Notice of Availability of Final Environmental Assessment and Finding of No Significant Impact for the Proposed Construction of Railroad Bridges Across Sand Creek and Lake Pend Oreille at Sandpoint, Bonner County, Idaho

Published date05 September 2019
Citation84 FR 46747
Record Number2019-19120
SectionNotices
CourtCoast Guard
Federal Register, Volume 84 Issue 172 (Thursday, September 5, 2019)
[Federal Register Volume 84, Number 172 (Thursday, September 5, 2019)]
                [Notices]
                [Pages 46747-46749]
                From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
                [FR Doc No: 2019-19120]
                =======================================================================
                -----------------------------------------------------------------------
                DEPARTMENT OF HOMELAND SECURITY
                Coast Guard
                [Docket No. USCG-2018-1085]
                RIN 1625-AA09
                Notice of Availability of Final Environmental Assessment and
                Finding of No Significant Impact for the Proposed Construction of
                Railroad Bridges Across Sand Creek and Lake Pend Oreille at Sandpoint,
                Bonner County, Idaho
                AGENCY: Coast Guard, DHS.
                ACTION: Notice of availability.
                -----------------------------------------------------------------------
                SUMMARY: The United States Coast Guard (USCG) announces the
                availability of a Final Environmental Assessment (FEA) and Finding of
                No Significant Impact (FONSI) in accordance with National Environmental
                Policy Act of 1969 (NEPA), as amended (42 U.S.C. 4321 et seq.) and the
                National Historic Preservation Act (NHPA), as amended (16 U.S.C. 470 et
                seq.) for the proposed construction of railroad bridges across Lake
                Pend Oreille and Sand Creek at Sandpoint, Bonner County, Idaho. The
                proposed bridges will be built parallel to existing railroad bridges
                crossing the same waterbodies. As structures over navigable waters of
                the United States, the proposed bridges require a Coast Guard Bridge
                Permit. This notice provides information on where to view the FEA and
                FONSI. There is no comment period associated with this notice.
                ADDRESSES: We have uploaded the FEA and FONSI to our online docket at
                http://www.regulations.gov. Additionally, the East Bonner County
                Library at 1407 Cedar Street, Sandpoint, Idaho, 83864 will maintain
                printed copies of the FEA and FONSI for public review. The documents
                will be available for inspection at this location between 9 a.m. and 7
                p.m. Monday through Thursday and 10 a.m. and 5 p.m. Friday and
                Saturday, except Sundays and Federal holidays. The Thirteenth Coast
                Guard District Bridge Office at 915 2nd Avenue, Seattle, WA 98174-1067
                will also maintain printed copies of the FEA and FONSI for public
                review. The documents will be available for inspection at this location
                between 8 a.m. and 4 p.m., Monday through Friday, except Federal
                holidays.
                FOR FURTHER INFORMATION CONTACT: If you have questions about this
                notice please contact Mr. Steven Fischer, District Bridge Manager,
                Thirteenth
                [[Page 46748]]
                Coast Guard District, U.S. Coast Guard; telephone 206-220-7282.
                SUPPLEMENTARY INFORMATION:
                I. Authority
                 The FEA and FONSI have been prepared in accordance with the
                National Environmental Policy Act (NEPA) (42 U.S.C. 4321 et seq.);
                Council on Environmental Quality (CEQ) Regulations for Implementing
                NEPA (40 CFR 1500-1508) and associated CEQ guidelines: Department of
                Homeland Security Directive 5100.1, National Environmental Policy Act
                Implementing Procedures and Policy for Considering Environmental
                Impacts.
                II. Viewing the FEA and FONSI
                 To view the FEA and FONSI, please visit http://www.regulations.gov,
                enter ``USCG-2018-1085'' in the search field, press ``Enter,'' and then
                select the ``Open Docket Folder'' option. The FEA and FONSI are also
                available for public review at the East Bonner County Library at 1407
                Cedar Street, Sandpoint, Idaho, 83864, between 9 a.m. and 7 p.m. Monday
                through Thursday and 10 a.m. and 5 p.m. Friday and Saturday, except
                Sundays and Federal holidays. The Thirteenth Coast Guard District
                Bridge Office at 915 2nd Avenue, Seattle, WA 98174-1067 will also
                maintain printed copies of the FEA and FONSI for public review. The
                documents will be available for inspection at this location between 8
                a.m. and 4 p.m., Monday through Friday, except Federal holidays.
                III. Privacy Act
                 Anyone can search the electronic form of comments received into any
                of our dockets by the name of the individual submitting the comment (or
                signing the comment, if submitted on behalf of an association,
                business, labor union, etc.). You may review a Privacy Act system of
                records notice regarding our public dockets in the January 17, 2008
                issue of the Federal Register (73 FR 3316).
                IV. Background and Purpose
                 The BNSF Railway Company (BNSF) has proposed to construct a second
                mainline track and associated bridges across Lake Pend Oreille and Sand
                Creek parallel to existing BNSF railroad track and bridges in and
                around Sandpoint, Bonner County, Idaho (Project). The present single-
                track configuration has become a constraint to efficient rail movement,
                resulting in congestion on the BNSF main line, rail yards and sidings
                as trains await clearance to cross the existing single-track bridges.
                Moreover, trains awaiting an opportunity to cross the bridges often
                block vehicular traffic at both public and private at-grade rail
                crossings. The delays attributable to this congestion hinder the timely
                transport and delivery of people, goods and services to local and
                regional destinations. This Project is intended to relieve this
                congestion and enable more efficient movement of trains through the
                Lake Pend Oreille region. The capacity of the rail line through
                Sandpoint and across Lake Pend Oreille is approximately 79 trains per
                day while the current average rail traffic volume on that line segment
                is approximately 60 trains per day. Adding a second main line track
                along this segment would not increase capacity of the rail line because
                there are other constraints outside of the Lake Pend Oreille area.
                 Alternatives considered for the Project include a ``No Action
                Alternative'' that simply preserves the status quo and a Proposed
                Action Alternative that satisfies the purpose and need of the Project.
                Several additional alternatives including (a) a second main line track
                placed east of the existing main track line, (b) alternate routes and
                (c) shifting rail traffic to other railroads were considered and
                dismissed based on infeasibility or impracticability.
                 The federal bridge statutes, including the River and Harbors Act of
                1899, as amended, the Act of March 23, 1906, as amended, and the
                General Bridge Act of 1946 (33 U.S.C. 525 et seq.), require that the
                location and plans for bridges in or over navigable waters of the
                United States be approved by the Secretary of Homeland Security, who
                has delegated that responsibility to the Coast Guard. Lake Pend Oreille
                and Sand Creek are navigable waters of the U.S. as defined in 33 CFR
                2.36(a). In exercising these bridge authorities, the Coast Guard
                considers navigational and environmental impacts, which include
                historic and tribal effects. The Coast Guard's primary responsibility
                regarding BNSF's proposed railroad bridges is to ensure these
                structures do not unreasonably obstruct navigation.
                 Because the intent of the bridge statutes is to preserve
                navigation, the Coast Guard's permit authority is limited to the bridge
                and its essential components including approaches and abutments.
                Consequently, the Coast Guard does not have the authority to approve or
                disapprove broader aspects of a project beyond the bridges themselves.
                For example, if a project sponsor proposes to build a new highway or
                rail line and the project includes a bridge, the Coast Guard's permit
                authority is limited to the bridge and its effect upon navigation, but
                does not extend to the connecting highway or rail line.
                 As lead federal agency for this Project, the Coast Guard is
                responsible for the review of its potential effects on the human
                environment, including historic properties and tribal impacts, pursuant
                to NEPA and the NHPA. The Coast Guard is therefore required by law to
                ensure potential environmental effects are carefully evaluated in each
                bridge permitting decision.
                 On July 13, 2018, as part of this evaluation process, the
                Coast Guard solicited comments from State and Federal agencies with
                expertise in, and authority over, particular resources that may be
                impacted by the project. Additionally, the Coast Guard sought input
                from all tribes that may be affected or otherwise have expertise or
                equities in the Project. Following tribal and expert agency outreach,
                the Coast Guard revised its evaluation, and then sought comments from
                the general public. Agencies that have participated in the
                environmental review of this Project include the U.S. Army Corps of
                Engineers (USACE), the U.S. Fish and Wildlife Service (USFWS), the U.S.
                Environmental Protection Agency (EPA), Idaho Department of Lands (IDL)
                and the Idaho Department of Environmental Quality (IDEQ).
                 On February 6, 2019, the USCG issued a notice in the Federal
                Register announcing the availability of a Draft Environmental
                Assessment for public review and comment (FR USCG-2018-1085). The Coast
                Guard then held Public Meetings in Ponderay, Idaho on March 13, 2019.
                During the comment period, the USCG received comments in favor of and
                opposed to the Project. The comments in favor of the Project generally
                spoke to economic benefits and requests to expedite the environmental
                review and issue required permits. The comments in opposition to the
                Project identified a variety of concerns including, but not limited to,
                (a) requests to elevate the level of federal environmental review to an
                Environmental Impact Statement (EIS); (b) concern regarding derailments
                within the Lake Pend Oreille region and preparedness for response to a
                derailment causing a spill of coal or petroleum products; (c) fugitive
                coal dust emissions and the effects upon air and water quality; and (d)
                the potential for increased rail traffic through the Lake Pend Oreille
                rail corridor.
                 With regard to derailments, the Federal Railroad Administration
                accident statistics and additional detail regarding BNSF's plan to
                prevent derailments has been added to Section 3.14 (Hazardous Materials
                and Wastes)
                [[Page 46749]]
                to better characterize derailment risk. Additional details regarding
                spill response planning for different types of spills under various
                weather conditions have been added to Section 3.14. In addition, the
                Lake Pend Oreille Geographic Response Plan, which is to be implemented
                in the event of a rail accident, is included in Appendix N of the Final
                EA.
                 With regard to fugitive coal dust emissions and the effects upon
                air and water quality, Section 3.1 of the Final EA explains that the
                current use of load profiling and dust suppressants has been shown to
                achieve at least an 85 percent reduction in fugitive coal dust and
                allow only trace amounts to be lost during transit, which are well
                below levels that could be harmful to human or ecological health.
                Section 3.1 also references several NEPA documents from the U.S. Army
                Corps of Engineers and the Surface Transportation Board supporting this
                determination.
                 With regard to concern for increased rail traffic through the Lake
                Pend Oreille rail corridor, the maximum capacity of the rail line
                through Sandpoint and across Lake Pend Oreille is approximately 79
                trains per day while the current average rail traffic volume on that
                line segment is approximately 60 trains per day. This Project does not
                add any origin or destination facilities; therefore, it would not
                induce increases or decreases in rail traffic, but rather is designed
                to increase efficiency of rail current rail transportation. The market
                conditions influencing rail train traffic growth in the study area
                exist with or without construction of a second main line track and
                associated bridges. Adding a second main line track along this segment
                would not increase overall capacity of the rail line because there are
                other constraints on the main lines leading into the Sandpoint and Lake
                Pend Oreille area.
                 Based on the information examined through the study of this
                Project, the USCG has determined that an Environmental Assessment is
                the appropriate level of environmental documentation. The USCG has
                determined that there are no significant impacts associated with the
                Project and has issued a Finding of No Significant Impact.
                 This notice is being provided for information purposes only, and as
                such, there is no public comment period associated with this notice.
                 This notice is issued under the authority of 5 U.S.C. 552(a).
                 Dated: August 29, 2019.
                Brian L. Dunn,
                Chief, Office of Bridge Programs, U.S. Coast Guard.
                [FR Doc. 2019-19120 Filed 9-4-19; 8:45 am]