New Hampshire Hydro Associates; Rivermill Hydroelectric, Inc.; Notice of Transfer of Exemption

Federal Register, Volume 80 Issue 55 (Monday, March 23, 2015)

Federal Register Volume 80, Number 55 (Monday, March 23, 2015)

Notices

Pages 15198-15199

From the Federal Register Online via the Government Printing Office www.gpo.gov

FR Doc No: 2015-06531

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

Project No. 9403-008

New Hampshire Hydro Associates; Rivermill Hydroelectric, Inc.; Notice of Transfer of Exemption

  1. By letter filed March 10, 2015, New Hampshire Hydro Associates informed the Commission that the exemption from licensing for the HDI Mascoma Dam Project, FERC No. 9403, originally issued September 21, 1988,\1\ has been transferred to Rivermill Hydroelectric, Inc. The project is located on the Mascoma River in Grafton County, New Hampshire. The transfer of an exemption does not require Commission approval.

    ---------------------------------------------------------------------------

    \1\ 44 FERC 62,273, Order Granting Exemption from Licensing (5 MW or Less) (1988).

    ---------------------------------------------------------------------------

  2. Rivermill Hydroelectric, Inc. is now the exemptee of the HDI Mascoma Dam Project, FERC No. 9403. All correspondence should be forwarded to: Michael Hansen, Rivermill Hydroelectric, Inc., 44 Deer Ridge Drive, Barrington, NH 03825.

    Page 15199

    Dated: March 16, 2015.

    Kimberly D. Bose,

    Secretary.

    FR Doc. 2015-06531 Filed 3-20-15; 8:45 am

    BILLING CODE 6717-01-P