Kansas Regulatory Program,

[Federal Register: January 23, 2008 (Volume 73, Number 15)]

[Proposed Rules]

[Page 3894-3898]

From the Federal Register Online via GPO Access [wais.access.gpo.gov]

[DOCID:fr23ja08-17]

DEPARTMENT OF THE INTERIOR

Office of Surface Mining Reclamation and Enforcement

30 CFR Part 916

[Docket No. OSM-2008-0001; Sats No. KS-024-FOR]

Kansas Regulatory Program

AGENCY: Office of Surface Mining Reclamation and Enforcement, Interior.

ACTION: Proposed rule; public comment period and opportunity for public hearing on proposed amendment.

SUMMARY: We, the Office of Surface Mining Reclamation and Enforcement (OSM), are announcing receipt of a proposed amendment to the Kansas regulatory program (Kansas program) under the Surface Mining Control and Reclamation Act of 1977 (SMCRA or the Act). Kansas proposes revisions to its 2002 Kansas Revegetation Guidelines and its Normal Husbandry Practices. Kansas intends to update obsolete information used in determining the forage production success standard for warm season native grasses. Kansas also proposes to update their normal husbandry practices to increase clarity and to update references to other Agencies technical guidelines. These documents give the times and locations that the Kansas programs and proposed amendments to that program are available for your inspection, the comment period during which you may submit written comments on the amendments, and the procedures that we will follow for the public hearing, if one is requested.

DATES: We will accept written comments on this amendment until 4 p.m., c.d.t., February 22, 2008. If requested, we will hold a public hearing on the amendment on February 19, 2008. We will accept requests to speak at a hearing until 4 p.m., c.d.t. on February 7, 2008.

ADDRESSES: You may submit comments, identified by Docket No. OSM-2008- 0001, by any of the following methods:

Mail/Hand Delivery: Alfred L. Clayborne, Director, Tulsa Field Office, Office of Surface Mining Reclamation and Enforcement, 1645 South 101 St East Avenue, Tulsa, Oklahoma 74128.

Federal eRulemaking Portal: http://www.regulations.gov.

The proposed rule has been assigned Docket ID: OSM-2008-0001. If you would like to submit comments through the Federal eRulemaking Portal, go to http://www.regulations.gov and do the following. Click on the ``Advanced

Docket Search'' button on the right side of the screen. Type in the Docket ID (OSM-2008-0001) and click the ``Submit'' button at the bottom of the page. The next screen will display the Docket Search Results for the rulemaking. If you click on OSM-2008-0001, you can view the proposed rule and submit a comment. You can also view supporting material and any comments submitted by others.

Instructions: For detailed instructions on submitting comments and additional information on the rulemaking process, see the ``Public Comment Procedures'' heading of the SUPPLEMENTARY INFORMATION section of this document.

Docket: In addition to obtaining copies of documents at http://www.regulations.gov, you may review copies of the Kansas program, this

amendment, a listing of any scheduled public hearings, and all written comments received in response to this document, at the address listed below during normal business hours, Monday through Friday, excluding holidays. You may receive one free copy of the amendment by contacting OSM's Tulsa Field Office. Alfred L. Clayborne, Director, Tulsa Field Office, Office of Surface Mining Reclamation and Enforcement, 1645 South 101 St East Avenue, Tulsa, Oklahoma 74128-6547, Telephone: (918) 581-6430, E-mail: aclayborne@osmre.gov.

In addition, you may review a copy of the amendment during regular business

[[Page 3895]]

hours at the following location: Kansas Department of Health and Environment, Surface Mining Section, 4033 Parkview Drive, Frontenac, Kansas 66763, Telephone: (316) 231-8540.

FOR FURTHER INFORMATION CONTACT: Alfred L. Clayborne, Director, Tulsa Field Office. Telephone: (918) 581-6430. E-mail: aclayborne@osmre.gov.

SUPPLEMENTARY INFORMATION:

  1. Background on the Kansas Program II. Description of the Proposed Amendment III. Public Comment Procedures IV. Procedural Determinations

  2. Background on the Kansas Program

    Section 503(a) of the Act permits a State to assume primacy for the regulation of surface coal mining and reclamation operations on non- Federal and non-Indian lands within its borders by demonstrating that its program includes, among other things, ``* * * a State law which provides for the regulation of surface coal mining and reclamation operations in accordance with the requirements of this Act * * *; and rules and regulations consistent with regulations issued by the Secretary pursuant to this Act.'' See 30 U.S.C. 1253(a)(1) and (7). On the basis of these criteria, the Secretary of the Interior conditionally approved the Kansas program on January 21, 1981. You can find background information on the Kansas program, including the Secretary's findings, the disposition of comments, and the conditions of approval, in the January 21, 1981, Federal Register (46 FR 5892). You can also find later actions concerning the Kansas program and program amendments at 30 CFR 916.10, 916.12, 916.15, and 916.16.

  3. Description of the Proposed Amendment

    By letter dated November 19, 2007 (Administrative Record No. 626 and 627), Kansas sent us amendments to its program under SMCRA (30 U.S.C. 1201, et seq.). Kansas sent the amendments in one package, identifying the Revegetation Success Guidelines as KS-024-FOR and the Normal Husbandry Practices as KS-025-FOR. We have combined these both under one docket number (KS-024-FOR). Kansas submitted these amendments at their own initiative. Below is a summary of the changes proposed by Kansas. The full text of the program amendments are available for you to read at the locations listed above under ADDRESSES.

    Kansas determined that a portion of its currently approved 2002 Revegetation Guidelines contains information that needs to be updated. During a review of its revegetation guidelines, the State found that Appendix C, USDA-SCS Technical Guide Notice KS-145 (KS-415) lists an animal unit month (AUM) value that yields an extremely low production rate. The AUM value is used to calculate the forage production success standard for warm season native grasses. Upon discovering this, Kansas contacted the USDA Natural Resources Conservation Service (NRCS) who informed the State that KS-415 is now considered obsolete. Because of this, Kansas proposes to no longer allow Kansas coal operators to use KS-415 in determining the forage production success standard for warm season native grasses only. Kansas coal operators will continue to use KS-415 for determining forage production success standards for wheat, grain sorghum, and soybeans. In order to calculate the forage production success standard for any area seeded to warm season native grasses where the postmining land use requires both cover and production data, Kansas proposes to replace KS-415 with the NRCS's ``Electronic Field Office Technical Guides'' for rangeland, grazed forestland, and native pastureland interpretations for Linn, Crawford, Cherokee, and Bourbon Counties. Kansas also proposes that the forage production success standard established in each permit be based on the total dry weight production listed for an average year.

    Kansas Department of Health and Environment (KDHE) proposes to update the approved selected husbandry practices which are considered to be normal in Kansas. Utilization of these practices will not result in the KDHE mandating an extension to the period of responsibility for revegetation success and bond liability. The probability of permanent revegetation failure will not be increased if the approved practices are discontinued after expiration of the liability period. Kansas suggests that the proposed practices are considered normal husbandry practices within the region for unmined lands having land uses similar to the approved postmining land use of the disturbed area. They include such practices as mowing, liming, fertilization, disease, pest and vermin control; and any pruning, reseeding, and transplanting specifically necessitated by such actions. Practices not approved, and which will result in an extension of the liability period, include any seeding, fertilization, or irrigation performed at levels which exceed those normally applied in maintaining comparable unmined land in the surrounding area.

    In determining what is an approved selective husbandry practice, evaluations shall include Surface Mining Section (SMS) Professional Judgments, the incorporation of guidelines provided by approved source documents, and information provided by Kansas State University (KSU) and the United States Department of Agriculture, Natural Resources Conservation Service (NRCS). Both NRCS and KSU have established and published many recommended fertility and management practices for row crops, hayland, and grazingland tailored for soil conditions, crop rotations, tillage and application practices.

    If this amendment is approved, the SMS will compare the proposed management practices on mined land with recommended practices provided by KSU and NRCS to determine if the mined land practices can be considered normal husbandry. Through the routine inspection process, the SMS will monitor liability start dates, liming and fertilization activities and evaluate and determine the success of the reclamation. If the SMS determines site specific management practices are outside the normal husbandry practices, a decision will be made whether or not the liability period must restart.

    On all lands with a postmining land use in perennial cover, the SMS shall consider limited reseeding and associated fertilization and liming as non-augmentative if the cumulative area is small. Reseeding of small areas without restarting the period of operation responsibility shall be left up to the judgment of the SMS in conjunction with the NRCS or KSU Extension Agriculture Service and in no case shall the cumulative areas reseeded be greater than 3 acres or 10% of the permit area whichever is less. Exceptions to this maximum size may be made if the area is comprised of a waterway, terrace or other water control structures. In all cases, the reestablished vegetation shall be in place for a sufficient length of time to not adversely affect the SMS's ability to make a valid determination at the time of bond release as to whether the site has been properly reclaimed.

    Approved normal husbandry practices conducted in consultation with KSU or NRCS are not considered augmentation. Evidence of consultation may be required by the SMS. Practices listed in the following documents are approved: Kansas State University Publications, Established Native Grasses, October 1997

    [[Page 3896]]

    Native Hay Meadow Management, July 1992 Trees and Shrubs for Difficult Sites, February 2006 Fertilization Trees, May 2001 Chemical Weed Control in Tree Planning, March 2001 Weed Control Options in Tree Planting, February 2006 Tree Planting Guide, June 2004 Tall Planting Guide, June 2004 Tall Fescue Production and Utilization, April 1994 Maintaining Grass Waterways, April 2004 Rangeland Weed Management, December 1991

    United States Department of Agriculture (USDA) Natural Resources Conservation Service (NRCS) Conservation Practice Standards 314 Brush Management 322 Channel Bank Vegetation 327 Conservative cover 656 Constructive Wetland 332 Contour Buffer Strips 340 Cover Crop 341 Critical Area Planting 362 Diversion 647 Early Successional Habitat Development/Management 386 Field Boarder 393 Filter Strip 511 Forage Harvest Management 666 Forest Stand Improvement 412 Grassed Waterway 484 Mulching 590 Nutrient Management 512 Pasture and Hay Planting 595 Pest Management 338 Prescribed Burning 528 Prescribed Grazing 550 Range Planting 329B Residue Management, Mulch Till 329A Residue Management, No Till/Strip Till 344 Residue Management, Seasonal 391 Riparian Forest Buffer 656 Shallow Water Management for Wildlife 580 Streambank and Shoreline protection 600 Terrace 612 Tree/Shrub Establishment 660 Tree/Shrub Pruning 645 Upland Wildlife Habitat Management 644 Wetland Wildlife Habitat Management 380 Windbreak/Shelterbelt Establishment Kansas Forestry Technical Note KS-9 Tree/Shrub Establishment and Maintenance Guidelines

    The repair of rills and gullies will not be allowed in the State of Kansas without restarting the revegetation liability period, unless the occurrences and the treatment of such rills and gullies constitutes a normal conservation practice in the region as described below:

    In the coal mining region of Kansas, the normal range of precipitation during fall or spring seeding seasons may result in the formation of rills and gullies during the initial establishment of a permanent vegetation cover for any land use. The NRCS has prepared guidelines for the treatment of rills and gullies as part of their critical areas planting (CAP) process. The SMS has determined that the NRCS CAP for the treatment of rills and gullies in the coal mining regions of Kansas constitutes the treatment practice which is the usual degree of management customarily performed to prevent exploitation, destruction or neglect of the soil resources and maintain the productivity of the land uses. This treatment would not be considered an augmented practice because the NRCS guidance is the standard development for the normal treatment of rills and gullies that may develop during the initial establishment of a permanent cover of vegetation on unmined lands in Kansas. If the use of the NRCS guidelines to control rills and gullies under CAP does not stop erosion, any continued treatment of rills and gullies after the initial vegetative establishment would be considered an augmented practice that would restart the liability period. In addition, the KDHE SMS defines the treatment of rills and gullies requiring a permanent reseeding of more than 10 acres in a contiguous block, or 10 percent of the permit area initially seeded during a single year, to be an augmented practice because of the potential for delay of seeding large area to reduce the probability of revegetation success.

    CAP requires active furrows, rills, ditches, or gullies be filled to aid the conservation practices application. The rills and gullies should be filled with topsoil, if the eroding site is not large, or contoured and/or smoothed if the site is large. The area must be seeded during the appropriate seeding season with approved perennial species followed by an application of mulch. If permanent seeding of the area must be delayed due to weather condition, then appropriate temporary erosion control measures must be utilized. Mulch that is to be applied must be free of noxious weeds including Johnson grass and sericea lespedeza, anchored during or immediately after application, and be applied at the following rates:

    1. Native hay or straw: Apply at the rate of 2 tons/acre and crimp into the soil. Native hay mulch should be less than two (2) years old. Where appropriate based on surrounding vegetation, cool season (fescue) hay may be used. Apply at the rate of 2 tons/acre and crimp into the soil.

    2. Wood chips: Apply at the rate of 11-15 tons/acre.

    3. Strawy manure: Apply at the rate of 10 tons/acre. Strawy manure need not be anchored if it contains heavy solids.

    The use of fabric, hay bales, and/or designed rock riprap structure to fill or repair rills and gullies will be approved on a case-by-case basis. Monitoring of these areas will be required to assure that the treatment provides long-term erosion control, does not disrupt the post mining land use, and that the permanent vegetation becomes established. If this treatment is not effective, then filling of the rills and gullies with topsoil and revegetation will be required. Depending on site conditions, terracing, erosion control fabric, wattles, or other measures may be needed to control erosion until vegetation is established. If the drainage area is of a sufficient size to create continued problems with rills and gullies, the operator will install terraces to control the amount and/or velocity of water moving across the area. These terraces will be designed and constructed in accordance with K.A.R. 47-9-(c)(9).

    Liming, fertilization, mulching, seeding or stocking (stems) following the reclamation of any temporary roads, temporary sediment or hydraulic control structures, or areas where the vegetation was disturbed by vehicular traffic not under the control of the permittee shall not be considered augmentation.

    Reliming and/or refertilization of revegetated areas, reseeding cropland in annual crops; or renovating pastureland or cropland areas in perennial cover by over seeding with legumes after a phase II bond release shall be considered normal husbandry practices and shall not restart the liability period if the amount and frequency of these practices do not exceed normal husbandry practices used on unmined land within the region. Other normal husbandry practices that my be conducted on postmining land uses of fish and wildlife habitat, recreation, and forestry without restarting the liability period are disease, pest, and vermin control; and any pruning, reseeding, and transplanting specifically necessitated by such actions. Replanting more than 20% of the trees/shrubs needed to meet the established technical success will restart the 5-year liability time clock. Trees and shrubs counted in determining the success of stocking

    [[Page 3897]]

    shall be healthy and have been in place for not less than two growing seasons. At the time of bond release, at least 80% of the trees and shrubs used to determine such success shall have been in place for a minimum of three years.

  4. Public Comment Procedures

    Under the provisions of 30 CFR 732.17(h), we are seeking your comments on whether the amendment satisfies the applicable program approval criteria of 30 CFR 732.15. If we approve the amendment, it will become part of the State program.

    Written Comments

    Send your written or electronic comments to OSM at one of the two addresses given above. Your written comments should be specific, pertain only to the issues proposed in this rulemaking, and include explanations in support of your recommendations. We cannot ensure that comments received after the close of the comment period (see DATES) or sent to an address other than the two listed above will be included in the docket for this rulemaking and considered.

    Availability of Comments

    Before including your address, phone number, e-mail address, or other personal identifying information in your comment, you should be aware that your entire comment--including your personal identifying information--may be made publicly available at any time. While you can ask us in your comment to withhold your personal identifying information from public review, we cannot guarantee that we will be able to do so.

    Public Hearing

    If you wish to speak at the public hearing, contact the person listed under FOR FURTHER INFORMATION CONTACT by 4 p.m., c.d.t. on February 7, 2008. If you are disabled and need reasonable accommodations to attend a public hearing, contact the person listed under FOR FURTHER INFORMATION CONTACT. We will arrange the location and time of the hearing with those persons requesting the hearing. If no one requests an opportunity to speak, we will not hold a hearing.

    To assist the transcriber and ensure an accurate record, we request, if possible, that each person who speaks at the public hearing provide us with a written copy of his or her comments. The public hearing will continue on the specified date until everyone scheduled to speak has been given an opportunity to be heard. If you are in the audience and have not been scheduled to speak and wish to do so, you will be allowed to speak after those who have been scheduled. We will end the hearing after everyone scheduled to speak and others present in the audience who wish to speak, have been heard.

    Public Meeting

    If only one person requests an opportunity to speak, we may hold a public meeting rather than a public hearing. If you wish to meet with us to discuss the amendment, please request a meeting by contacting the person listed under FOR FURTHER INFORMATION CONTACT. All such meetings are open to the public and, if possible, we will post notices of meetings at the locations listed under ADDRESSES. We will make a written summary of each meeting a part of the administrative record.

  5. Procedural Determinations

    Executive Order 12630--Takings

    This rule does not have takings implications. This determination is based on the analysis performed for the counterpart Federal regulation.

    Executive Order 12866--Regulatory Planning and Review

    This rule is exempted from review by the Office of Management and Budget (OMB) under Executive Order 12866.

    Executive Order 12988--Civil Justice Reform

    The Department of the Interior has conducted the reviews required by section 3 of Executive Order 12988 and has determined that this rule meets the applicable standards of subsections (a) and (b) of that section. However, these standards are not applicable to the actual language of State regulatory programs and program amendments because each program is drafted and promulgated by a specific State, not by OSM. Under sections 503 and 505 of SMCRA (30 U.S.C. 1253 and 1255) and the Federal regulations at 30 CFR 730.11, 732.15, and 732.17(h)(10), decisions on proposed State regulatory programs and program amendments submitted by the States must be based solely on a determination of whether the submittal is consistent with SMCRA and its implementing Federal regulations and whether the other requirements of 30 CFR parts 730, 731, and 732 have been met.

    Executive Order 13132--Federalism

    This rule does not have Federalism implications. SMCRA delineates the roles of the Federal and State governments with regard to the regulation of surface coal mining and reclamation operations. One of the purposes of SMCRA is to ``establish a nationwide program to protect society and the environment from the adverse effects of surface coal mining operations.'' Section 503(a)(1) of SMCRA requires that State laws regulating surface coal mining and reclamation operations be ``in accordance with'' the requirements of SMCRA, and section 503(a)(7) requires that State programs contain rules and regulations ``consistent with'' regulations issued by the Secretary pursuant to SMCRA.

    Executive Order 13175--Consultation and Coordination With Indian Tribal Governments

    In accordance with Executive Order 13175, we have evaluated the potential effects of this rule on Federally-recognized Indian tribes and have determined that the rule does not have substantial direct effects on one or more Indian tribes, on the relationship between the Federal Government and Indian tribes, or on the distribution of power and responsibilities between the Federal Government and Indian tribes. This determination is based on the fact that the Kansas program does not regulate coal exploration and surface coal mining and reclamation operations on Indian lands. Therefore, the Kansas program has no effect on Federally-recognized Indian tribes.

    Executive Order 13211--Regulations That Significantly Affect the Supply, Distribution, or Use of Energy

    On May 18, 2001, the President issued Executive Order 13211 which requires agencies to prepare a Statement of Energy Effects for a rule that is (1) considered significant under Executive Order 12866, and (2) likely to have a significant adverse effect on the supply, distribution, or use of energy. Because this rule is exempt from review under Executive Order 12866 and is not expected to have a significant adverse effect on the supply, distribution, or use of energy, a Statement of Energy Effects is not required.

    National Environmental Policy Act

    This rule does not require an environmental impact statement because section 702(d) of SMCRA (30 U.S.C. 1292(d)) provides that agency decisions on proposed State regulatory program provisions do not constitute major Federal actions within the meaning of section 102(2)(C) of the National Environmental Policy Act (42 U.S.C. 4332(2)(C)).

    [[Page 3898]]

    Paperwork Reduction Act

    This rule does not contain information collection requirements that require approval by OMB under the Paperwork Reduction Act (44 U.S.C. 3507, et seq.).

    Regulatory Flexibility Act

    The Department of the Interior certifies that this rule will not have a significant economic impact on a substantial number of small entities under the Regulatory Flexibility Act (5 U.S.C. 601, et seq.). The State submittal, which is the subject of this rule, is based upon counterpart Federal regulations for which an economic analysis was prepared and certification made that such regulations would not have a significant economic effect upon a substantial number of small entities. In making the determination as to whether this rule would have a significant economic impact, the Department relied upon the data and assumptions for the counterpart Federal regulations.

    Small Business Regulatory Enforcement Fairness Act

    This rule is not a major rule under 5 U.S.C. 804(2), the Small Business Regulatory Enforcement Fairness Act. This rule: (a) Does not have an annual effect on the economy of $100 million; (b) Will not cause a major increase in costs or prices for consumers, individual industries, Federal, State, or local government agencies, or geographic regions; and (c) Does not have significant adverse effects on competition, employment, investment, productivity, innovation, or the ability of U.S.-based enterprises to compete with foreign-based enterprises. This determination is based upon the fact that the State submittal, which is the subject of this rule, is based upon counterpart Federal regulations for which an analysis was prepared and a determination made that the Federal regulation was not considered a major rule.

    Unfunded Mandates

    This rule will not impose an unfunded mandate on State, local, or tribal governments or the private sector of $100 million or more in any given year. This determination is based upon the fact that the State submittal, which is the subject of this rule, is based upon counterpart Federal regulations for which an analysis was prepared and a determination made that the Federal regulation did not impose an unfunded mandate.

    List of Subjects in 30 CFR Part 916

    Intergovernmental relations, Surface mining, Underground mining.

    Dated: December 26, 2007. Len Meier, Acting Regional Director, Mid-Continent Region. [FR Doc. E8-1113 Filed 1-22-08; 8:45 am]

    BILLING CODE 4310-05-P

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT