Applications, hearings, determinations, etc.: NorAm Gas Transmission Co.,

[Federal Register: November 10, 1998 (Volume 63, Number 217)]

[Notices]

[Page 63040-63041]

From the Federal Register Online via GPO Access [wais.access.gpo.gov]

[DOCID:fr10no98-60]

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP99-42-000]

NorAm Gas Transmission Company; Notice of Request Under Blanket Authorization

November 4, 1998.

Take notice that on October 29, 1998, NorAm Gas Transmission Company (Applicant), 525 Milam Street, P.O. Box 21734, Shreveport, Louisiana, 71151, filedin Docket No. CP99-42-000 a request pursuant to Sections 157.205 and 157.211 of the Commission's Regulations under the Natural Gas Act (18 CFR 157.205 and 157.211) for approval to construct and operate a new delivery tap for service to ARKLA, a division of NorAm Energy Corporation and an affiliate of Applicant, under Applicant's blanket certificate issued in Docket Nos. CP82-384-000 and CP82-384-001, pursuant to Section 7(c) of the Natural Gas Act (NGA), all as more fully set forth in the request which is on file

[[Page 63041]]

with the Commission and open to public inspection.

Applicant proposes to construct and operate an additional two-inch delivery tap and first-cut regulator to render service for ARKLA located on Applicant's Line No. BT-14 in Faulkner County, Arkansas. Applicant asserts that the volumes of natural gas to be delivered at the proposed tap, up to 9,000 Dth per year and 30 Dth on a peak day, are within the certificated entitlement of ARKLA. Applicant states that ARKLA will construct, at its cost, a two-inch meter station and convey ownership to Applicant. Applicant further asserts that it has sufficient capacity to accomplish the deliveries without detriment to Applicant's other customers. Applicant indicates that the total cost of construction of the proposed facility is estimated to be $2,250, which sum ARKLA will reimburse Applicant.

Any person or the Commission's Staff may, within 45 days of the issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission's Rules of Practice and Procedure (18 CFR 385.214), a motion to intervene and pursuant to Section 157.205 of the regulations under the Natural Gas Act (18 CFR 157.205), a protest to the request. If no protest is filedwithin the time allowed therefor, the proposed activities shall be deemed to be authorized effective the day after the time allowed for filing a protest. If a protest is filed and not withdrawn 30 days after the time allowed for filing a protest, the instant request shall be treated as an application for authorization pursuant to Section 7 of the Natural Gas Act. Linwood A. Watson, Jr., Acting Secretary.

[FR Doc. 98-30018Filed11-9-98; 8:45 am]

BILLING CODE 6717-01-M