Notice of Institution of Section 206 Proceeding and Refund Effective Date

Federal Register, Volume 83 Issue 55 (Wednesday, March 21, 2018)

Federal Register Volume 83, Number 55 (Wednesday, March 21, 2018)

Notices

Page 12371

From the Federal Register Online via the Government Publishing Office www.gpo.gov

FR Doc No: 2018-05674

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

Notice of Institution of Section 206 Proceeding and Refund Effective Date

------------------------------------------------------------------------

Docket No.

------------------------------------------------------------------------

AEP Appalachian Transmission Company, Inc.. EL18-62-000

AEP Indiana Michigan Transmission Company, ...........................

Inc.

AEP Kentucky Transmission Company, Inc..... ...........................

AEP Ohio Transmission Company, Inc......... ...........................

AEP West Virginia Transmission Company, Inc ...........................

AEP Oklahoma Transmission Company, Inc..... EL18-63-000

AEP Southwestern Transmission Company, Inc. ...........................

Baltimore Gas and Electric Company......... EL18-64-000

Black Hills Power, Inc..................... EL18-65-000

Citizens Sunrise Transmission LLC.......... EL18-66-000

San Diego Gas & Electric Company........... EL18-67-000

Transource Maryland, LLC................... EL18-68-000

Transource Pennsylvania, LLC............... EL18-69-000

Transource West Virginia, LLC.............. EL18-70-000

UNS Electric, Inc.......................... EL18-71-000, (not

consolidated)

------------------------------------------------------------------------

On March 15, 2018, the Commission issued an order in Docket Nos. EL18-62-000, EL18-63-000, EL18-64-000, EL18-65-000, EL18-66-000, EL18-

67-000, EL18-68-000, EL18-69-000, EL18-70-000, and EL18-71-000 pursuant to section 206 of the Federal Power Act (FPA), 16 U.S.C. 824e (2012), instituting an investigation into the justness and reasonableness of each of the above-captioned public utilities' transmission formula rates under its open access transmission tariff or transmission owner tariff on file with the Commission. AEP Appalachian Transmission Company, Inc., et al., 162 FERC 61,225 (2018).

The refund effective date in Docket Nos. EL18-62-000, EL18-63-000, EL18-64-000, EL18-65-000, EL18-66-000, EL18-67-000, EL18-68-000, EL18-

69-000, EL18-70-000, and EL18-71-000, established pursuant to section 206(b) of the FPA, will be the date of publication of this notice in the Federal Register.

Any interested person desiring to be heard in Docket Nos. EL18-62-

000, EL18-63-000, EL18-64-000, EL18-65-000, EL18-66-000, EL18-67-000, EL18-68-000, EL18-69-000, EL18-70-000, and EL18-71-000 must file a notice of intervention or motion to intervene, as appropriate, with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rule 214 of the Commission's Rules of Practice and Procedure, 18 CFR 385.214, within 21 days of the date of issuance of the order.

Dated: March 15, 2018.

Nathaniel J. Davis, Sr.,

Deputy Secretary.

FR Doc. 2018-05674 Filed 3-20-18; 8:45 am

BILLING CODE 6717-01-P