., Washington, DC 20590, between 9 a.m. and 5 p.m., Monday through Friday, except Federal holidays.

FOR FURTHER INFORMATION CONTACT: If you have questions on this temporary deviation, call or email Mr. Steven Fischer, Bridge Administrator, Thirteenth Coast Guard District; telephone 206-220-7282, email d13-pf-d13bridges@uscg.mil. If you have questions on viewing the docket, call Cheryl Collins, Program Manager, Docket Operations, telephone 202-366-9826.

SUPPLEMENTARY INFORMATION: TriMet Public Transit and Multnomah County have requested that the upper deck of the Steel Bridge and the Burnside Bridge remain in the closed-to-navigation position to accommodate the annual Rose Festival Parade event. The Steel Bridge, mile 12.1, and the Burnside Bridge, mile 12.4, both cross the Willamette River.

The Steel Bridge is a double-deck lift bridge with a lower lift deck and an upper lift deck which operate independent of each other. When both decks are in the down position the bridge provides 26 feet of vertical clearance. When the lower deck is in the up position, the bridge provides 71 feet of vertical clearance. This deviation does not affect the operating schedule of the lower deck which opens on signal.

The normal operating schedule for the upper deck of the Steel Bridge operates in accordance with 33 CFR 117.897(c)(3)(ii) which states from 8 a.m. to 5 p.m. Monday through Friday one hour advance notice shall be given for draw openings, and at all other times two hours advance notice shall be given to obtain an opening.

The Burnside Bridge provides a vertical clearance of 64 feet in the closed-to-navigation position. The normal operating schedule for the Burnside Bridge operates in accordance with 33 CFR 117.897(c)(3)(iii) which states from 8 a.m. to 5 p.m. Monday through Friday, one hour's notice shall be given for draw openings. At all other times, two hours notice is required. The Steel Bridge and Burnside Bridge clearances are above Columbia River Datum 0.0.

The deviation period is from 7 a.m. to 2 p.m. on June 6, 2015 to accommodate the route of the annual Rose Festival Parade event. The deviation allows the upper deck of the Steel Bridge, mile 12.1, and the Burnside Bridge, mile 12.4, both crossing the Willamette River, to remain in the closed-to-navigation position and need not open for maritime traffic from 7 a.m. to 2 p.m. on June 6, 2015. Waterway usage on this part of the Willamette River includes vessels ranging from commercial tug and barge to small pleasure craft.

Vessels able to pass through the Steel Bridge and Burnside Bridge in the closed positions may do so at anytime. The bridges will be able to open for emergencies and there is no immediate alternate route for vessels to pass. The Coast Guard will also inform the users of the waterways through our Local and Broadcast Notices to Mariners of the change in operating schedule for the bridges so that vessels can arrange their transits to minimize any impact caused by the temporary deviation.

In accordance with 33 CFR 117.35(e), the drawbridge must return to its regular operating schedule immediately at the end of the designated time period. This deviation from the operating regulations is authorized under 33 CFR 117.35.

Dated: May 12, 2015.

Steven M Fischer,

Bridge Administrator, Thirteenth Coast Guard District.

FR Doc. 2015-11831 Filed 5-15-15; 8:45 am

BILLING CODE 9110-04-P