NASA FAR Supplement: Proposal Adequacy Checklist

Federal Register, Volume 78 Issue 209 (Tuesday, October 29, 2013)

Federal Register Volume 78, Number 209 (Tuesday, October 29, 2013)

Proposed Rules

Pages 64442-64446

From the Federal Register Online via the Government Printing Office www.gpo.gov

FR Doc No: 2013-25287

=======================================================================

-----------------------------------------------------------------------

NATIONAL AERONAUTICS AND SPACE ADMINISTRATION

48 CFR Parts 1815 and 1852

RIN 2700-AE13

NASA FAR Supplement: Proposal Adequacy Checklist

AGENCY: National Aeronautics and Space Administration.

ACTION: Proposed rule.

-----------------------------------------------------------------------

SUMMARY: NASA is proposing to amend the NASA FAR Supplement (NFS) to incorporate a proposal adequacy checklist for proposals in response to solicitations that require the submission of certified cost or pricing data.

DATES: Interested parties should submit comments to NASA at the address below on or before December 30, 2013 to be considered in formulation of the final rule.

ADDRESSES: Interested parties may submit comments, identified by RIN number 2700-AE13 via the Federal eRulemaking Portal: http://www.regulations.gov. Follow the instructions for submitting comments. Comments may also be submitted to William Roets via email at william.roets-1@NASA.gov.

FOR FURTHER INFORMATION CONTACT: William Roets, NASA, Office of Procurement, email: william.roets-1@NASA.gov, or phone: 202-358-4483.

SUPPLEMENTARY INFORMATION:

  1. Background

    This proposed rule supports the NASA Assistant Administrator for Procurement's ``Reducing Transaction Costs in NASA Procurements'' initiative by incorporating the requirement for a proposal adequacy checklist into the NFS at 1815.408-70(c), and associated solicitation provision at NFS 1852.215-85, to ensure offerors take responsibility for submitting thorough, accurate, and complete proposals. The provision will be included in solicitations that require the submission of certified cost or pricing data.

  2. Executive Orders 12866 and 13563

    Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This proposed rule is not a significant regulatory action under section 3(f) of Executive Order 12866. This proposed rule is not a major rule under 5 U.S.C. 804.

  3. Regulatory Flexibility Act

    NASA does not expect this proposed rule to have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq. However, an Initial Regulatory Flexibility Analysis has been performed and is summarized as follows:

    This proposed rule amends the NFS to add a checklist for NASA contractors to complete under solicitations that require the submission of certified cost or pricing data. This rule supports the NASA Assistant Administrator for Procurement's ``Reducing Transaction Costs in NASA Procurements'' initiative by increasing uniformity across NASA and minimizing local variations in this area which will decrease proposal preparation costs.

    The objective of this proposed rule is to ensure that offerors submit thorough, accurate, and complete proposals. By completing the checklist, offerors will be able to self-validate the adequacy of their proposals which will improve the quality of their initial proposal submissions. This will reduce the need for contractors to rework their initial proposal submissions which will save the Government time and resources in performing the evaluation of the proposal.

    The rule will apply to actions where certified cost or pricing data is required. Based on data collected in FPDS-NG for FY2010-2012, there are on average 1162

    Page 64443

    actions per year that met the criteria where the proposal adequacy checklist is to be utilized. On average, 462 of those actions were with small business concerns.

    This proposed rule imposes no new reporting requirements. The rule does not duplicate, overlap, or conflict with any other Federal rules. No alternatives were identified that would meet the objectives of the rule. Excluding the small number of small business concerns that may be subject to the rule would not be in the best interest of the small business concerns or the Government because the proposal adequacy checklist was created directly from requirements already in the Federal Acquisition Regulation. While the checklist does not add burden, it provides a useful tool for ensuring proposal adequacy.

    NASA invites comments from small business concerns and other interested parties on the expected impact of this proposed rule on small entities. NASA will also consider comments from small entities concerning the existing regulations in subparts affected by this proposed rule in accordance with 5 U.S.C. 610. Interested parties must submit such comments separately and should cite 5 U.S.C. 610 and RIN number 2700-AE13 in correspondence.

  4. Paperwork Reduction Act

    This proposed rule contains information collection requirements that require the approval of the Office of Management and Budget under the Paperwork Reduction Act (44 U.S.C. Chapter 35). However, these changes to the NFS do not impose additional information collection requirements to the paperwork burden previously approved under OMB Control Number 9000-0013, entitled ``Cost or Pricing Data Exemption Information.''

    List of Subjects in 48 CFR 1815 and 1852

    Government procurement.

    William P. McNally,

    Assistant Administrator for Procurement.

    Accordingly, 48 CFR parts 1815 and 1852 are proposed to be amended as follows:

    PART 1815--CONTRACTING BY NEGOTIATION ACQUISITION

    0

    1. The authority citation for part 1815 continues to read as follows:

      Authority: 42 U.S.C. 2473(c)(1).

      0

    2. In section 1815.408-70, paragraph (c) is added to read as follows:

      1815.408-70 NASA solicitation provisions and contract clauses.

      * * * * *

      (c) When the solicitation requires the submission of certified cost or pricing data, the contracting officer shall include 1815.215-85, Proposal Adequacy Checklist, in the solicitation to facilitate submission of a thorough, accurate, and complete proposal.

      PART 1852--SOLICITATION PROVISIONS AND CONTRACT CLAUSES

      0

    3. The authority citation for part 1852 continues to read as follows:

      Authority: 42 U.S.C. 2473(c)(1).

      0

    4. Clause 1852.215-85 is added to read as follows:

      1852.215-85 Proposal Adequacy Checklist.

      As prescribed in 1815.408-70(c), use the following provision:

      PROPOSAL ADEQUACY CHECKLIST

      (XX/XX)

      The offeror shall complete and submit as part of their proposal the following checklist, providing location of requested information, or an explanation of why the requested information is not provided. In preparation of the offeror's checklist, offerors may elect to have their prospective subcontractors use the same or similar checklist as appropriate.

      Proposal Adequacy Checklist

      ----------------------------------------------------------------------------------------------------------------

      If not provided

      explain (may use

      References Submission item Proposal page No. continuation pages

      traceable to this

      checklist)

      ----------------------------------------------------------------------------------------------------------------

      General Instructions

      ----------------------------------------------------------------------------------------------------------------

    5. FAR 15.408, Table 15-2, Is there a properly completed ..................... .....................

      Section I Paragraph A. first page of the proposal per

      FAR 15.408 Table 15-2 I.A or as

      specified in the solicitation?

    6. FAR 15.408, Table 15-2, Does the proposal identify the ..................... .....................

      Section I Paragraph A(7). need for Government-furnished

      material/tooling/test equipment?

      Include the accountable contract

      number and contracting officer

      contact information if known.

    7. FAR 15.408, Table 15-2, If your organization is subject to ..................... .....................

      Section I Paragraph A(8). Cost Accounting Standards (CAS),

      does the proposal identify the

      current status of your CAS

      Disclosure Statement? Does the

      proposal identify and explain

      notifications of noncompliance

      with Cost Accounting Standards

      Board or Cost Accounting

      Standards (CAS); any proposal

      inconsistencies with your

      disclosed practices or applicable

      CAS; and inconsistencies with

      your established estimating and

      accounting principles and

      procedures?

    8. FAR 15.408, Table 15-2, Does the proposal disclose any ..................... .....................

      Section I, Paragraph C(1), other known activity that could

      FAR 2.101, ``Cost or pricing materially impact the costs?

      data''. This may include, but is not

      limited to, such factors as--

      (1) Vendor quotations;

      (2) Nonrecurring costs; ..................... .....................

      (3) Information on changes in ..................... .....................

      production methods and in

      production or purchasing

      volume;

      (4) Data supporting projections ..................... .....................

      of business prospects and

      objectives and related

      operations costs;

      (5) Unit-cost trends such as ..................... .....................

      those associated with labor

      efficiency;

      (6) Make-or-buy decisions; ..................... .....................

      (7) Estimated resources to ..................... .....................

      attain business goals; and

      Page 64444

      (8) Information on management ..................... .....................

      decisions that could have a

      significant bearing on costs.

    9. FAR 15.408, Table 15-2, Is an Index of all certified cost ..................... .....................

      Section I Paragraph B. or pricing data and information

      accompanying or identified in the

      proposal provided and

      appropriately referenced?

    10. FAR 15.403-1(b)............ Are there any exceptions to ..................... .....................

      submission of certified cost or

      pricing data pursuant to FAR

      15.403-1(b)? If so, is supporting

      documentation included in the

      proposal? (Note questions 18-20.)

    11. FAR 15.408, Table 15-2, Does the proposal disclose the ..................... .....................

      Section I Paragraph C(2)(i). judgmental factors applied and

      the mathematical or other methods

      used in the estimate, including

      those used in projecting from

      known data?

    12. FAR 15.408, Table 15-2, Does the proposal disclose the ..................... .....................

      Section I Paragraph C(2)(ii). nature and amount of any

      contingencies included in the

      proposed price?

    13. FAR 15.408 Table 15-2, Does the proposal explain the ..................... .....................

      Section II, Paragraph A or B. basis of all cost estimating

      relationships (labor hours or

      material) proposed on other than

      a discrete basis?

    14. FAR 15.408, Table 15-2, Is there a summary of total cost ..................... .....................

      Section I Paragraphs D and E. by element of cost and are the

      elements of cost cross-referenced

      to the supporting cost or pricing

      data? (Breakdowns for each cost

      element must be consistent with

      your cost accounting system,

      including breakdown by year.)

    15. FAR 15.408, Table 15-2, If more than one Contract Line ..................... .....................

      Section I Paragraphs D and E. Item Number (CLIN) or sub

      Contract Line Item Number (sub-

      CLIN) is proposed as required by

      the RFP, are there summary total

      amounts covering all line items

      for each element of cost and is

      it cross-referenced to the

      supporting cost or pricing data?

    16. FAR 15.408, Table 15-2, Does the proposal identify any ..................... .....................

      Section I Paragraph F. incurred costs for work performed

      before the submission of the

      proposal?

    17. FAR 15.408, Table 15-2, Is there a Government forward ..................... .....................

      Section I Paragraph G. pricing rate agreement (FPRA)? If

      so, the offeror shall identify

      the official submittal of such

      rate and factor data. If not,

      does the proposal include all

      rates and factors by year that

      are utilized in the development

      of the proposal and the basis for

      those rates and factors?

      ----------------------------------------------------------------------------------------------------------------

      Cost Elements

      ----------------------------------------------------------------------------------------------------------------

      Materials and Services

      ----------------------------------------------------------------------------------------------------------------

    18. FAR 15.408, Table 15-2, Does the proposal include a ..................... .....................

      Section II Paragraph A. consolidated summary of

      individual material and services,

      frequently referred to as a

      Consolidated Bill of Material

      (CBOM), to include the basis for

      pricing? The offeror's

      consolidated summary shall

      include raw materials, parts,

      components, assemblies,

      subcontracts and services to be

      produced or performed by others,

      identifying as a minimum the

      item, source, quantity, and

      price.

      ----------------------------------------------------------------------------------------------------------------

      Subcontracts (Purchased materials or services)

      ----------------------------------------------------------------------------------------------------------------

    19. FAR 15.404-3(c), FAR Per the thresholds of FAR 15.404- ..................... .....................

      52.244-2. 3(c), Subcontract Pricing

      Considerations, does the proposal

      include a copy of the applicable

      subcontractor's certified cost or

      pricing data?

    20. FAR 15.408, Table 15-2, Is there a price/cost analysis ..................... .....................

      Note 1; Section II Paragraph establishing the reasonableness

  5. of each of the proposed

    subcontracts included with the

    proposal?

    If the offeror's price/cost ..................... .....................

    analyses are not provided with

    the proposal, does the proposal

    include a matrix identifying

    dates for receipt of

    subcontractor proposal,

    completion of fact finding for

    purposes of price/cost analysis,

    and submission of the price/cost

    analysis?

    ----------------------------------------------------------------------------------------------------------------

    Exceptions to Certified Cost or Pricing Data

    ----------------------------------------------------------------------------------------------------------------

    1. FAR 52.215-20, FAR 2.101, Has the offeror submitted an ..................... .....................

      ``commercial item''. exception to the submission of

      certified cost or pricing data

      for commercial items proposed

      either at the prime or

      subcontractor level, in

      accordance with provision 52.215-

      20?

      a. Has the offeror specifically ..................... .....................

      identified the type of

      commercial item claim (FAR

      2.101 commercial item

      definition, paragraphs (1)

      through (8)), and the basis on

      which the item meets the

      definition?

      Page 64445

      b. For modified commercial ..................... .....................

      items (FAR 2.101 commercial

      item definition paragraph

      (3)); did the offeror classify

      the modification(s) as either--

      i. A modification of a type ..................... .....................

      customarily available in the

      commercial marketplace

      (paragraph (3)(i)); or

      ii. A minor modification ..................... .....................

      (paragraph (3)(ii)) of a

      type not customarily

      available in the commercial

      marketplace made to meet

      Federal Government

      requirements not exceeding

      the thresholds in FAR 15.403-

      1(c)(3)(iii)(B)?

      c. For proposed commercial ..................... .....................

      items ``of a type'', or

      ``evolved'' or modified (FAR

      2.101 commercial item

      definition paragraphs (1)

      through (3)), did the

      contractor provide a technical

      description of the differences

      between the proposed item and

      the comparison item(s)?

    2. FAR 15.408, Table 15-2, Does the proposal support the ..................... .....................

      Section II Paragraph A(1). degree of competition and the

      basis for establishing the source

      and reasonableness of price for

      each subcontract or purchase

      order priced on a competitive

      basis exceeding the threshold for

      certified cost or pricing data?

      ----------------------------------------------------------------------------------------------------------------

      Interorganizational Transfers

      ----------------------------------------------------------------------------------------------------------------

    3. FAR 15.408, Table 15-2, For inter-organizational transfers ..................... .....................

      Section II Paragraph A.(2). proposed at cost, does the

      proposal include a complete cost

      proposal in compliance with Table

      15-2?

    4. FAR 15.408, Table 15-2, For inter-organizational transfers ..................... .....................

      Section II Paragraph A(1). proposed at price in accordance

      with FAR 31.205-26(e), does the

      proposal provide an analysis by

      the prime that supports the

      exception from certified cost or

      pricing data in accordance with

      FAR 15.403-1?

      ----------------------------------------------------------------------------------------------------------------

      Direct Labor

      ----------------------------------------------------------------------------------------------------------------

    5. FAR 15.408, Table 15-2, Does the proposal include a time ..................... .....................

      Section II Paragraph B. phased (i.e.; monthly, quarterly)

      breakdown of labor hours, rates

      and costs by category or skill

      level? If labor is the allocation

      base for indirect costs, the

      labor cost must be summarized in

      order that the applicable

      overhead rate can be applied.

    6. FAR 15.408, Table 15-2, For labor Basis of Estimates ..................... .....................

      Section II Paragraph B. (BOEs), does the proposal include

      labor categories, labor hours,

      and task descriptions, (e.g.;

      Statement of Work reference,

      applicable CLIN, Work Breakdown

      Structure, rationale for

      estimate, applicable history, and

      time-phasing)?

    7. FAR subpart 22.10......... If covered by the Service Contract ..................... .....................

      Labor Standards statute (41

      U.S.C. chapter 67), are the rates

      in the proposal in compliance

      with the minimum rates specified

      in the statute?

      ----------------------------------------------------------------------------------------------------------------

      Indirect Costs

      ----------------------------------------------------------------------------------------------------------------

    8. FAR 15.408, Table 15-2, Does the proposal indicate the ..................... .....................

      Section II Paragraph C. basis of estimate for proposed

      indirect costs and how they are

      applied? (Support for the

      indirect rates could consist of

      cost breakdowns, trends, and

      budgetary data.)

      ----------------------------------------------------------------------------------------------------------------

      Other Costs

      ----------------------------------------------------------------------------------------------------------------

    9. FAR 15.408, Table 15-2, Does the proposal include other ..................... .....................

      Section II Paragraph D. direct costs and the basis for

      pricing? If travel is included

      does the proposal include number

      of trips, number of people,

      number of days per trip,

      locations, and rates (e.g.

      airfare, per diem, hotel, car

      rental, etc.)?

    10. FAR 15.408, Table 15-2, If royalties exceed $1,500 does ..................... .....................

      Section II Paragraph E. the proposal provide the

      information/data identified by

      Table 15-2?

    11. FAR 15.408, Table 15-2, When facilities capital cost of ..................... .....................

      Section II Paragraph F. money is proposed, does the

      proposal include submission of

      Form CASB-CMF or reference to an

      FPRA/FPRP and show the

      calculation of the proposed

      amount?

      ----------------------------------------------------------------------------------------------------------------

      Formats for Submission of Line Item Summaries

      ----------------------------------------------------------------------------------------------------------------

    12. FAR 15.408, Table 15-2, Are all cost element breakdowns ..................... .....................

      Section III. provided using the applicable

      format prescribed in FAR 15.408,

      Table 15-2 III? (or alternative

      format if specified in the

      request for proposal)

      Page 64446

    13. FAR 15.408, Table 15-2, If the proposal is for a ..................... .....................

      Section III Paragraph B. modification or change order,

      have cost of work deleted

      (credits) and cost of work added

      (debits) been provided in the

      format described in FAR 15.408,

      Table 15-2.III.B?

    14. FAR 15.408, Table 15-2, For price revisions/ ..................... .....................

      Section III Paragraph C. redeterminations, does the

      proposal follow the format in FAR

      15.408, Table 15-2.III.C?

      ----------------------------------------------------------------------------------------------------------------

      Other

      ----------------------------------------------------------------------------------------------------------------

    15. FAR 16.4.................. If an incentive contract type, ..................... .....................

      does the proposal include offeror

      proposed target cost, target

      profit or fee, share ratio, and,

      when applicable, minimum/maximum

      fee, ceiling price?

    16. FAR 16.203-4 and FAR If Economic Price Adjustments are ..................... .....................

      15.408 Table 15-2, Section being proposed, does the proposal

      II, Paragraphs A, B, C, and D. show the rationale and

      application for the economic

      price adjustment?

    17. FAR 52.232-28............. If the offeror is proposing ..................... .....................

      Performance-Based Payments did

      the offeror comply with FAR

      52.232-28?

    18. FAR 15.408(n), FAR 52.215- Excessive Pass-through Charges- ..................... .....................

      22, FAR 52.215-23. Identification of Subcontract

      Effort: If the offeror intends to

      subcontract more than 70% of the

      total cost of work to be

      performed, does the proposal

      identify: (i) the amount of the

      offeror's indirect costs and

      profit applicable to the work to

      be performed by the proposed

      subcontractor(s); and (ii) a

      description of the added value

      provided by the offeror as

      related to the work to be

      performed by the proposed

      subcontractor(s)?

      ----------------------------------------------------------------------------------------------------------------

      (End of provision)

      FR Doc. 2013-25287 Filed 10-28-13; 8:45 am

      BILLING CODE 7510-01-P

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT