Requirements for MODUs and Other Vessels Conducting Outer Continental Shelf Activities With Dynamic Positioning Systems

Federal Register, Volume 79 Issue 229 (Friday, November 28, 2014)

Federal Register Volume 79, Number 229 (Friday, November 28, 2014)

Proposed Rules

Pages 70943-70994

From the Federal Register Online via the Government Printing Office www.gpo.gov

FR Doc No: 2014-27594

Page 70943

Vol. 79

Friday,

No. 229

November 28, 2014

Part III

Department of Homeland Security

-----------------------------------------------------------------------

Coast Guard

-----------------------------------------------------------------------

33 CFR Parts 140, 143, and 146

46 CFR Parts 61 and 62

Requirements for MODUs and Other Vessels Conducting Outer Continental Shelf Activities With Dynamic Positioning Systems; Proposed Rule

Page 70944

-----------------------------------------------------------------------

DEPARTMENT OF HOMELAND SECURITY

Coast Guard

33 CFR Parts 140, 143, and 146

46 CFR Parts 61 and 62

Docket No. USCG-2014-0063

RIN 1625-AC16

Requirements for MODUs and Other Vessels Conducting Outer Continental Shelf Activities With Dynamic Positioning Systems

AGENCY: Coast Guard, DHS.

ACTION: Notice of proposed rulemaking.

-----------------------------------------------------------------------

SUMMARY: The Coast Guard proposes to establish minimum design, operation, training, and manning standards for mobile offshore drilling units (MODUs) and other vessels using dynamic positioning systems to engage in Outer Continental Shelf activities. Establishing these minimum standards is necessary to improve the safety of people and property involved in such operations, and the protection of the environment in which they operate. This notice of proposed rulemaking would decrease the risk of a loss of position by a dynamically-

positioned MODU or other vessel that could result in a fire, explosion, or subsea spill, and supports the Coast Guard's strategic goals of maritime safety and protection of natural resources.

DATES: Comments and related material must be submitted to the online docket via http://www.regulations.gov or reach the Docket Management Facility on or before February 26, 2015. Comments sent to the Office of Management and Budget (OMB) on collection of information must reach OMB on or before February 26, 2015.

ADDRESSES: Submit comments using one of the listed methods, and see SUPPLEMENTARY INFORMATION for more information on public comments.

Online--http://www.regulations.gov following Web site instructions.

Fax--202-493-2251.

Mail or hand delivery--Docket Management Facility (M-30), U.S. Department of Transportation, West Building Ground Floor, Room W12-140, 1200 New Jersey Avenue SE., Washington, DC 20590-0001. Hand delivery hours: 9 a.m. to 5 p.m., Monday through Friday, except Federal holidays (telephone 202-366-9329).

Collection of Information. Submit any comments on the collection of information discussed in section VI.D. of this preamble both to the Coast Guard's docket and to the Office of Information and Regulatory Affairs (OIRA) in the White House Office of Management and Budget. OIRA submissions can use one of the listed methods.

Email (preferred)_oira_submission@omb.eop.gov (include the docket number and ``Attention: Desk Officer for Coast Guard, DHS'' in the subject line of the email).

Fax--202-395-6566.

Mail--Office of Information and Regulatory Affairs, Office of Management and Budget, 725 17th Street NW., Washington, DC 20503, ATTN: Desk Officer, U.S. Coast Guard.

Viewing material proposed for incorporation by reference: Make arrangements to view this material by calling the Coast Guard's Office of Regulations and Administrative Law at 202-372-3870 or by emailing HQS-SMB-CoastGuardRegulationsLaw@uscg.mil.

FOR FURTHER INFORMATION CONTACT: For information about this document, call or email Lieutenant Jeff Bybee, Coast Guard; telephone 202-372-

1357, email Jeff.B.Bybee@uscg.mil. For information about viewing or submitting material to the docket, call Cheryl Collins, Program Manager, Docket Operations, telephone 202-366-9826.

SUPPLEMENTARY INFORMATION:

Table of Contents for Preamble

I. Public Participation and Request for Comments

  1. Submitting Comments

  2. Viewing Comments and Documents

  3. Privacy Act

  4. Public Meeting

    II. Abbreviations

    III. Basis and Purpose

  5. Basis

  6. Purpose

    IV. Background

    V. Discussion of Proposed Rule

    VI. Incorporation by Reference

    VII. Regulatory Analyses

  7. Regulatory Planning and Review

  8. Small Entities

  9. Assistance for Small Entities

  10. Collection of Information

  11. Federalism

  12. Unfunded Mandates Reform Act

  13. Taking of Private Property

  14. Civil Justice Reform

    I. Protection of Children

  15. Indian Tribal Governments

  16. Energy Effects

    L. Technical Standards

  17. Environment

    I. Public Participation and Request for Comments

    We encourage you to submit comments (or related material) on this rulemaking. We will consider all submissions and may adjust our final action based on your comments. Comments should be marked with docket number USCG-2014-0063 and should provide a reason for each suggestion or recommendation. You should provide personal contact information so that we can contact you if we have questions regarding your comments, but please note that all comments will be posted to the online docket without change and that any personal information you include can be searchable online (see the Federal Register Privacy Act notice regarding our public dockets, 73 FR 3316, Jan. 17, 2008.

    Mailed or hand-delivered comments should be in an unbound 8\1/2\ x 11 inch format suitable for reproduction. The Docket Management Facility will acknowledge receipt of mailed comments if you enclose a stamped, self-addressed postcard or envelope with your submission.

    Documents mentioned in this notice, and all public comments, are in our online docket at http://www.regulations.gov and can be viewed by following the Web site's instructions. You can also view the docket at the Docket Management Facility (see the mailing address under ADDRESSES) between 9 a.m. and 5 p.m., Monday through Friday, except Federal holidays.

  18. Public Meeting

    We plan to hold a public meeting and will announce the time and place in a later notice in the Federal Register.

    II. Abbreviations

    ANSI American National Standards Institute

    ASOC Activity Specific Operating Criteria

    CAMO Critical Activity Mode of Operation

    DHS Department of Homeland Security

    DP Dynamic Positioning

    DP-1 Equipment class 1

    DP-2 Equipment class 2

    DP-3 Equipment class 3

    DPO Dynamic Positioning Operator

    DPOQ Dynamic Positioning Operator, Qualified

    DPSAO Dynamic Positioning System Assurance Organization

    DPVAD Dynamic Positioning Verification Acceptance Document

    FMEA Failure Modes and Effects Analysis

    FR Federal Register

    GT ITC Gross tonnage as measured under 46 U.S.C. 14302, Convention Measurement System

    IEC International Electrotechnical Commission

    IMCA International Marine Contractors Association

    IMO International Maritime Organization

    MERPAC Merchant Personnel Advisory Committee

    MISLE Marine Information for Safety and Law Enforcement

    MODU Mobile Offshore Drilling Unit

    Page 70945

    MOU Mobile Offshore Units

    MSC Marine Safety Center

    MTS Marine Technology Society

    NOSAC National Offshore Safety Advisory Committee

    NPRM Notice of proposed rulemaking

    OCMI Officer in Charge, Marine Inspection

    OCS Outer Continental Shelf

    OCS NCOE Coast Guard Outer Continental Shelf National Center of Expertise

    OMB Office of Management and Budget

    OSV Offshore Supply Vessel

    Sec. Section symbol

    SMS Safety Management System

    STCW Standards for Training Certification and Watchkeeping

    U.S.C. United States Code

    VSL Value of a statistical life

    WSOC Well Specific Operating Criteria

    III. Basis and Purpose

  19. Basis

    Several sections of the Outer Continental Shelf Lands Act (OCSLA) (43 U.S.C. 1331-1356a) provide ``the Secretary of the Department in which the Coast Guard is operating'' with rulemaking authority. The Secretary's authority under all these sections is delegated to the Coast Guard through Department of Homeland Security Delegation No. 0170.1, paragraph II(90).

    43 U.S.C. 1333(d)(1) gives the Secretary ``authority to promulgate and enforce such reasonable regulations with respect to lights and other warning devices, safety equipment, and other matters relating to the promotion of safety of life and property on the artificial islands, installations, and other devices referred to in subsection (a) \1\ of this section or on the waters adjacent thereto, as the Secretary may deem necessary.'' The Coast Guard interprets section 1333(d)(1) as conferring authority to regulate any Outer Continental Shelf (OCS) vessel or facility (collectively referred to as ``OCS unit'') attached to the OCS seabed or engaged in OCS activity to support such a unit.\2\

    ---------------------------------------------------------------------------

    \1\ 43 U.S.C. 1333(a) extends the Constitution, laws and civil and political jurisdiction of the United States to, among other things, all artificial islands, and all installations and other devices permanently or temporarily attached to the seabed, which may be erected thereon for the purpose of exploring for, developing, or producing resources therefrom, or any such installation or other device (other than a ship or vessel) for the purpose of transporting such resources.

    \2\ OCS activity is defined in 33 CFR 140.10 to mean ``any offshore activity associated with exploration for, or development or production of, the minerals of the Outer Continental Shelf.''

    ---------------------------------------------------------------------------

    Section 1347(c) requires promulgation of ``regulations or standards applying to unregulated hazardous working conditions related to activities on the OCS when . . . such regulations or standards are determined to be necessary'' and authorizes the modification ``from time to time'' of ``any regulations, interim or final, dealing with hazardous working conditions on the OCS.'' Section 1348(c) requires promulgation of regulations for onsite scheduled or unscheduled inspections of OCS facilities ``to assure compliance with . . . environmental or safety regulations.'' Additionally, section 1356 calls for regulations requiring, with limited exceptions, all OCS units to be manned by U.S. citizens or resident aliens and to comply with ``such minimum standards of design, construction, alteration, and repair'' as the Secretary or the Secretary of the Interior establishes.

  20. Purpose

    Dynamic Positioning (DP) systems typically use computers to automate control of vital power and propulsion systems to maintain a vessel's position using a position referencing system. Mobile offshore drilling units (MODUs) engaged in deepwater drilling and vessels engaged in other operations that require station-keeping adjacent to MODUs or production platforms now routinely use DP systems for cargo, personnel, or fuel transfers where conventional mooring is not practical. Coast Guard regulations have not kept pace with these new technological developments.

    A DP incident that results in a loss of position \3\ on a MODU or other vessel engaged in Outer Continental Shelf (OCS) activities is a system safety failure that may result in serious consequences for human safety and the environment during certain critical operations. For example, a loss of position on a MODU during well-control operations could result in a subsea spill that is difficult to contain.\4\ A logistics vessel could lose position and strike a floating or fixed facility, thereby causing damage to the gas export riser, which may result in an explosion, a loss of life, or an environmental event.\5\ A project/construction vessel could lose position while conducting diving operations, risking the lives of the divers.\6\

    ---------------------------------------------------------------------------

    \3\ As defined in a MODU's Well Specific Operating Criteria (WSOC) or the Activity Specific Operating Criteria (ASOC) for a vessel other than a MODU. WSOC and ASOC are defined in proposed 46 CFR 62.10-1.

    \4\ When a MODU performs an emergency disconnect from a well during critical activities involving hydrocarbon pressure, the Blowout Preventer (BOP) is the last line of defense to shut in the well and prevent a subsea spill and/or an uncontrolled fuel source from potentially feeding a fire on the MODU. The potential for failure of the BOP was illustrated during the DEEPWATER HORIZON casualty. The Coast Guard has received multiple voluntary reports of DP system failures that caused a loss of position and an emergency disconnect, including failures during critical activities when the BOP was the only thing preventing a catastrophic spill. Because there is no mandatory reporting requirement, the Coast Guard believes that emergency disconnects during critical activities are much more prevalent than indicated by voluntary reports.

    \5\ In one example from voluntary reporting, a dynamically-

    positioned MODU on the U.S. OCS suffered a loss of position during critical activities while attached to a well in April 2010, and the subsea gear was damaged when the MODU performed an emergency disconnect. Another example occurred in July 2005, when the dynamically-positioned logistics vessel SAMUDRA SURAKSHA suffered a loss of position while attempting a personnel transfer and collided with the MUMBAI HIGH NORTH (MHN) platform. The collision severed at least one gas riser, causing a massive fire that destroyed the MHN platform within 2 hours and killed 22 people.

    \6\ For example, in September 2012, the dynamically positioned project/construction vessel BIBBY TOPAZ suffered a loss of position that severed the umbilical of a diver. Similar incidents involving the severing of diver umbilicals have resulted in diver fatalities.

    ---------------------------------------------------------------------------

    To reduce the likelihood of a DP incident causing loss of position and the resulting consequences, many large offshore lease-holding corporations require MODUs and other vessels using DP systems while performing Critical OCS Activities \7\ on their leases to meet a minimum DP system design standard.\8\ Additionally, they require these vessels to implement operating guidelines and employ procedures and decision-support tools to ensure the DP system is operated within its design limits. They also require Dynamic Positioning Operators (DPOs) and other essential personnel to be well trained.

    ---------------------------------------------------------------------------

    \7\ A Critical OCS Activity is defined in 33 CFR 140.305 of this NPRM, in part, as ``OCS Activities where maintaining station is critical because a loss of position could cause a personal injury, environmental pollution, or catastrophic damage.'' Section 140.305 also contains non-exhasutive lists of examples of activities that meet the definitions of Critical OCS Activities on a MODU and Critical OCS Activities on Vessels Other than MODUs. The Coast Guard would provide the DP system industry advance notice and an opportunity to provide input before determining that additional activities meet either of the latter two definitions.

    \8\ Based on teleconferences with industry that took place in January 2013. The minutes are publicly available at http://www.uscg.mil/hq/cg5/cg521/.

    ---------------------------------------------------------------------------

    We are proposing DP standards for MODUs and other vessels that use DP to engage in OCS activities because of the risks described above; the ongoing trend of more operators moving further offshore for mineral exploration and production; the expanded use of DP, which is driven in part by the trend of moving operations further offshore and resultant mooring challenges; the difficulty of responding to incidents further offshore, as illustrated by the 2010 DEEPWATER HORIZON incident; the need to update outdated or outmoded Coast Guard regulations to align with changes in the technology

    Page 70946

    and operations that have transpired since these regulations were last updated; and the need to establish appropriate measures that consistently assess DP system capabilities and improve DP system reliability for each OCS activity. These DP standards include operation, design, training, manning, and watchkeeping components.

    IV. Background

  21. General

    The U.S. Coast Guard, within the U.S. Department of Homeland Security, is responsible for, among other things, protecting the marine environment and promoting the safety of life and property on the OCS. Under OCSLA, Title 46 United States Code, 33 CFR chapter I subchapter N, and 46 CFR chapter I subchapter I-A, the Coast Guard regulates OCS facilities, MODUs, and other vessels engaged in OCS activities, including, but not limited to, tank vessels, offshore supply vessels, and other vessels involved in OCS activities.

    The Bureau of Safety and Environmental Enforcement (BSEE), within the U.S. Department of Interior, is responsible for managing the nation's gas, oil, and other mineral resources on the OCS in a safe and environmentally sound manner. Under the OCSLA and Title 30 CFR, BSEE regulates activities such as oil and gas well exploration, drilling, completion, development, production and servicing, as well as pipeline transportation and storage activities under its jurisdiction. BSEE also grants rights-of use and easements to construct and maintain facilities and rights of way for sub-sea pipelines, umbilicals and other equipment. Among other BSEE regulations applicable to oil, gas, and sulfur operations on the OCS, 30 CFR part 250, subpart S, requires covered units to maintain a Safety and Environmental Management System, and 30 CFR part 250, subpart D, sets minimum requirements for blowout preventers to reduce the likelihood and impact of process safety failures.

    Under a Memorandum of Agreement \9\ between the Coast Guard and BSEE, the Coast Guard is responsible as the lead agency for regulation of DP system design, and all aspects of DP system operation except criteria for well shut-in and disconnect when out of the watch circle.\10\

    ---------------------------------------------------------------------------

    \9\ Memorandum of Agreement Between the Minerals Management Service--U.S. Department of the Interior and the U.S. Coast Guard--

    U.S. Department of Homeland Security (MMS/USCG MOA: OCS-04), dated 28 February 2008, Annex I, Items 4.c and 4.d. The Minerals Management Service has since been renamed the Bureau of Safety and Environmental Enforcement. See also, the Memorandum of Understanding Between the Bureau of Safety and Environmental Enforcement--U.S. Department of the Interior, and the U.S. Coast Guard--U.S. Department of Homeland Security, dated 27 November 2012. The MOA and MOU are available on the docket by following the instructions under the ``Viewing comments and documents'' section of this preamble.

    \10\ Watch circles show critical distances between the wellhead and the MODU, and are used to define when a MODU must take certain actions during a loss of position incident to disconnect and separate from the BOP without damage to the MODU or well, injury to the crew, or an environmental event. Watch circles are also used in a similar way by vessels other than a MODU to avoid the adverse effects of a loss of position.

    ---------------------------------------------------------------------------

  22. Operation and Design Standards

    We initially addressed DP systems in the Coast Guard Eighth District policy letter 01-2003, dated January 22, 2003, ``Use of Dynamic Positioning by Offshore Supply Vessels for Oil and HAZMAT Transfers'' (available in the docket by following the instructions in the ``Viewing comments and documents'' section above). That policy letter provided guidance for certain Offshore Supply Vessels (OSVs) engaged in certain operations in the Gulf of Mexico, and is consistent with International Maritime Organization (IMO) Maritime Safety Committee Circular 645 (MSC/Circ.645), ``Guidelines for Vessels with Dynamic Positioning Systems,'' June 6, 1994, which divides DP system equipment into classes based on reliability levels designated as equipment class 1, 2, or 3. Equipment class 1 (DP-1) is the least reliable and equipment class 3 (DP-3) is the most reliable.

    These DP system equipment classes are used today, and IMO MSC/

    Circ.645 is the foundation for the proposed regulations in this notice. DP system technologies and industry experience, however, have advanced since IMO MSC/Circ.645 was published. Consequently, there is a significant performance disparity among DP systems that have the same equipment class rating, because system configuration, operational, and maintenance decisions may effectively degrade DP systems rated as equipment class 2 (DP-2) or DP-3 to the extent that they perform as if they were rated DP-1. For example, degradation can occur when an operator of a vessel with a DP-2 system chooses to operate with closed bus ties and minimize the number of generators online in order to save fuel and avoid wear and tear on equipment. By doing so, the redundancy afforded by DP-2 may be compromised.

    To address this performance disparity, we propose to incorporate IMO MSC/Circ.645 into regulations as mandatory provisions. We also propose to adopt in regulations DP guidance issued by the Marine Technology Society (MTS) \11\ as mandatory provisions to provide owners or operators of DP MODUs and other vessels essential information on how to meet some of the requirements in this notice of proposed rulemaking (NPRM).\12\

    ---------------------------------------------------------------------------

    \11\ MTS is an international organization incorporated in 1963 to give members of academia, government and industry a common forum for the exchange of information and ideas. Its purpose is to promote awareness, understanding, advancement, and application of marine technology. The MTS Dynamic Positioning Committee was established in 1996 to promote a greater international understanding of DP and related issues, and to provide a forum for the exchange of information about technology, training and education, improvement of reliability, development of guidelines, and other pertinent issues to facilitate incident-free DP System operations.

    \12\ ``DP Operations Guidance'' (Marine Technology Society, Part 1, Oct. 2010; Part 2, App. 1, March 2012; Part 2, App. 2, July 2012; Part 2, App. 3, July 2012). These documents are available in the docket for this rulemaking by following the instructions in the ``Viewing comments and documents'' section of this NPRM.)

    ---------------------------------------------------------------------------

    Additionally, in March 2010, we tasked the National Offshore Safety Advisory Committee (NOSAC) with developing recommendations for DP system design, engineering, and operation standards. The NOSAC provided its recommendations in June 2010 (available in the docket by following the instructions in the ``Viewing comments and documents'' section above), and we have considered them in developing this NPRM. A key feature of the NOSAC recommendations is the risk-based approach of applying higher DP equipment class requirements to higher risk operations. As part of its recommendations, the NOSAC also submitted a draft revision of the DP operations guidance developed by MTS. This draft guidance, which was issued by the Dynamic Positioning Committee of the MTS, also linked DP equipment class to operations.

    After receiving the MTS draft guidelines as part of the NOSAC recommendation, we published a draft policy letter, ``Dynamically Positioned Mobile Offshore Drilling Unit Critical Systems, Personnel and Training,'' in the Federal Register on December 29, 2011 (76 FR 81957). The MTS was among those that submitted public comment on the draft letter, and we participated in several DP conferences sponsored by MTS. Also, in a ``Notice of Recommended Interim Voluntary Guidance'' published in the Federal Register on May 4, 2012 (77 FR 26562), we recommended that owners or operators of DP MODUs voluntarily follow the guidance provided in the

    Page 70947

    MTS DP Operations Guidance (MTS DP Operations Guide), Part 2, Appendix 1, on MODUs (March 2012). Subsequently, we published a follow-up ``Notice of Recommended Interim Voluntary Guidance'' in the Federal Register on October 12, 2012 (77 FR 62247), which recommended that owners or operators of DP vessels other than MODUs \13\ that conduct OCS activities on the U.S. OCS follow the 2012 MTS DP Operations Guide, Part 2, Appendix 2, on project construction vessels (July 2012), or Appendix 3, on logistics vessels (July 2012), as appropriate.

    ---------------------------------------------------------------------------

    \13\ Throughout this NPRM, references to ``vessels other than MODUs'' that conduct certain activities or possess certain design characteristics are intended to mean vessels that conduct such activities or possess such characteristics and are not MODUs.

    ---------------------------------------------------------------------------

    This NPRM would require new and existing MODUs, and new vessels other than MODUs, that engage in Critical OCS Activities using a DP system, to comply with certain provisions of IMO MSC/Circ.645 and the MTS DP operations guidance documents listed in the preceding paragraph.\14\ These documents outline a process for determining the design limits of a DP system and operating within those limits. The MTS DP Operations Guide provides guidance on determining a DP system's worst-case failure, which is the critical design parameter that drives how the system should be operated. The worst-case failure is used to determine the Critical Activity Mode of Operation (CAMO), which is defined in the MTS DP Operations Guide and in Sec. 140.305 of this NPRM. The DP system's CAMO is then incorporated into the Activity Specific Operating Criteria (ASOC) or Well Specific Operating Criteria (WSOC) \15\ covering Critical OCS Activities; those criteria must clearly state when a specific OCS activity is a Critical OCS Activity. Operating a DP system within an ASOC or WSOC appropriate to the specific OCS activity and in its CAMO during Critical OCS Activities helps ensure that the DP vessel is operated within its design limits and reduces the likelihood of a loss of position.

    ---------------------------------------------------------------------------

    \14\ See the discussion of ``Standard DP Requirements (Critical OCS Activities)'' in Section V of this preamble.

    \15\ ASOC and WSOC are defined in proposed 46 CFR 62.10-1 and are similar to the Activity Specific Operating Guidelines (ASOG) and Well Specific Operating Guidelines (WSOG) in the MTS DP Operations Guide. With Coast Guard concurrence, the content of the ASOC and WSOC may differ from the recommendations in the Operations Guide, and vessels would be required by the proposed regulations to operate within their ASOC or WSOC.

    ---------------------------------------------------------------------------

    In this NPRM, we propose design and operational standards for DP systems used on MODUs and other vessels. As discussed below in Section V of this NPRM and depicted in Chart A on page 33, we structured these proposed requirements using a risk-based approach tied to the type and size of the MODU or other vessel and whether a Critical OCS Activity is conducted. We are proposing the regulations below after considering the NOSAC recommendations, the MTS and IMO guidance, the current and expected use of DP technology, and the risks associated with loss of position while using DP systems to engage in Critical OCS Activities.

  23. Training, Manning and Watchkeeping Standards

    The increased use of DP provides significant new challenges for the operators and crews of MODUs and other vessels operating on the U.S. OCS. Properly qualified DP system operators and on-watch personnel must have an in-depth knowledge of these positioning systems, be able to constantly and consistently monitor them, and, when appropriate, take manual control to maintain the safety of the vessel, its personnel and the environment. Casualty investigations and anecdotal information regarding near misses due to DP failures have highlighted the need for regulations that address training, manning, and watchkeeping requirements in support of DP systems. The DEEPWATER HORIZON casualty investigation, in particular, highlighted DP operational concerns, including competence, communications, and handling of emergencies, and recommended that we develop operational requirements for vessels fitted with DP.\16\

    ---------------------------------------------------------------------------

    \16\ DEEPWATER HORIZON--FINAL REPORT available at https://homeport.uscg.mil/mycg/portal/ep/contentView.do?contentId=323899&pageTypeId=13489&contentType=EDITORIAL.

    ---------------------------------------------------------------------------

    We do not yet have any operational training standards specifically for DP systems, nor do we have manning or watchkeeping requirements that take into account operations using DP systems. Furthermore, the existing manning and watchkeeping requirements in 46 CFR part 15 apply only to U.S. vessels, including MODUs. To address these gaps, we propose minimum training, watchkeeping, and manning standards for U.S. and foreign MODUs and other vessels using DP systems to engage in OCS activities on the U.S. OCS. We developed these proposed standards after considering internationally accepted standards and input from the industry.

    The regulations proposed in this NPRM were developed, in part, based on the recognition that, under applicable law, any MODU or other vessel operating solely with a DP system is a self-propelled motor vessel and is considered to be underway. 46 CFR 10.107 defines ``self propelled'' as ``propelled by machinery'' and ``mechanically propelled.'' Additionally, 46 U.S.C. 2101, paragraph (16), defines ``motor vessel'' as ``a vessel propelled by machinery other than steam.'' Because any vessel operating solely with a DP system is propelled by machinery, such vessels are self-propelled. Similarly, because any vessel operating solely with a DP system is propelled by machinery other than steam, such vessels are motor vessels. Further, such vessels are self-propelled motor vessels regardless of whether the machinery involved is used for the vessel to make way (transiting) or to maintain a fixed position.

    Self-propelled motor vessels, which include MODUs operating solely with a DP system, are subject to the Standards for Training Certification and Watchkeeping (STCW) Convention. Under Article III, the STCW Convention applies to seafarers serving on board seagoing ships, including self-propelled MODUs, and existing requirements in 46 CFR 15.1101 specify that a ``seagoing vessel means a self-propelled vessel in commercial service that operates beyond the Boundary Line established by 46 CFR part 7. It does not include a vessel that navigates exclusively on inland waters.'' Because MODUs and other vessels operating solely with a DP system on the U.S. OCS are self-

    propelled motor vessels operating beyond the Boundary Line, they are seagoing ships for purposes of the STCW Convention. Consequently, the STCW Convention watchkeeping and hours of rest provisions and the training requirements for personnel standing watches apply to mariners serving on MODUs and other vessels using a DP system to engage in OCS activities on the U.S. OCS.

    Additionally, MODUs and other vessels operating solely with a DP system are considered to be underway. ``Underway'' is defined in 46 CFR 10.107 as--

    A vessel . . . not at anchor, made fast to the shore, or aground. When referring to a mobile offshore drilling unit (MODU), underway means that the MODU is not in an on-location or laid-up status and includes that period of time when the MODU is deploying or recovering its mooring system.

    A vessel operating with DP is underway when it is not: At anchor, made fast to the shore or ocean bottom, aground, or in a laid-up or on-

    location

    Page 70948

    status.\17\ Because MODUs and other vessels operating solely with a DP system are considered to be underway, the regulations in 46 CFR subpart B that implement STCW Convention watchkeeping and hours of rest provisions and the training requirements for personnel standing watches also apply to mariners serving on MODUs and other vessels using a DP system to engage in OCS activities on the U.S. OCS.

    ---------------------------------------------------------------------------

    \17\ 46 CFR 10.107 defines ``on-location'' as ``a mobile offshore drilling unit that is bottom bearing or moored with anchors placed in the drilling configuration.

    ---------------------------------------------------------------------------

    Further, those regulations are consistent with IMO Resolution A.1079(28), entitled ``Recommendations for the Training and Certification of Personnel on Mobile Offshore Units (MOUs),'' and dated December 4, 2013, which defines a self-propelled MOU as ``a MOU fitted with a mechanical means of propulsion to navigate independently,'' \18\ and specifies that all maritime crew members on self-propelled MOUs should meet the requirements of the STCW Convention, as amended.\19\

    ---------------------------------------------------------------------------

    \18\ IMO Resolution A.1079(28), para. 2.

    \19\ Id. at para. 4. This document is available in the docket for this rulemaking by following the instructions in the ``Viewing comments and documents'' section of this NPRM.

    ---------------------------------------------------------------------------

    The 2010 amendments to the STCW Convention contain guidance on the training, experience, and professional competence of personnel who operate DP systems. The guidance specifies the content of the training such personnel should receive and the experience they should possess. We considered the STCW Convention guidance in developing the operational training, manning, and watchkeeping standards in this NPRM.

    Additionally, in November 2011, we tasked the NOSAC with developing recommendations for safe standards for personnel operating vessels using DP systems on the OCS. The NOSAC provided its recommendations in November 2012 (available in the docket by following the instructions in the ``Viewing comments and documents'' section above). The NOSAC also submitted reports containing recommended practices for MODUs and other vessels operating DP systems on the U.S. OCS from each of the three main groups of NOSAC stakeholders; specifically, the owners or operators of: (1) OSVs and small vessels; (2) MODUs; and, (3) manned and unmanned barges.

    In March 2012, we tasked the Merchant Personnel Advisory Committee (MERPAC) with reviewing the safe operation of dynamically positioned vessels operating on the U.S. OCS. MERPAC provided its recommendations in September 2012 (available in the docket by following the instructions in the ``Viewing comments and documents'' section above).

    We considered the recommendations from both advisory committees in developing the training, manning, and watchkeeping standards in this NPRM. Both committees supported the three key recommendations summarized as follows:

    Recommendation 1. DPOs should be credentialed but not necessarily ``licensed.'' If the DPO is not a licensed officer, a licensed officer of the navigation watch shall be provided, if required.

    Recommendation 2. Minimum training should meet the standards found in the International Marine Contractors Association's ``The Training and Experience of Key DP Personnel'' (International Marine Contractors Association (IMCA) M 117, Rev. 1, February 2006); and IMO Maritime Safety Committee Circular 738, ``Guidelines for Dynamic Positioning System (DP) Operator Training'' (MSC/Circ.738/Rev. 1, July 2006). In addition to meeting these training standards, further training and/or competency assessments should be required to ensure the proper performance of duties, and should be the responsibility of companies based on the DP system, vessel type, and service/activities.

    Recommendation 3. Operational measures, including DP system and crew competency requirements, manning, and watch protocols should be based on risk assessments performed under a Safety Management System (SMS).

    We agree with the first recommendation that the DPO must be a credentialed mariner, but need not be licensed. The DPO can also be the officer in charge of a navigational watch, provided the DP system and the navigational equipment are collocated, and the person is a qualified DPO who also holds the appropriate mate or officer endorsement.

    We fully agree with the second recommendation.

    Regarding the third recommendation, we agree with the adoption of operational measures, including the risk-based approach to DP system and crew competency requirements. Additionally, we partially agree with the recommendation that manning and watch protocols be risk based. Because a vessel operating under DP is considered to be underway, MODUs and other vessels using DP must comply with existing laws, regulations, and international requirements on manning and watchkeeping. However, the process to determine watchkeeping and manning protocols should account for the capabilities and limitations of each DP system and the nature of the operations of the vessel, including MODUs. Manning and watch protocols incorporating a risk-based approach would improve the safety of navigation on the U.S. OCS.

    Regarding the training requirements of personnel who stand watch on MODUs, we are cognizant that the competency requirements in STCW for masters and officers in charge of the navigational watch may exceed what is required for a MODU. The STCW Convention, however, already permits the issuance of limitations based on vessel types after identifying the competencies that are not applicable. In addition, some flag states already issue certificates of competency for masters restricted to MODUs that would be acceptable for the operation of MODUs using a DP system to engage in OCS activities on the U.S. OCS.

    The existing training, watchkeeping, and hours of rest provisions in 46 CFR part 15 applicable to U.S. MODUs and other vessels are consistent with STCW requirements. Furthermore, foreign vessels operating on the U.S. OCS are obligated to comply with STCW requirements because they are seagoing vessels under the STCW Convention. As a party to the STCW Convention, we are proposing changes in this proposed rule to address the gap with respect to the application of STCW requirements to non-U.S. MODUs using a DP system to engage in OCS activities on the U.S. OCS by extending the application of the Convention requirements to them.

    Application of the STCW provisions to these MODUs is consistent with the guidance in IMO Resolution A.1079(28), ``Recommendations for the Training and Certification of Personnel on Mobile Offshore Units,'' which specifies that crew members on self-propelled mobile offshore units should meet the requirements of the STCW Convention, as amended.\20\ The Dynamic Positioning Operator, Qualified (DPOQ) must have a thorough knowledge of the CAMO and either the ASOC or WSOC, and must be familiar with the vessel's Failure Modes and Effects Analysis (FMEA) so that he or she understands the vessel's capabilities and can anticipate the vessel's movements in the event of DP system failure or other reduced operating capacity. Although we recognize that mariners working on board MODUs and other vessels should

    Page 70949

    also have additional knowledge and understanding of the industrial mission, as provided in IMO Resolution A.1079(28), such a requirement is outside the scope of this rulemaking.

    ---------------------------------------------------------------------------

    \20\ IMO Resolution A.1079(28), para. 4.

    ---------------------------------------------------------------------------

  24. Classification, Plan Review, and Certification

    This NPRM proposes to require any MODU that uses a DP system to engage in Critical OCS Activities, or any other vessel that uses a new DP system to engage in Critical OCS Activities, to obtain a DP notation equivalent to IMO MSC/Circ.645 equipment class DP-2 or higher from a classification society recognized under 46 CFR 8.230. The classification society must possess DP system rules that are aligned with IMO MSC/Circ.645 and meet the requirements of proposed 46 CFR 61.50-3 and the MTS DP Operations Guide provisions applicable to the vessel being classed. The Coast Guard Outer Continental Shelf National Center of Expertise (OCS NCOE) would determine whether the classification society is recognized under 46 CFR 8.230, whether its DP system rules are aligned with IMO MSC/Circ.645 and the MTS DP Operations Guide provisions applicable to the vessel being classed, and whether the notations are equivalent to DP-2 or higher. Under proposed Sec. 61.50-20, actions of the OCS NCOE would be appealable to the U.S. Coast Guard Deputy Commandant for Prevention.

    Obtaining a classification society notation of DP-2 or higher mitigates the risk of MODUs and other vessels losing position during DP operations on the U.S. OCS. A DP-2 notation from a classification society serves as a fundamental building block for safe DP operations by ensuring a minimum level of reliability for a DP system, but the notation does not consider the mission of the vessel, nor does it address operations. The MTS DP Operations Guide further enhances safe DP operations by ensuring the MODU or other vessel is operated within the design limits of the DP system for the industrial mission it must carry out.

    As we discuss further in section V. of this preamble, different levels of risk are associated with different vessels and missions. In general, we are proposing a risk-based approach tied to the type of vessel and whether the vessel conducts Critical OCS Activities. In addition, we propose to distinguish between vessels other than MODUs based on vessel size. For the lower risk category of vessels that conduct Critical OCS Activities, meeting IMO MSC/Circ.645, obtaining surveys from a DP system assurance organization (DPSAO), meeting DP personnel and system training requirements, and following the MTS guidance is sufficient to ensure a satisfactory safety level.

    Accordingly, we do not propose to require such vessels to obtain plan review from a DPSAO and obtain a DP notation equivalent to IMO MSC/Circ.645 equipment class DP-2 or higher from a classification society for the purpose of determining compliance with Coast Guard DP requirements. Instead, we would rely on the DPSAO to verify compliance with the provisions of this NPRM and be able to provide evidence of this to the Coast Guard upon request.

    This NPRM would require more oversight on MODUs and other larger vessels that use a DP system to engage in Critical OCS Activities. These higher-risk vessels would be required to obtain plan review and surveys from a DPSAO \21\ in accordance with Sec. 61.50-3 of this NPRM.

    ---------------------------------------------------------------------------

    \21\ Dynamic Positioning System Assurance Organizations are described in Sec. 61.50-3 of this NPRM.

    ---------------------------------------------------------------------------

    To qualify for Coast Guard authorization to conduct surveys and verify compliance with the provisions in this NPRM, a DPSAO must demonstrate competency and effectiveness in vessel plan review and survey. Some of the criteria the Coast Guard currently uses to recognize classification societies under 46 CFR 8.230 are also applicable to DP system assurance organizations, such as having quality systems based on industry standards, and financial independence from MODU and other vessel owners and builders. Additional criteria would include a documented history of providing FMEA and survey services on a wide variety of MODUs and other vessels with various industrial missions, and a minimum amount of documented history of providing high quality, effective DP assurance, such as recommending enhancements to design or operational measures.

    In developing the classification, plan review, and certification provisions of this NPRM, we consulted with organizations that currently conduct DP assurance on MODUs and other vessels on the U.S. OCS, and leaseholders who require MODUs and other vessels with which they contract to follow the MTS DP Operations Guide. Based on this feedback and our experience with classification societies and DPSAOs, we are proposing criteria for DP system assurance organizations that are highly qualified in DP system assurance.

    Classification societies and other DPSAOs that are highly qualified in DP system assurance would need to be accepted by the Coast Guard after demonstrating they meet our proposed criteria. After acceptance by the Coast Guard, classification societies and other highly qualified organizations would be eligible to conduct the DP plan review and surveys that would be required on MODUs and other large vessels.

    V. Discussion of Proposed Rule

    This NPRM would set standards for MODUs and other vessels that use a DP system for OCS activities, but would not require vessels to be equipped with a DP system. These standards would not prevent owners or operators from choosing to meet a higher standard or seeking approval of equivalent safety measures.

    In this NPRM, we took potential economic impact into consideration by phasing in certain vessels, other than MODUs, with existing DP systems. We also propose a risk-based approach tied to the type and size of the MODU or other vessel and the category (critical or non-

    critical) of OCS activity the DP system is used to conduct. This approach is depicted in Chart A.

    BILLING CODE 9110-04-P

    Page 70950

    GRAPHIC TIFF OMITTED TP28NO14.000

    BILLING CODE 9110-04-C

    The chart depicts five levels of DP requirements (none, minimum, intermediate, standard, and enhanced) that MODUs and other vessels that use a DP system for OCS activities must satisfy depending on the level of risk. The requirements would be progressive; a MODU or other vessel that is subject to the enhanced DP system requirements would need to meet the standard, intermediate, and minimum requirements as well.

    When developing these proposed requirements, we considered the risk-based approach of the MTS DP Operations Guide. The MTS DP Operations Guide, in Part 1 of section 4.1, recommends various DP equipment classes based on the type of OCS activity the DP system is used to conduct. A similar approach is taken in

    Page 70951

    section 4.4, which recommends different numbers and types of position reference sensors based on the OCS activity.

    The MTS DP Operations Guide also distinguishes between critical and non-critical activities and recommends more stringent operational requirements for critical activities. The proposed regulations reflect the risk-based approach in the guide by adjusting the DP system reliability standard and level of oversight depending on the size of the vessel and the OCS activity the MODU or other vessel is designed to perform. This NPRM would require owners or operators of DP MODUs and other vessels to follow the MTS DP Operations Guide, which provides essential information to support compliance with some of the requirements proposed in this NPRM.

    Primarily, this NPRM would distinguish between MODUs and other vessels that use DP systems to engage in Critical OCS Activities and those that do not by requiring higher DP standards and more robust oversight for Critical OCS Activities. For example, because a MODU has a higher risk profile than a logistics vessel under the MTS DP Operations Guide, this NPRM would require a MODU to meet higher DP standards and be subject to more robust oversight than a logistics vessel.

    This NPRM would also distinguish between the sizes of vessels other than MODUs that use a DP system for OCS activities. A primary risk from such vessels is a loss of position that results in a collision with another structure. The consequences of such a collision increase with the size of the vessel. For this reason, we propose to require a higher DP standard for the largest vessels other than MODUs with new DP systems, which are those greater than 6000 GT ITC.

    For the same reason, we also propose a phase-in for existing vessels other than MODUs, where the largest such vessels are required to comply first and the smallest--those of 500 GT ITC or less (500 GRT if GT ITC not assigned)--are required to comply only with the minimum DP requirements of this NPRM. The NPRM would require vessels other than MODUs, greater than 500 tons but less than 900 tons, equipped with existing DP systems, to comply with the intermediate requirements within 9 years after publication of the final rule; vessels of at least 900 tons but less than 1900 tons to comply within 6 years after publication of the final rule; and vessels of 1900 tons or more to comply within 3 years after publication of the final rule. The decisions to phase in vessels other than MODUs and apply minimum requirements to the smallest of them are also discussed in the regulatory analysis section of this NPRM. Those proposed provisions are intended to reduce economic impact by providing industry time to transition to the new requirements. A detailed discussion of the top four levels of Chart A follows.

    Minimum DP Requirements (Non-Critical OCS Activities)

    This NPRM would require vessels, other than MODUs, that use an existing DP system to engage in non-critical OCS activities or are 500 GT ITC or less to meet minimum DP requirements. For example, a vessel 500 GT ITC or less that uses an existing DP system to engage in Critical OCS Activities would be required to meet minimum DP requirements, as would a vessel greater than 500 GT ITC that uses an existing DP system to engage in non-critical OCS activities. Additionally, vessels, other than MODUs, that use a new DP system to engage in non-critical OCS activities, and MODUs that use a new or existing DP system for the same purpose, would be required to meet minimum training and DP system requirements. There are no DP incident reporting requirements for MODUs and vessels other than MODUs subject to only Minimum DP System Requirements.

    Proposed 33 CFR 140.330 and 46 CFR 62.40-3 would require the DP system controls to be designed and operated in a manner that reduces the probability of adverse events such as a drive-off or drift-off after a DP system failure. The DP system would be required to be equipped with audible and visual alarms that notify the DPO of DP system failure and independent controls immediately available to the DPO that function after the failure.

    Proposed 33 CFR 140.315 would establish minimum requirements for DPO and DPOQ training that ensure they are appropriately trained in the use and limitations of the DP system. Both DPOs and DPOQs would be required to be familiar with the CAMO, and either the ASOC or WSOC of their MODU or other vessel, and to demonstrate a fundamental understanding of the specific DP system's FMEA.

    Under proposed Sec. 140.325, MODUs and other vessels would be required to have a vessel-specific DP system operating manual on board and readily available to the DPO. Additionally, MODUs and vessels conducting vessel-to-vessel transfer operations using DP systems would need to ensure clear communication and appropriate emergency preparedness between the two vessels, which may have differing DP system capabilities and operating procedures.

    Intermediate DP Requirements

    In addition to meeting the minimum DP requirements described above, proposed 33 CFR 140.335 would require vessels, other than MODUs, greater than 500 GT ITC (500 GRT if GT ITC not assigned) that use a DP system installed before 30 DAYS AFTER DATE OF PUBLICATION OF THE FINAL RULE to engage in Critical OCS Activities, to develop and adhere to their CAMO and ASOC. A Critical OCS Activity is defined in proposed 33 CFR 140.305 as an activity on the OCS in which the accuracy and consistency of the vessel's position is a major factor in the safety of personnel, property, and the environment. For the reasons stated in section III.B. of this preamble, we believe that the risk of an injury, collision, or spill incident is higher when a DP system is used to engage in Critical OCS Activities and should be subject to a higher safety requirement.

    Additionally, 33 CFR 140.335 would require MODUs that use a DP system to engage in Critical OCS Activities to develop and adhere to their CAMO and WSOC. The CAMO, ASOC, and WSOC would ensure each DP system is operated within its design limits for the specific operation. Owners or operators would also be required to report DP system incidents involving a reactive change from ``green'' to ``yellow'' or ``red'' as defined by the ASOC or WSOC. The reporting requirement would apply to DP system incidents that occur at any time, not just those that occur during Critical OCS Activities.

    Proposed 46 CFR 61.50-2 would require DP system surveys to be completed by a DPSAO. In addition, the MODU or vessel owner or operator would be required to provide the Coast Guard with at least 30 days advance notice of these surveys, which would enable the Coast Guard oversight needed to strike a balance between ensuring that third parties are adequately performing delegated functions on the Coast Guard's behalf, and reducing visits to the vessel by the Coast Guard.

    The surveys under proposed 46 CFR 61.50-5 through 61.50-15 are based on those described in IMO MSC/Circ.645 and the MTS DP Operations Guide, and would consist of an initial survey, an annual survey that ensures the DP system remains in good working order, and periodic surveys that fully test all systems at least once every 5 years. The specific tests to be conducted during the surveys and the documentation that

    Page 70952

    would be required are discussed in detail in proposed part 61 of this NPRM.

    Proposed 46 CFR 61.50-3 creates requirements that each DPSAO must meet to receive approval from the OCS NCOE to conduct the surveys described above. These provisions include requirements for DPSAOs to produce documents showing they have a history of providing DP assurance to MODUs and vessels other than MODUs, and have adequate resources and experience that demonstrate they are highly qualified to provide DP system oversight.

    Proposed 46 CFR 61.50-4 requires an annual report to be submitted by each DPSAO to the OCS NCOE. The annual report must contain each investigation summary reported to the DPSAO under proposed 33 CFR 140.335(i). The annual report would provide valuable feedback and allow the Coast Guard to verify that the FMEA, WSOC, ASOC and CAMO are being updated with lessons learned that address the cause(s) of each incident, thereby reducing the likelihood that future incidents will occur. Additionally, the OCS NCOE may periodically audit the records of DPSAOs to determine whether they are continuing to provide the DP system oversight necessary to verify that DP system are in compliance with the applicable requirements of this NPRM.

    Proposed 46 CFR 62.40-15 through 62.40-25 would require MODUs and other vessels to which Sec. 140.335 applies to conduct testing based on the FMEA to determine the CAMO for the DP system. The purpose of the testing is to uncover failure modes. For example, failure modes that could be transmitted through a bus tie should be included in the CAMO. For this type of failure mode, the CAMO should require electrical isolation during Critical OCS Activities to prevent the failure from resulting in a complete power loss and subsequent drift off.

    Compliance with these provisions of this NPRM would be documented on the Dynamic Positioning Verification Acceptance Document (DPVAD) issued by a DPSAO under proposed 33 CFR 140.335.

    Standard DP Requirements (Critical OCS Activities)

    In addition to meeting the minimum and intermediate DP requirements described above, proposed 33 CFR 140.340 and 46 CFR 62.25-40 and 62.40-

    5 would require vessels other than MODUs, of 6000 GT ITC or less, that use a new DP system to engage in Critical OCS Activities, to comply with IMO MSC/Circ.645 and the environmental type testing provisions of International Electrotechnical Commission Standard 60092-504 ``Electrical Installation in Ships'', and would require that such vessels meet the provisions of the applicable MTS DP Operations Guide. Because Critical OCS Activities consist of relatively high-risk activities, including those where loss of position on a vessel could strike the production riser of a floating or fixed facility, which may result in an explosion, a loss of life, and/or an environmental event similar in magnitude to that of the DEEPWATER HORIZON, Critical OCS Activities should be subject to a higher safety requirement.

    DP systems on these vessels would, at a minimum, be required to comply with the provisions of IMO MSC/Circ.645 and the MTS DP Operations Guide (incorporated by reference, see Sec. 62.05-1) relevant to equipment class 2 (DP-2) or higher. The applicable provisions of IMO MSC/Circ.645 are the following paragraphs:

    1.1 Purpose and Responsibility;

    1.3 Definitions;

    2 Equipment Classes;

    3 Functional Requirements; and

    4 Operational Requirements.

    As discussed in the ``Background'' section above, IMO MSC/Circ.645 and the MTS DP Operations Guide contain recommendations. Circular 645, however, is a mature, performance based document with wide industry acceptance, and we propose to incorporate it into regulations as mandatory provisions. The proposed regulations would also include a survey and certification scheme different from that in the Circular. Specifically, we propose to require the initial survey to include a Failure Modes and Effects Analysis (FMEA) proving test, and require the Critical Activity Mode of Operation (CAMO) to be identified.

    Development of a CAMO and ASOC or WSOC would also be required for each vessel and well, which have different characteristics and risks. Because of these differences, the proposed regulations cannot prescribe in detail the content of these documents. Such regulations would be extremely lengthy, in a constant state of change as DP technology evolves, and prone to overbroad misapplication of standards that should be tailored to each vessel and well.

    Instead, we propose to require that owners or operators consult the applicable portions of the MTS DP Operations Guide as a method of drafting these documents and complying with the other mandatory provisions of the regulations. The MTS DP Operations Guide contains principles for the development of these documents that address the risks experienced by today's modern DP vessels. The Guide also contains highly useful examples that will be applicable to a large majority of vessels and wells.

    We anticipate that the examples in the MTS DP Operations Guide will be used by industry largely without change. However, some vessels will employ solutions to obtain DP reliability that vary from the examples in the Guide, and will have the option to request the use of alternative guidance from the Coast Guard Office of Design and Engineering Standards (Commandant (CG-ENG)). Where this occurs, the OCMI, the vessel owner or operator, the classification society, and the DPSAO will apply the relevant principles of the MTS DP Operations Guide to ensure the ASOC or WSOC and CAMO provide a sufficient level of DP reliability to meet the DP-2 performance standard in IMO MSC/Circ.645, paragraph 2.2.2.

    Owners or operators would also be required under proposed 46 CFR 62.40-10 to obtain an equivalent class notation from a classification society possessing DP system rules that are aligned with IMO MSC/

    Circ.645 and meet the requirements of proposed 46 CFR 61.50-3 and the MTS DP Operations Guide provisions applicable to the vessel being classed. These other vessels would also need to meet the environmental design requirements of proposed 46 CFR 62.25-40. That section is modeled after a standard promulgated by the International Electrotechnical Commission (IEC) to ensure critical equipment is appropriately designed to withstand the marine environment.\22\

    ---------------------------------------------------------------------------

    \22\ IEC 60092-504, Third Edition 2001-03, Electrical Installations in Ships--Part 504: Special Features--Control and Instrumentation, Clause 5.

    ---------------------------------------------------------------------------

    Enhanced DP Requirements (MODUs and New DP Systems on Large Vessels)

    In addition to meeting the minimum, intermediate, and standard DP requirements described above, proposed 33 CFR 140.345 and 46 CFR 62.20-

    2 would require vessels other than MODUs, greater than 6000 GT ITC, that use new DP systems to engage in Critical OCS Activities, and MODUs that conduct Critical OCS Activities, to obtain plan review and surveys from a DPSAO, which would be subject to oversight by the Coast Guard.

    The enhanced DP requirements are intended to improve DP designs to support the industrial mission of the MODU or large vessel, and are necessary because, as discussed in the Background section of this preamble, a significant performance disparity exists in various

    Page 70953

    DP systems rated DP-2. For example, a DP-2 system on one vessel could consist of a power system with two large generators, two switchboards, and a bus tie; a DP-2 system on another vessel could consist of four smaller generators, four switchboards, and four bus ties. All other things being equal, a bus failure on the first power system would result in a 50 percent reduction in power and thrust, while a bus failure on the second would result in a 25 percent reduction.

    For these reasons, and particularly because of the higher risk profile of these vessels when they are engaging in Critical OCS Activities with a DP system, more rigorous safety standards are necessary.

    Dynamic Positioning Verification Acceptance Document (DPVAD)

    Proposed 33 CFR 140.335 would create a new document for vessels other than MODUs of at least 500 GT ITC, and MODUs that use a DP system to conduct Critical OCS Activities.

    A DPVAD would document compliance with the requirements of this NPRM. This document would need to be renewed every 5 years, and would be issued by a DPSAO after verifying that the vessel has met the applicable DP requirements in this NPRM.

    Training

    Operating a DP system requires such familiarity with the system that the industry and international community have developed the term DPO to describe a person qualified to operate a vessel in DP system mode. This NPRM proposes to adopt that term, as well as the related concept of a qualified trainee, called a DPOQ. Both terms are defined in proposed 33 CFR 140.305.

    We propose to require that when using a DP system to maintain station, a DPO must either operate the DP system or supervise a DPOQ who is operating the DP system. A DPOQ, if present, may operate the DP system if the DPO and the vessel's master have endorsed the DPOQ in writing. Both the DPO and DPOQ must be mariners holding credentials as a rating forming part of the navigational watch, able seafarer-deck, operational-level deck officer, chief mate, master, a rating forming part of the engineering watch, able seafarer-engine, operational-level engineer officer, second engineer, or chief engineer, and must have completed the applicable DP system training set out in proposed 33 CFR 140.315.

    The training requirements for the DPO and DPOQ are based on international standards: Section B-V/e of the STCW Code; IMCA M 117 Rev.1, ``The Training and Experience of Key DP Personnel''; and IMO MSC/Circ. 738, ``Guidelines for Dynamic Positioning System (DP) Operator Training''. There are several training facilities in the United States that are certified by the Nautical Institute, which has established industry-accepted standards meeting the IMO and IMCA guidance. Mariners who receive the training specified in proposed 33 CFR 140.315, and familiarize themselves with the specific system to be operated on a particular vessel, are qualified to operate that MODU or other vessel in DP mode.

    A DPOQ, by contrast, is a trainee qualified to operate a DP system when directly supervised by a DPO. The DPOQ must complete training that provides an introduction to the functions and use of a DP system, as well as 30 days of training on board any DP system-equipped vessel, and must demonstrate understanding of the specific vessel's system he or she would operate such that the DPO and the vessel's master give written endorsements of the DPOQ's qualifications. This training sequence is based on IMCA M 117, and is in keeping with current industry practices.

    Because DP systems vary widely, qualifying as a DPOQ is vessel specific; a DPOQ from one vessel would still require familiarization to qualify as another vessel's DPOQ. The DPOQ must be familiar with the specific vessel's DP system, including the generation, distribution, and management of power. The DPOQ also must have a thorough knowledge of the CAMO and either the ASOC or WSOC, and must be familiar with the vessel's FMEA so that he or she understands the vessel's capabilities and can anticipate the vessel's movements in the event of DP system failure or other reduced operating capacity. Although we recognize that mariners working on board MODUs and other vessels should also have additional knowledge and understanding of the industrial mission, as provided in IMO Resolution A.1079(28), ``Recommendations for the training and certification of personnel on mobile offshore units (MOUs),'' such a requirement is outside the scope of this rulemaking.

    All records of training for the DPO and DPOQ must be maintained by that individual and the owner or operator of the vessel. The Coast Guard would accept company letters, course completion certificates from a training institution, letters or course completion certificates from the DP system manufacturer, or certifications from an industry-accepted organization as proof that the seafarer received training.

    Manning and Watchkeeping

    We also propose to include a definition of DP system in 33 CFR 140.305 and 46 CFR 62.10.1 to make clear that a vessel using a DP system is a vessel ``underway.'' As discussed above in the ``Background'' section of this preamble, a vessel using a DP system is underway when it is not at anchor, made fast to the shore or ocean bottom, aground, or in an on-location or laid-up status. Clarifying that a vessel conducting DP operations is underway would ensure that appropriate manning, training, certification, and hours of rest requirements apply.

    To address the application of the STCW Convention to MODUs and other vessels using a DP system to engage in OCS activities on the U.S. OCS, we propose manning requirements in 33 CFR 140.320 that meet the training, certification, and watchkeeping provisions of the STCW Convention. The specifics of these requirements are discussed below.

    We propose a risk-based approach using a performance standard in 33 CFR 140.310 to determine the number of DPOs and DPOQs necessary for the safe operation of the DP system. The performance standard includes compliance with STCW hours of rest, conditions for the operation with a DPO and DPOQ, use of the officer of the watch as the DPO, and consideration of the nature of the DP operations and the DP system. This approach provides the flexibility to use different configurations when operations or the DP system may require additional personnel, in order to enhance navigational situational awareness.

    To ensure proper navigation and adequate operational oversight of DPOs, we are proposing a requirement in 33 CFR 140.320 that any MODU or other vessel using a DP to engage in OCS activities on the U.S. OCS must be under the command of a master and maintain navigational watches.

    These proposed requirements are necessary for the safety of the vessel and its personnel in the event of a loss of position that requires the use of manual control, and when other navigational issues arise that are beyond the duties and responsibilities of the DPO. Even when maintaining a fixed position using a functional DP system, a situation may arise, such as avoiding a collision with a vessel, that would be outside of the scope of a DPO's training, authority, and skill level, and require a qualified master and navigational watch. Additionally, these proposed

    Page 70954

    requirements are consistent with STCW training, certification, and watchkeeping provisions, as well as the requirements in 46 CFR part 15, that are applicable to U.S. MODUs and other vessels.

    To address the concern that the requirements in the STCW tables of competency for masters and officers in charge of the navigational watch exceed what is required in these proposed regulations for a MODU, the STCW Convention permits the issuance of limitations based on vessel types after identifying the competencies that are not applicable. Although the proposed requirements do not refer to specific STCW regulations or identify the appropriate competencies (specifically, knowledge, understanding, and proficiency) applicable to MODUs, the Coast Guard will address any differences through the issuance of exemptions and limitations to the credential in accordance with 46 CFR 11.301(f). We may also consider developing policy to identify any differences based on MODU type, if appropriate.

    In addition, we propose to include a requirement in 33 CFR 140.320 that the master and officers meet hours of rest requirements in Regulation VIII/1 of the International Convention on Standards of Training, Certification and Watchkeeping for Seafarers, 1978, as amended, and Section A-VIII/1 of the Seafarers' Training, Certification and Watchkeeping Code. These provisions would ensure that the watchkeeping personnel and the watches on board MODUs and other vessels are arranged to protect personnel from impairment because of fatigue. These proposed requirements are consistent with the existing regulations in 46 CFR part 15 as applicable to U.S. MODUs and other vessels.

    We are also proposing a requirement in 33 CFR 140.310 to ensure that the DPO and the officer of the watch are in direct communications during DP system operation. Nothing in this NPRM, however, is to be interpreted as removing or decreasing the responsibility of the master and watchstanding officers for the safe navigation and operation of the vessel. Changes to the authority of the master and crew on a MODU, including matters relating to a MODU's industrial mission, are outside the scope of this NPRM.

    Lastly, we propose to include a requirement in 33 CFR 140.320 that each MODU be issued a manning document identifying the personnel complement necessary to maintain watches and meet the hours of rest requirements. Furthermore, a provision similar to existing 46 CFR 15.520 would permit the flag state to also consider the specialized nature of each MODU, including the limitations and capabilities of the DP system, when determining the minimum manning complement.

    VI. Incorporation by Reference

    Material proposed for incorporation by reference appears in 33 CFR 140.7, 46 CFR 61.03-1, and 46 CFR 62.05-1. See ADDRESSES for information on viewing this material. Copies of the material are available from the sources listed in 33 CFR 140.7, 46 CFR 61.03-1, and 46 CFR 62.05-1. Before publishing a binding rule, we will submit this material to the Director of the Federal Register for approval of the incorporation by reference.

    VII. Regulatory Analyses

    We developed this NPRM after considering numerous statutes and Executive Orders (E.O.s) related to rulemaking. Below, we summarize our analyses based on these statutes or E.O.s.

  25. Regulatory Planning and Review

    Executive Orders 12866 (``Regulatory Planning and Review'') and 13563 (``Improving Regulation and Regulatory Review'') direct agencies to assess the costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). Executive Order 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This NPRM is not a significant regulatory action under section 3(f) of E.O. 12866.

    Accordingly, this NPRM has not been reviewed by the Office of Management and Budget. A preliminary Regulatory Analysis (RA) discussing costs, benefits, and alternatives considered is available in the docket by following the instructions in the ``Viewing comments and documents'' section of this preamble above.

    Table 1 summarizes the impacts of this NPRM.

    Table 1--Summary of Affected Population, Costs, and Benefits

    ------------------------------------------------------------------------

    Category Notice of proposed rulemaking

    ------------------------------------------------------------------------

    Applicability..................... U.S.- and foreign-flag vessels that

    use an existing or new DP system.

    Affected population over 10-year 583 existing OSVs, 53 existing

    period. MODUs, and 43 existing crewboats.

    322 future OSVs, 57 future MODUs,

    and 20 future crewboats.

    Industry Costs (7% discount rate). $20.180 million (annualized).

    $141.733 million (10-year).

    Benefits (7% discount rate)....... Monetized, avoided property damage

    and loss of production:

    $8.812 million (annualized).

    $61.895 million (10-year).

    Non-quantified:

    Reducing the risk of injuries, loss

    of life, and environmental damage

    due to a loss of position resulting

    from a DP failure.

    Breakeven Analysis................ One incident of the magnitude of the

    SAMUDRA SURAKSHA disaster would

    need to be prevented every 48 years

    for the benefits to equal the

    costs.

    ------------------------------------------------------------------------

    * Please refer to the Regulatory Analysis in the docket for details.

    A summary of the RA follows.

    During interactions with industry at National Advisory Committees, DP conferences, and industry training seminars in DP design and operations, industry expressed the need for a uniform DP standard from the United States as a Coastal State. In response, we have developed this NPRM, which would provide MODUs and other vessels that engage in OCS Activities while using a DP system on the U.S. OCS a uniform standard that addresses design, construction, and operation of DP systems. This standard would aid

    Page 70955

    owners or operators in safely meeting energy market demands and pursuing offshore energy ventures that are farther offshore and in deeper waters.

    To minimize the costs to industry, we have based our proposed standards and requirements on established guidelines used by today's DP industry, specifically IMO MSC/Circ.645 and the MTS ``DP Operations Guide.'' We have also limited the application of the DP system design standards to existing and new MODUs, and to new vessels other than MODUs (e.g., OSVs and crewboats) that engage in Critical OCS Activities while using a DP system. Vessels other than MODUs, with existing DP systems that conduct Critical OCS Activities, would be ``grandfathered'' from complying with the DP systems design standards, which are the most costly requirements of this NPRM, and would be permitted to phase-in operating standards, such as developing and maintaining an FMEA, CAMO, and ASOCs, reporting and investigating DP incidents, and conducting DP Surveys, according to the applicable date listed in Table 2.

    Table 2--Phase-In Schedule for Vessels (Except MODUs) With Existing DP Systems

    ----------------------------------------------------------------------------------------------------------------

    Date requirements

    Tonnage of vessel other than MODU effective Number of OSVs and crewboats affected

    ----------------------------------------------------------------------------------------------------------------

    At least 1,900 GT ITC................ Date of Final Rule + 3 224 OSVs and 0 Crewboats.

    years.

    At least 900 GT ITC.................. Date of Final Rule + 6 183 OSVs and 0 Crewboats.

    years.

    Greater than 500 GT ITC.............. Date of Final Rule + 9 85 OSVs and 1 Crewboat.

    years.

    ----------------------------------------------------------------------------------------------------------------

    This flexibility in the phase-in schedule is expected to minimize costs for the population of vessels most likely to not be in compliance with the provisions of this NPRM by date of publication of a final rule. Further, by extending the phase-in timeline, we have reduced the possibility that DP testing providers would be overwhelmed by any sudden increase in demand for their services. Therefore, although a less lengthy phase-in schedule would lead to an earlier accrual of benefits, it may not lead to lower costs overall, if indirect costs (such as a lower quality of service, longer delays between testings, and higher prices in the short-term) are also taken into account.

    When properly designed and operated within design limits, DP systems provide industry with an ability to safely maintain position, using these rapidly evolving, computerized systems to stay within meters of their desired location even in the face of wind, wave, and current forces. However, these systems are not immune from failures and, because MODUs and other vessels in this industry perform high-

    hazard industrial missions, including drilling for oil and gas, conducting personnel transfers, and handling large quantities of oil and hazardous materials, a loss of position could result in an incident with significant loss of life or large spill of oil or hazardous materials. Establishing minimum standards for DP systems used to conduct OCS activities would promote the safety of people and property engaged in such operations. While this NPRM would impose no carriage requirements nor require use of DP, it would require that minimum design, operation, manning, personnel, and training requirements be met if the vessel is using DP.

    This NPRM would also require vessels engaged in certain critical situations (e.g., transfer of personnel and/or hazardous materials) to meet DP-2 design standards to ensure that a single failure of a primary component does not lead to catastrophic consequences.

    Additionally, the provisions required of MODUs and other vessels engaged in Critical OCS Activities enhance the capability of a DP system beyond what it would achieve by obtaining a DP equipment class 2 or 3 notation from a classification society with DP rules aligned with IMO MSC/Circ.645. The enhanced capability enables a MODU or other vessel to more safely perform its industrial mission because the DP system is more fault-tolerant and fault-resistant, and has greater capability to maintain position after a worst-case failure than a vessel operating with DP equipment class 1. Further, these additional provisions would require owners or operators to develop and implement operational measures and decision-support tools (ASOC or WSOC, and CAMO) to operate a DP system within its design limits, mitigating the severity of a DP system failure in the event that one occurred.

    Reason for Coast Guard Action

    MODUs and other vessels that use DP to engage in OCS activities that operate with lower safety standards may cause harm or increased risk of harm to human safety and the environment. The costs of these lower safety standards (increased risk) are not completely borne by the OSV or MODU owners or operators, so they are external to the business decisions of these owners or operators. The crew, which may face increased risk from lower safety standards, may not have any say in safety-related decisions. Since the crew may be adversely affected by business decisions which it may not be able to mitigate through increasing its price (labor cost), it absorbs the cost of the externality (increased risk from lower safety standards), which is a market failure. Oil spills that result from OSV or MODU accidents also impose an externality in the forms of environmental damage and clean-up costs that are not borne directly by the OSV and MODU owners.

    Affected Population

    Based on the Coast Guard's Marine Information for Safety and Law Enforcement (MISLE) data, we estimate that 583 existing OSVs (460 U.S.-

    flag), 53 existing MODUs (2 U.S.-flag), and 43 existing crewboats (42 U.S.-flag) would be affected by this NPRM. Using historical population data from MISLE, we forecast that over the 10-year period of this analysis, 322 future OSVs (which include OSVs less than 6,000 GT ITC and OSVs of at least 6,000 GT ITC), 579 future MODUs, and 20 future crewboats would be affected by this NPRM.\23\

    ---------------------------------------------------------------------------

    \23\ Of this, 255 future OSVs, 2 future MODUs, and 16 future crewboats are expected to be U.S.-flag.

    Page 70956

    Table 3--Summary of Affected Population

    ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

    Future Existing Phased-in

    Future Existing Phased-in OSVs of at OSVs of at OSVs of at

    Year OSVs less OSVs less OSVs less least least least Future Existing Future Existing Phased-in

    than 6,000 than 6,000 than 6,000 6,000 GT 6,000 GT 6,000 GT MODUs MODUs crewboats crewboats crewboats

    GT ITC GT ITC GT ITC ITC ITC ITC

    ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

    Base........................................................ .......... 563 .......... .......... 20 .......... .......... 53 .......... 43 ..........

    1........................................................... 22 .......... 0 5 .......... 0 6 .......... 3 .......... 0

    2........................................................... 46 .......... 0 10 .......... 0 14 .......... 6 .......... 0

    3........................................................... 54 .......... 0 15 .......... 0 20 .......... 10 .......... 0

    4........................................................... 77 .......... 224 20 .......... 20 27 .......... 12 .......... 0

    5........................................................... 102 .......... 0 25 .......... 0 33 .......... 14 .......... 0

    6........................................................... 128 .......... 0 30 .......... 0 38 .......... 15 .......... 0

    7........................................................... 159 .......... 183 35 .......... 0 43 .......... 16 .......... 0

    8........................................................... 195 .......... 0 40 .......... 0 48 .......... 17 .......... 0

    9........................................................... 233 .......... 0 45 .......... 0 53 .......... 18 .......... 0

    10.......................................................... 272 .......... 85 50 .......... 0 57 .......... 20 .......... 1

    ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

    This NPRM would create design, operating, manning, and safety standards by adding or amending regulations in the following categories:

    Minimum DP System Requirements

    DPO and DPOQ Personnel and Training \24\ (33 CFR 140.310 and 140.315)--would establish the minimum number of DPOs and DPOQs necessary for the safe operation of the DP system, as well as minimum training and experience requirements that a DPO or DPOQ must meet prior to operating a DP system on the U.S. OCS. A DPO or DPOQ must demonstrate thorough knowledge of the vessel's DP system components, operational manuals, and the CAMO and ASOC or WSOC. We expect no additional cost to be incurred by industry as a result of these manning requirements and training procedures, because industry contracts currently require these standards.\25\ In addition to incorporating these standards into this NPRM, we would also require company letters, course completion certificates from a training institution, letters or course completion certificates from the DP system manufacturer, or certification from an industry-accepted organization as proof of completion of training requirements. We estimate that it would cost industry $14.30 per DPO or DPOQ to have this documentation made available for review by a Coast Guard official during an inspection (6 minutes x $143.00 per hour). This cost would be incurred by an owner or operator each time a new DPO/DPOQ is hired.

    ---------------------------------------------------------------------------

    \24\ In year 1, we expect that 585 OSVs less than 6,000 GT ITC, 25 OSVs of at least 6,000 GT ITC, 59 MODUs, and 46 crewboats would incur costs as a result of this provision. Over the 10-year study, 1,078 vessels would incur costs.

    \25\ Based on teleconferences with industry that took place in January 2013. The minutes are publicly available at http://www.uscg.mil/hq/cg5/cg521/.

    ---------------------------------------------------------------------------

    DP Manning Requirements (33 CFR 140.320)--would require all applicable MODUs and other vessels using a DP system to engage in OCS activities on the U.S. OCS to be under the command of a master and have an adequate number of mates or navigational watches to meet the hours of rest requirements in Regulation VIII/1 of the STCW and Section A-

    VIII/1 of the ``Seafarers' Training, Certification and Watchkeeping Code.'' By providing some flexibility in the minimum number of required masters and navigational watches, we expect that all but six vessels would comply with this requirement prior to the issuance of a final rule in order to compete in international markets that already require this standard.\26\ We estimate that if a vessel would not have complied with this requirement in the absence of a final rule, then at most it would incur an annual cost of $1,193,920. This maximum cost would be incurred if a vessel did not meet the minimum number of mates and navigational watches as required in this proposed provision. We estimate that each of the six non-compliant MODUs would need to hire two new masters and six new navigational watches in order to comply with the hours of rest requirements in STCW.\27\

    ---------------------------------------------------------------------------

    \26\ After examining all applicable vessels' Minimum Safe Manning Certificates, we found only six existing U.S. OCS MODUs that would not comply with this requirement. All six of these MODUs are owned by a single entity and are flagged by Liberia, which considers these MODUs non-self-propelled.

    \27\ The Coast Guard assumes that these positions would operate under current industry practices: A master and navigational watch would work a 28-day on/off schedule, with each work day consisting of an 8-hour shift; the master would then be on call for the remainder of the day, while three navigational watches would rotate 8-hour shifts throughout the day. We also expect that two masters and six navigational watches would alternate 28-day on/off rotations throughout the year in order to keep that MODU operational year round. As a result, one crew, which consists of three navigational watches and one master, would work seven rotations per year, while the other group would work six rotations per year.

    ---------------------------------------------------------------------------

    Intermediate DP System Requirements

    FMEA and FMEA Proving Test Document \28\ (33 CFR 140.335, 46 CFR 62.40-15 and 62.40-20)--would require all applicable vessels that use a DP system while engaging in Critical OCS Activities to complete and maintain an FMEA and an FMEA proving test document. An FMEA would test a vessel's DP system to establish design and operational limits, which could then be used to develop a CAMO and ASOC or WSOC. With these support tools, operators would have criteria for deciding when to cease operations to prevent a worst-case failure from occurring.

    ---------------------------------------------------------------------------

    \28\ In year 1, we expect that 12 OSVs under 6,000 GT ITC, and 2 crewboats would incur costs as a result of this provision. Over the 10-year study, 390 OSVs under 6,000 GT ITC and 14 crewboats would incur costs.

    ---------------------------------------------------------------------------

    Based on roundtable discussions that included a majority of the owners and operators of MODUs operating on the U.S. OCS,\29\ we expect that all existing and future MODUs would comply with this requirement even in the absence of this NPRM in order to compete in international markets. However, similar roundtable discussions with OSV and crewboat owners and operators indicated that roughly 50 percent of current vessels would not be in compliance with this proposed requirement. Owners and operators of OSVs and crewboats further indicated that it is likely that a similar percentage of future vessels would also not be compliant with these proposed requirements in the absence of a rule. Through statements given by FMEA testing providers, we estimate that it

    Page 70957

    would cost an owner or operator of a OSV or crewboat a one-time payment of $275,000 per vessel to comply with this proposed requirement.

    ---------------------------------------------------------------------------

    \29\ During the development of this NPRM, the Coast Guard held three roundtable discussions with representatives from various industry segments. Participants and summaries from these discussions are available at http://www.uscg.mil/hq/cg5/cg521/ cg521/.

    ---------------------------------------------------------------------------

    CAMO and ASOC or WSOC \30\ (33 CFR 140.335)--would require all applicable vessels to include in the vessel's DP Operations Manual a defined CAMO and, depending on whether the vessel is a MODU or vessel other than a MODU, a ASOC or WSOC. A vessel's CAMO is developed after conducting an FMEA to determine a DP system's worst-case failure. The CAMO will tabulate how to configure the vessel's DP system, including power generation and distribution, propulsion, and position reference systems, so that the DP system, as a whole is fault tolerant and fault resistant. The vessel's CAMO is then used to develop an ASOC or WSOC that will provide criteria on the operational, environmental, and equipment performance limits considered necessary for safe DP system operations while operating on a well. These tools are supplements to a DP-2 or higher class system, which would further decrease the probability that a worst-case failure could occur.

    ---------------------------------------------------------------------------

    \30\ In year 1, we expect that 15 OSVs, and 2 crewboats would incur costs as a result of this provision. Over the 10-year study, 390 OSVs under 6,000 GT ITC, 40 OSVs of at least 6,000 GT ITC, 35 MODUs (only the cost of a CAMO), and 14 crewboats would incur costs.

    ---------------------------------------------------------------------------

    Based on roundtable discussions with MODU owners and operators, all existing and future MODUs are expected to comply with the requirement that a MODU must have a WSOC, although only 70 percent of existing and future MODUs have--or are expected to have--developed a CAMO in the absence of this proposed rule.\31\ Similar conversations with owners and operators of OSVs and crewboats indicated that approximately 50 percent of current vessels would not be compliant with either of these requirements. Owners and operators of OSVs and crewboats further indicated that it is likely that a similar percentage of future vessels would also not be compliant with these requirements in the absence of a rule. Through statements provided by industry, we estimate that it would cost an owner or operator a one-time payment of $9,120 per vessel to develop a CAMO and ASOC or WSOC simultaneously (160 hours x $59.00 per hour), or $4,560 to develop a CAMO or ASOC or WSOC separately (80 hours x $59.00 per hour).

    ---------------------------------------------------------------------------

    \31\ Based on teleconferences with industry that took place in January 2013. The minutes are publicly available at http://www.uscg.mil/hq/cg5/cg521/.

    ---------------------------------------------------------------------------

    Report Reactive Change of DP Status \32\ (33 CFR 140.335)--would require all applicable vessels to report to an authorized DPSAO any incident in which the vessel experiences a reactive change of the DP system's status from green to yellow and/or red. Neither the Coast Guard nor the IMO or MTS currently require vessels that use DP systems to report changes in status. The Coast Guard reviewed documents compiled by the International Marine Contractors Association (IMCA), which is an international trade association that represents offshore, marine, and underwater engineering companies. The IMCA documents compile Dynamic Positioning station-keeping incidents voluntarily reported by IMCA members. Although the documents do not specifically note whether an incident results in a change in status (i.e., green to red or yellow), IMCA notes that an activated red DP alert status would classify as an incident. We use the IMCA incident rate per vessel as the best available data on the change in status from green to red.

    ---------------------------------------------------------------------------

    \32\ In year 1, we expect that 22 OSVs under 6,000 GT ITC, 5 OSVs of at least 6,000 GT ITC, 59 MODUs, and 3 crewboats would incur costs as a result of this provision. Over the 10-year study, 764 OSVs under 6,000 GT ITC, 70 OSVs of at least 6,000 GT ITC, 110 MODUs, and 21 crewboats would need to report DP incidents.

    ---------------------------------------------------------------------------

    Based on a review of IMCA station keeping incident reports from 2004 through 2010 (which is the last year the report was available publically), we estimated that a vessel would experience a reactive change of the DP system's status from green to red an average of 1.45 times per year.\33\ Based on subject matter expert input from Coast Guard personnel in the Office of Design and Engineering Standards, we assume that vessels would incur a similar number of reactive changes of the DP system's status from green to yellow, and therefore estimate that an owner or operator would need to report an average of 2.90 incidents per year per vessel. The rate of DP incidents per vessel may decrease over time as a result of other requirements in this proposal. We assess the impact of the decreased incident rate in the Benefits section of this document.

    ---------------------------------------------------------------------------

    \33\ These reports can be purchased through the IMCA Web site at: http://www.imca-int.com/.

    ---------------------------------------------------------------------------

    Because this proposed requirement would be new, we anticipate creating new burdens for industry. We estimate that it would cost an owner or operator $47.67 per change in DP status to comply with this proposed requirement (20 minutes x $143 per hour). Further, we estimate that it would cost the authorized DPSAO $13.67 per change in DP status to review and record the information, which we assume would be passed on to the owner or operator through the form of the DPSAO charging higher prices for its services (20 minutes x $41.00 per hour).\34\

    ---------------------------------------------------------------------------

    \34\ According to a Coast Guard Subject Matter Expert, it would take an owner or operator 20 minutes to report a DP status change to a DPSAO--which is expected to be done via email, and that it would take an employee from the DPSAO an additional 20 minutes to read and respond to this report.

    ---------------------------------------------------------------------------

    DP Incident Investigations \35\ (33 CFR 140.335)--would require all applicable MODUs and other vessels to conduct a DP incident investigation for every reported DP status change from green to red or yellow, and then to submit a summary report of the investigation's findings to the authorized DPSAO. As every DP incident would require a DP investigation, we estimate that an average of 2.90 DP incident investigations would need to be conducted per year per vessel.

    ---------------------------------------------------------------------------

    \35\ In year 1, we expect that 12 OSVs under 6,000 GT ITC, 3 OSVs of at least 6,000 GT ITC, and 3 crewboats would incur costs to conduct DP investigations. Additionally, 22 OSVs under 6,000 GT ITC, 5 OSVs of at least 6,000 GT ITC, 59 MODUs, and 3 crewboats would incur costs to submit DP investigation reports to the DPSAO during the first year. Over the 10-year study, 383 OSVs under 6,000 GT ITC, 35 OSVs of at least 6,000 GT ITC, and 21 crewboats would incur costs to conduct DP investigations, and 895 OSVs under 6,000 GT ITC, 70 OSVs of at least 6,000 GT ITC, 110 MODUs, and 21 crewboats would need to submit DP investigation reports.

    ---------------------------------------------------------------------------

    After conducting roundtable discussions with owners and operators of MODUs and other vessels, we determined that all existing MODUs and 50 percent of existing OSVs are currently conducting DP investigations following a DP incident, despite not being required to do so.\36\ Through these same roundtable discussions, we determined that no owners or operators of crewboats currently conduct an investigation following a DP incident. For owners or operators that do not, or would not, conduct a DP incident investigation in the absence of a rule, we estimate that it would cost $570 per DP incident to conduct the investigation (10 hours x $57.00 per hour).\37\

    ---------------------------------------------------------------------------

    \36\ Based on teleconferences with industry that took place in January 2013. The minutes are publicly available at http://www.uscg.mil/hq/cg5/cg521/.

    \37\ According to a Coast Guard Subject Matter Expert, it would take 10 hours on average for a ship engineer employed by the owner or operator to conduct a DP incident investigation.

    ---------------------------------------------------------------------------

    In addition to the costs that would be incurred to conduct DP incident investigations, all owners or operators using DP while conducting Critical OCS Activities would experience new costs to submit the summary report of the DP investigation to the authorized DPSAO.

    Page 70958

    As this is a new reporting requirement, it is not expected that any of the affected population would be compliant with this part of the provision in the absence of this NPRM. Consequently, we estimate that it would cost an owner or operator $119.10 per DP incident investigation to write the summary report and then submit it to the authorized DPSAO ((2 hours x $57.00 per hour) + $5.10 shipping fee).\38\ Further, we estimate that it would cost an authorized DPSAO $82.00 per report to review and record the information, which we assume would then be passed on to the owner or operator through the form of the DPSAO charging higher prices for its services (2 hours x $41.00 per hour).\39\

    ---------------------------------------------------------------------------

    \38\ According to a Coast Guard Subject Matter Expert, it would take a ship engineer 2 additional hours to write a DP investigation summary and then submit it to the DPSAO. Also included in this estimate is the time it would take on average to make changes to the vessel's CAMO and ASOCs/WSOCs.

    \39\ According to a Coast Guard Subject Matter Expert, it would take a DPSAO employee 2 hours on average to read through the report and respond if necessary.

    ---------------------------------------------------------------------------

    Annual DP Incident Investigation Report \40\ (46 CFR 61.50-4)--

    would require a DPSAO to submit an annual report containing a summary of each DP incident investigation conducted throughout the year for all vessels using its services. Because this would be a new requirement, we anticipate new burdens for industry and estimate that it would cost an owner or operator $169.10 per year to have the DPSAO file the annual report ((4 hours x $41.00 per hour) + $5.10 shipping fee).\41\ Further, we estimate that it would cost the Government $150.00 per report to review the information provided and respond if necessary (2 hours x $75.00 per hour).

    ---------------------------------------------------------------------------

    \40\ In year 1, we expect that 22 OSVs under 6,000 GT ITC, 5 OSVs of at least 6,000 GT ITC, 59 MODUs, and 3 crewboats would incur costs as a result of this provision. Over the 10-year study, 764 OSVs under 6,000 GT ITC, 70 OSVs of at least 6,000 GT ITC, 110 MODUs, and 21 crewboats would need to submit annual DP investigation reports.

    \41\ According to a Coast Guard Subject Matter Expert, it would take a DPSAO employee 4 hours on average to prepare the Annual DP Incident Investigation Report on behalf of the owner or operator.

    ---------------------------------------------------------------------------

    Emergency Disconnects and Serious Marine Incidents Resulting from a DP Status Change from Green to Red (33 CFR 140.335)--would require all applicable vessels to report to the cognizant OCMI any incident in which the vessel initiates an emergency disconnect or experiences a serious marine incident (as defined by 46 CFR 4.03-2) after experiencing a reactive change of the DP system's status from green to red. Based on a review of IMCA documents from 2004 through 2010, we estimated that a vessel would need to initiate an emergency disconnect 19 percent of the time it experiences a DP change in status. Further, based on the same industry documents, a serious marine incident (as defined by 46 CFR 4.03-2) would occur 5 percent of the time a vessel experiences a reactive change of the DP system's status from green to red. Because this is a new requirement, we anticipate creating new burdens for industry. We estimate that it would cost an owner or operator $47.67 per status change resulting in either an emergency disconnect or serious marine incident to comply with this requirement (20 minutes x $143.00 per hour). Further, we estimate that it would cost the government $25.00 per report to review and record the information (20 minutes x $75.00 per hour).

    Dynamic Positioning Verification and Acceptance Document (DPVAD) \42\ (33 CFR 140.335)--would create a new document for MODUs and applicable vessels, other than MODUs, that use a DP system to conduct Critical OCS Activities. This document would be issued by the authorized DPSAO that performed the vessel's DP surveys, and would need to be renewed once every 5 years.

    ---------------------------------------------------------------------------

    \42\ In year 1, we expect that 22 OSVs under 6,000 GT ITC, 5 OSVs of at least 6,000 GT ITC, 59 MODUs, and 3 crewboats would incur costs as a result of this provision. Over the 10-year study, 764 OSVs under 6,000 GT ITC, 70 OSVs of at least 6,000 GT ITC, 110 MODUs, and 21 crewboats would need to receive a DPVAD.

    ---------------------------------------------------------------------------

    According to a Coast Guard Subject Matter Expert, it is expected that it would take an additional 15 minutes for a DPSAO surveyor to complete the DPVAD, as the DPVAD would be issued by the same DPSAO that conducted the vessel's DP surveys. As a result, we estimate that it would cost an owner or operator $10.25 once every 5 years to comply with this provision (15 minutes x $41.00 per hour).

    DP Surveys \43\ (46 CFR 61.50-2, 61.50-5, 61.50-10, and 61.50-15)--

    would require all applicable vessels to have a DPSAO conduct DP system surveys on an initial, periodic, and annual basis. The organization could be the classification society that issues the DP notation under 62.40-5, because the NPRM would require that the classification society issuing the DP notation be highly qualified in DP system assurance. During the initial survey, and again during the periodic survey 5 years later, a full FMEA test must be performed. Based on roundtable discussions with owners and operators of MODUs and other vessels, of at least 6,000 GT ITC, we have determined that all existing vessels are currently in compliance with this requirement and that all future vessels would also be in compliance with this requirement.\44\ However, this provision would also require a DPSAO to notify the cognizant OCMI at least 30 days in advance of the time and location of these DP surveys. Because this is a new requirement, we anticipate new burdens for industry. We estimate that it would cost an owner or operator $4.10 per year to comply with this requirement (6 minutes x $41.00 per hour).\45\ Further, we anticipate that the OCMI would be present during most DP surveys. However, as we anticipate that these surveys would occur in conjunction with another Coast Guard inspection, the cost incurred by the Coast Guard to attend DP surveys would be minimized. We estimate that it would cost the Government an additional $607.50 per survey as a result of this NPRM ((6 minutes to record the time and location of survey + 8 hours to attend the survey) x $75.00 per hour).\46\

    ---------------------------------------------------------------------------

    \43\ In year 1, we expect that 22 OSVs under 6,000 GT ITC, 5 OSVs of at least 6,000 GT ITC, 59 MODUs, and 3 crewboats would incur costs as a result of this provision. Over the 10-year study, 764 OSVs under 6,000 GT ITC, 70 OSVs of at least 6,000 GT ITC, 110 MODUs, and 21 crewboats would need to report the time and location of the DP Survey.

    \44\ Based on teleconferences with industry that took place in January 2013. The minutes are publicly available at http://www.uscg.mil/hq/cg5/cg521/.

    \45\ According to a Coast Guard Subject Matter Expert, it would take a DPSAO employee 6 minutes on average to notify the OCMI on the time and location of the DP Survey.

    \46\ According to a Coast Guard Subject Matter Expert, a DP Survey would take approximately 8 hours to conduct.

    ---------------------------------------------------------------------------

    Standard DP System Requirements

    DP System Equipment and Notation Requirements \47\ (46 CFR 62.40-

    5)--would require all applicable vessels that use a DP system while engaging in Critical OCS Activities to use, at a minimum, a DP-2 class system and to obtain, at a minimum, a DP-2 class notation.

    Based on vessel specification sheets made publicly available by MODU owners and operators, all existing MODUs comply with this proposed requirement, even in the absence of this NPRM, in order to compete in international markets.\48\ The same cannot be said about vessels other than MODUs that use DP, however. After

    Page 70959

    examining existing OSV's and crewboat's vessel specification sheets, we have determined that only 60 percent of existing OSVs and 70 percent of existing crewboats that use DP would comply with the DP-2 equipment requirement. Because of the mechanical and structural demands associated with DP-2 systems or higher that are not feasible to satisfy in older vessels, the Coast Guard proposes to make the existing population of OSVs and crewboats exempt from the DP-2 equipment requirements of this NPRM.

    ---------------------------------------------------------------------------

    \47\ In year 1, we expect that 12 OSVs under 6,000 GT ITC, and 3 crewboats would incur costs to obtain DP-2 class notation. Over the 10-year study, 143 OSVs under 6,000 GT ITC, and 20 crewboats would incur costs as a result of this requirement.

    \48\ We assume that owners and operators of MODUs will continue to follow this practice in the future.

    ---------------------------------------------------------------------------

    Our research indicates, however, that offshore oil and gas entities are starting to require that all new, contracted OSVs be equipped with DP-2 systems or higher.\49\ This same request is not yet being made for all new, contracted crewboats though. As a result, we estimate that in the years 1 through 3 following the passage of a final rule, one, newly constructed crewboat per year would incur costs in order to comply with the DP-2 equipment requirement. In later years though, all crewboats are expected to be equipped with a DP-2 classed system even in the absence of this proposed rule.

    ---------------------------------------------------------------------------

    \49\ Tollefsen, Sveinung. ``DP systems in the OSV Industry,'' May 2010. http://dspace.mit.edu/bitstream/handle/1721.1/64580/727052552.pdf?sequence=1.

    ---------------------------------------------------------------------------

    In addition to determining the percentage of existing OSVs and crewboats that would comply with the equipment standard in this proposed rule, we also determined through looking at vessel specification sheets that only 50 percent of existing OSVs and 0 percent of existing crewboats would comply with the class notation requirement. We have found that although this NPRM would grandfather certain vessels (other than MODUs) that use a DP system installed prior to issuance of any rule from this provision, owners or operators of OSVs and crewboats have pointed out during roundtable discussions that it is likely that a similar percentage of future vessels would also not be compliant with this requirement in the absence of a proposed rule.

    We estimate that it would cost an owner or operator $876,237 per vessel to comply with the requirement that a vessel using DP to engage in Critical OCS Activities must use a DP-2 class system or higher, and an additional one-time payment of $64,250 per vessel to obtain a DP-2 class notation.

    Enhanced DP System Requirements

    DP System Plans \50\ (46 CFR 62.20-2)--would require all MODUs and other vessels, of at least 6,000 GT ITC, that use a DP system installed on or after the effective date of a final rule to submit their DP system plans to a DPSAO for approval. The organization could be the classification society that issues the DP notation under 62.40-5, because the NPRM would require that the classification society issuing the DP notation be highly qualified in DP system assurance. As proposed, these plans must include a system description, specifications of position reference and environmental monitoring sensors or systems, the location of thrusters and control system components, details of the DP system monitoring and alarm system, FMEA proving test documents and annual survey documents, the vessel's CAMO, and the DP system designer's or manufacture's self-certification of the DP system control equipment to the environmental design standards.

    ---------------------------------------------------------------------------

    \50\ In year 1, we expect that 5 OSVs of at least 6,000 GT ITC, and 59 MODUS would incur costs to submit their DP system plans to the DPSAO. Over the 10-year study, 50 OSVs of at least 6,000 GT ITC, and 110 MODUs would incur costs as a result of this proposed requirement.

    ---------------------------------------------------------------------------

    Based on roundtable discussions with owners and operators of MODUs and other vessels, of at least 6,000 GT ITC, we have determined that all vessels currently would be in compliance with this requirement in the absence of a rule.\51\ However, this provision would also require the DPSAO to submit the plans to the Coast Guard Outer Continental Shelf National Center of Expertise (OCS NCOE). Because this is a new requirement, we anticipate new burdens for industry. We estimate that it would cost a DPSAO $25.60 ((30 minutes x $41.00 per hour) + $5.10 shipping fee) to submit a vessel's DP system plan.\52\ Further, we estimate that it would cost the Government $2,700.00 (36 hours x $75.00 per hour) to review a DP system plan.

    ---------------------------------------------------------------------------

    \51\ Based on teleconferences with industry that took place in January 2013. The minutes are publicly available at http://www.uscg.mil/hq/cg5/cg521/.

    \52\ According to a Coast Guard Subject Matter Expert, it would take 30 minutes for a DPSAO to prepare and submit a vessel's DP system plan to the Coast Guard.

    ---------------------------------------------------------------------------

    Other

    Dynamic Positioning System Assurance Organization Application Process (46 CFR 61.50-3 and 62.40-5)--would require a DPSAO (for the purposes of conducting DP surveys under 61.50) to apply to the Coast Guard for acceptance to provide these services. This provision provides guidelines as to who should apply, as well as what information the applicant should provide in the application. We estimate that it would cost a DPSAO $1,235.10 to prepare and submit each application ((30 hours x $41.00 per hour) + $5.10 shipping fee). Further, we estimate that it would cost the Government $600.00 per application to review each document and reach a decision (8 hours x $75.00 per hour).

    Request for Comment

    We would appreciate additional comments on our cost assumptions, including rates of current compliance. Information is specifically requested on the following:

    (1) Fraction of current MODUs, OSVs and crewboats using DP-1, DP-2, or DP-3.

    (2) Fraction of newly built MODUs, OSVs and crewboats being equipped with DP-1, DP-2, or DP-3.

    (3) Frequency of changes in DP status from green to red and green to yellow.

    (4) Costs to develop an FMEA and WSOC/ASOC.

    (5) Additional cost to equip a newly built vessel with DP-2 instead of DP-1.

    Please submit all comments and related material according to the instructions given in the DATES, ADDRESSES, and Public Participation and Request for Comments sections of this preamble above.

    Costs

    We estimate the total average costs of this NPRM to industry for a 10-year period as summarized in Table 4.\53\

    ---------------------------------------------------------------------------

    \53\ We document the costs at a 7- and 3-percent discount rate as set forth by guidance in the Office of Management and Budget's (OMB) Circular A-4.

    Table 4--Total Industry Cost of NPRM

    Per year

    ----------------------------------------------------------------------------------------------------------------

    Discounted costs

    Year Undiscounted -----------------------------------

    costs 7% 3%

    ----------------------------------------------------------------------------------------------------------------

    1......................................................... $13,295,128 $11,612,479 $12,531,933

    Page 70960

    2......................................................... 13,583,758 11,864,581 12,803,995

    3......................................................... 10,900,925 8,898,402 9,975,891

    4......................................................... 44,460,494 33,918,698 39,502,573

    5......................................................... 12,960,131 9,240,394 11,179,523

    6......................................................... 12,958,982 8,635,117 10,852,943

    7......................................................... 40,540,725 25,246,726 32,963,320

    8......................................................... 15,177,650 8,833,530 11,981,377

    9......................................................... 15,965,539 8,684,195 12,236,256

    10........................................................ 29,112,460 14,799,299 21,662,405

    -----------------------------------------------------

    Total................................................. 208,955,792 141,733,422 175,690,215

    -----------------------------------------------------

    Annualized................................................ ................ $20,179,651 $20,596,253

    ----------------------------------------------------------------------------------------------------------------

    The 10-year discounted present value cost to industry of this NPRM is approximately $141.733 million ($73.239 million to domestic owners or operators), based on a 7-percent discount rate, and $175.690 million ($91.389 million to domestic owners or operators), based on a 3-percent discount rate. The annualized cost to industry is $20.180 million ($10.428 million to domestic owners or operators), based on a 7-percent discount rate, and $20.596 million ($10.714 million to domestic owners or operators), based on a 3-percent discount rate.

    Table 5 summarizes the total 10-year present value cost to industry of this NPRM by risk profile and requirement.

    Table 5--Total Marginal and Annualized Industry Costs for NPRM by Risk Profile

    ----------------------------------------------------------------------------------------------------------------

    10-year cost Annualized

    Requirement -------------------------------------------------------------------------------

    Undiscounted 7% 3% 7% 3%

    ----------------------------------------------------------------------------------------------------------------

    Minimum DP Manning Requirements

    ----------------------------------------------------------------------------------------------------------------

    Cost to Provide Proof of $467,996 $332,365 $400,855 $47,321 $46,992

    Training.......................

    Cost to Comply with DP Manning 71,635,200 50,313,567 61,106,279 7,163,520 7,163,520

    Requirements...................

    -------------------------------------------------------------------------------

    Total....................... 72,103,196 50,645,932 61,507,133 7,210,841 7,210,512

    ----------------------------------------------------------------------------------------------------------------

    Intermediate DP System Requirements

    ----------------------------------------------------------------------------------------------------------------

    Cost to Complete FMEA and FMEA 111,100,000 74,383,054 92,903,263 10,590,474 10,891,097

    Proving Test Document..........

    Cost to Develop CAMO and ASOC or 4,208,880 2,858,478 3,540,664 406,983 415,074

    WSOC...........................

    Cost to Report DP Status Changes 905,587 565,296 734,721 80,485 86,132

    from Green to Red or Yellow....

    Cost to Conduct DP Incident 6,591,592 4,081,179 5,329,997 581,068 624,838

    Investigations.................

    Cost to Submit Annual DP 860,550 537,146 698,162 76,478 81,846

    Incident Investigation Report..

    Cost to Report Emergency 28,791 18,548 23,667 2,641 2,774

    Disconnect and Serious Marine

    Incidents......................

    Cost to Obtain a DPVAD.......... 14,719 9,594 12,159 1,366 1,425

    Cost to Report DP Surveys....... 20,865 13,024 16,928 1,854 1,984

    -------------------------------------------------------------------------------

    Total....................... 123,730,983 82,466,319 103,259,560 11,741,349 12,105,171

    ----------------------------------------------------------------------------------------------------------------

    Standard DP System Requirements

    ----------------------------------------------------------------------------------------------------------------

    Cost to Obtain DP-2 System 2,628,711 2,299,523 2,478,534 327,400 290,560

    Equipment......................

    Cost to Obtain DP-2 Class 10,472,750 7,119,161 8,803,142 1,013,608 1,031,997

    Notation.......................

    -------------------------------------------------------------------------------

    Total....................... 13,101,461 9,418,684 11,281,676 1,341,009 1,322,557

    ----------------------------------------------------------------------------------------------------------------

    Enhanced DP System Requirements

    ----------------------------------------------------------------------------------------------------------------

    Cost to Submit DP System Plans.. 4,096 3,222 3,670 459 430

    -------------------------------------------------------------------------------

    Total....................... 4,096 3,222 3,670 459 430

    ----------------------------------------------------------------------------------------------------------------

    Page 70961

    We also expect that the Government would incur labor costs to review DPO/DPOQ training certificates, annual DP investigation reports, notices of Emergency Disconnects or Serious Marine Incidents that resulted from a DP failure, DPSAO applications, and DP system plans, as well as to attend DP surveys. Table 6 summarizes the 10-year costs of this NPRM to the Government.

    Table 6--Total Government Cost of NPRM

    Per year

    ----------------------------------------------------------------------------------------------------------------

    Discounted costs

    Year Undiscounted -----------------------------------

    costs 7% 3%

    ----------------------------------------------------------------------------------------------------------------

    1......................................................... $286,068 $267,353 $277,735

    2......................................................... 153,180 133,793 144,387

    3......................................................... 165,220 134,869 151,200

    4......................................................... 382,700 291,960 340,024

    5......................................................... 409,808 292,187 353,504

    6......................................................... 436,068 290,570 365,200

    7......................................................... 608,143 378,721 494,476

    8......................................................... 645,120 375,466 509,264

    9......................................................... 683,585 371,825 523,911

    10........................................................ 785,380 399,247 584,396

    -----------------------------------------------------

    Total................................................. 4,555,270 2,935,991 3,744,096

    -----------------------------------------------------

    Annualized................................................ 418,019 438,922

    ----------------------------------------------------------------------------------------------------------------

    The 10-year discounted present value cost to the Government of this NPRM is approximately $2.936 million based on a 7-percent discount rate, and $3.744 million based on a 3-percent discount rate. The annualized cost to industry is approximately $0.418 million, based on a 7-percent discount rate, and $0.439 million, based on a 3-percent discount rate.

    Table 7 summarizes, by requirement, the total 10-year present value cost of this NPRM to the Government.

    Table 7--Total Marginal and Annualized Government Costs for NPRM by Risk Profile

    ----------------------------------------------------------------------------------------------------------------

    10-Year cost Annualized

    Requirement -------------------------------------------------------------------------------

    Undiscounted 7% 3% 7% 3%

    ----------------------------------------------------------------------------------------------------------------

    Minimum DP Manning Requirements

    ----------------------------------------------------------------------------------------------------------------

    Cost to Review Proof of Training $245,453 $174,317 $210,238 $24,819 $24,646

    -------------------------------------------------------------------------------

    Total....................... 245,453 174,317 210,238 24,819 24,646

    ----------------------------------------------------------------------------------------------------------------

    Intermediate DP System Requirements

    ----------------------------------------------------------------------------------------------------------------

    Cost to Review Annual DP 763,350 476,475 619,304 67,839 72,601

    Incident Investigation Report..

    Cost to Review Emergency 15,100 9,728 12,413 1,385 1,455

    Disconnect and Serious Marine

    Incidents......................

    Cost to Record and Attend DP 3,091,568 1,929,724 2,508,182 274,749 294,035

    Surveys........................

    -------------------------------------------------------------------------------

    Total....................... 3,870,018 2,415,928 3,139,899 343,974 368,092

    ----------------------------------------------------------------------------------------------------------------

    Standard DP System Requirements

    ----------------------------------------------------------------------------------------------------------------

    No Cost to Government........... .............. .............. .............. .............. ..............

    -------------------------------------------------------------------------------

    Total....................... 0 0 0 0 0

    ----------------------------------------------------------------------------------------------------------------

    Enhanced DP System Requirements

    ----------------------------------------------------------------------------------------------------------------

    Cost to Review DP System Plans.. 432,000 339,849 387,093 48,387 45,379

    -------------------------------------------------------------------------------

    Total....................... 432,000 339,849 387,093 48,387 45,379

    ----------------------------------------------------------------------------------------------------------------

    Other Requirements

    ----------------------------------------------------------------------------------------------------------------

    Cost to Review DPSAO 7,800 5,523 6,866 786 805

    Applications...................

    -------------------------------------------------------------------------------

    Total....................... 7,800 5,523 6,866 786 805

    ----------------------------------------------------------------------------------------------------------------

    Page 70962

    We estimate that the combined total 10-year present value cost of this NPRM to industry and Government is $144.669 million ($74.991 million for domestic owners or operators), discounted at 7 percent, and $179.434 million ($93.665 million for domestic owners or operators), discounted at 3 percent. We estimate that the combined annualized cost to industry and government is $20.598 million ($10.677 million for domestic owners or operators), based on a 7-percent discount rate, and $21.035 million ($10.980 million for domestic owners or operators), based on a 3-percent discount rate.

    Table 8 summarizes the combined 10-year cost of this NPRM to industry and the Government.

    Table 8--Total Cost of NPRM

    Per year

    ----------------------------------------------------------------------------------------------------------------

    Discounted costs

    Year Undiscounted -----------------------------------

    costs 7% 3%

    ----------------------------------------------------------------------------------------------------------------

    1......................................................... 13,581,195 11,879,832 12,809,668

    2......................................................... 13,736,938 11,998,374 12,948,382

    3......................................................... 11,066,145 9,033,271 10,127,091

    4......................................................... 44,843,194 34,210,658 39,842,597

    5......................................................... 13,369,939 9,532,582 11,533,027

    6......................................................... 13,395,049 8,925,687 11,218,143

    7......................................................... 41,148,868 25,625,447 33,457,795

    8......................................................... 15,822,770 9,208,996 12,490,640

    9......................................................... 16,649,124 9,056,020 12,760,167

    10........................................................ 29,897,840 15,198,546 22,246,801

    -----------------------------------------------------

    Total................................................. 213,511,062 144,669,412 179,434,311

    -----------------------------------------------------

    Annualized................................................ 20,597,670 21,035,175

    ----------------------------------------------------------------------------------------------------------------

    Benefits

    As offshore drilling industry operations move farther offshore, maintaining vessel position and height becomes an increasingly more difficult task, especially as water depth precludes mooring. The vessel's position and height depend on an understanding of many variables, such as the speed and direction of waves and the wind, both of which can be very irregular at distances farther offshore. DP systems not only remove this uncertainty, they can also predict future changes in wave speed and direction based on current conditions.

    However, despite this advanced technology (and in some cases, because of this technology) a loss of position can still occur while operating under DP. Due to the high-risk environment that OSVs and MODUs work in, such a loss of position could result in catastrophic consequences. Property damage, environmental damages, and human casualties could occur in the event of a loss of position or propulsion.

    Table 9 presents the range of potential consequences at risk in the event of a DP loss of position or propulsion on a MODU, OSV, or crewboat.

    Table 9--Potential Monetary Consequences at Risk That Could Result From a DP System Loss of Position

    ----------------------------------------------------------------------------------------------------------------

    Consequence category Range of potential consequences

    ----------------------------------------------------------------------------------------------------------------

    Property Damage from Collision............. $5 million to $1 billion.

    Environmental Pollution.................... $5 million to $500 million.

    Riser Lost on Seabed....................... $7 million to $70 million.

    Pipe Bent or Buckled....................... $3 million to $30 million.

    Downtime from Production................... Up to $500 thousand per day.

    Loss of Life............................... $9.1 million per statistical life.

    ----------------------------------------------------------------------------------------------------------------

    At this time, the Coast Guard does not have a comprehensive source of information on changes in DP status and the resulting loss of position incidents, as vessels of all types currently do not have to report DP failures to the Coast Guard. A provision of this NPRM seeks to gather this data.

    The following incidents illustrate the potential consequences at risk if a position is lost during DP operations. In April 2010, the MODU DISCOVERER CLEAR LEADER experienced a DP system failure that resulted in a loss of position while conducting well control operations on the U.S. OCS. During the incident, the DPO was able to initiate a cease operations response, however, an emergency disconnect was required. Although the MODU's blow-out preventer was able to prevent a spill that could potentially have been on the magnitude of the DEEPWATER HORIZON incident, the subsea gear of the MODU suffered damages as a result of the MODU's loss of position. The Coast Guard's MISLE database lists property damages of $760,000 as a result of this incident. Further, the vessel experienced a loss of revenue during the time when its operations were suspended.

    In September 2012, a DP incident involving the construction OSV BIBBY TOPAZ occurred off the coast of Scotland. During dive support activities, the BIBBY TOPAZ suffered a DP system failure that resulted in a loss of position. At the time of the incident, three divers were in the water, and when the vessel experienced a loss of position, the umbilical cord of one of the divers was severed. The diver was unable to return to the diving bell and had to instead rely on his standby air tank for almost 40 minutes. When the rescue team found the diver, he was unconscious, although the team was able to revive him. While

    Page 70963

    this incident did not result in any fatalities, the vessel's loss of position put the lives of three divers at risk. The VSL of the lives that could have been lost as a result of this incident is $27,300,000. Although this incident did not take place in U.S. waters, dive support activities while operating under DP are regularly conducted on the U.S. OCS, with similar consequences at risk.

    Neither of these incidents capture fully the potential worst-case consequences of a loss of position that results from a collision under power of a MODU, OSV, or crewboat. The allision of the logistics OSV SAMUDRA SURAKSHA with a drilling platform illustrates the types and potential magnitude of worst-case consequences that could result from an OSV loss of position. In July 2005, the SAMUDRA SURAKSHA was transferring personnel off the coast of India when the vessel experienced a loss of position \54\ and collided with a platform, severing a gas riser in the process. Although an emergency shut-off of the gas riser was initiated, gas was released, resulting in an explosion and massive fire. Twenty-two crewmen lost their lives or went missing as a result of the explosion, which, when monetized at $9,100,000, amounts to $200,200,000. We use the fatalities as a reasonable worst-case scenario of the potential consequences at risk from a loss of position and resulting collision between vessels or platforms. The incident also had environmental damage, property damage and loss of production impacts.

    ---------------------------------------------------------------------------

    \54\ The vessel was equipped with DP but was not operating under DP at the time of the loss of position.

    ---------------------------------------------------------------------------

    This NPRM mitigates the risk of a DP loss of position in several ways. This NPRM provides other guidance on design and operation standards for all DP vessels. The development of decision support tools such as CAMOs and ASOC or WSOC would provide DPOs and DPOQs with a summarized and easy to understand guide on the limits to safe operating conditions, which would help DPOs and DPOQs react quicker to prevent or mitigate a loss of position while operating DP systems.

    Furthermore, requiring owners or operators of vessels using DP systems to examine DP failures and submit documents describing the time, location, and reason for why a system failure occurred will enable industry and the Coast Guard to better understand the causes of these failures and, in time, develop programs to prevent these same failures from occurring in the future. Additionally, this information can provide assistance to manufacturers and operators of DP systems in order to contribute to more efficient and safer DP systems and practices in the future.

    To better understand how many DP system incidents occur per year, we reviewed reports from the International Marine Contractors Association (IMCA), which collects and reports incidents of DP station-

    keeping incidents provided on a voluntary basis by its members. From 2004 through 2010, the IMCA lists 429 reported DP system incidents. However, this figure likely underestimates the number of DP system incidents that occurred because during that time period, members of the IMCA were not required to report station-keeping incidents. As a result of this under-reporting, we use the average rate per year at which DP system incidents occurred per vessel during that same time period, instead of the average number of DP incidents reported per year, since the rate is less likely to be influenced by the number of vessels reporting. Figure 1 displays the trend in the number of DP incidents reported to the IMCA from 2004 through 2010.

    GRAPHIC TIFF OMITTED TP28NO14.001

    Although reporting to the IMCA is voluntary, and therefore may not represent the true population mean of the entire affected population's DP incident rate, the IMCA data show that the rate of DP system incidents has remained relatively stable throughout the 7-year period studied, even as the number of vessels reporting has increased.\55\ This suggests that DP system incidents occur on a relatively

    Page 70964

    consistent basis (one to two times per vessel per year).

    ---------------------------------------------------------------------------

    \55\ Because this information was voluntarily provided to the IMCA, the reporting population may not be representative of the population as a whole. However, as the IMCA is the only organization that currently collects this data, it is the best data available at this time.

    ---------------------------------------------------------------------------

    The IMCA's report then categorizes the cause of each DP system incident that was reported as the fault of either: Environmental force, power/thrust equipment, DP equipment, or operator error. Figure 2 summarizes the categories as a percentage of the total number of DP system incidents that occurred from 2004 through 2010 (429 total).

    GRAPHIC TIFF OMITTED TP28NO14.002

    Although Figure 2 shows that only 13 percent of all DP system incidents are directly linked to operator error, nearly 94 percent could have been mitigated by attention to human factors--environmental faults could have been reduced through the development of a well defined ASOC or WSOC, power/thrust faults could have been mitigated through the development of a properly defined CAMO, DP system faults could have been reduced through the development of a well defined ASOC or WSOC, and operator faults could have been diminished through DPOs and DPOQs becoming more familiar and experienced with a vessel's ASOC or WSOC.\56\

    ---------------------------------------------------------------------------

    \56\ International Marine Contractors Association. ``Dynamic Positioning Station Keeping Incidents: Incidents reported for 2008 (DP system 19)''. Pg. 2.

    ---------------------------------------------------------------------------

    With regard to the nonhuman, factor-related elements of this NPRM, DP system incidents resulting from power generation or thrust faults could have been mitigated through the redundancy provided by DP-2, and by developing and maintaining a vessel's CAMO. A CAMO would ``identify the equipment configuration and methods of operation that ensure the vessel meets its maximum level of redundancy, functionality and operation and that no single fault will exceed the identified worst case failure.'' \57\ Additionally, a CAMO would define the most robust configuration for the vessel's power plant set-up, thrusters, power management, etc., thereby diminishing the likelihood that an incident could occur as a result of human negligence in designing the vessel's operating systems.

    ---------------------------------------------------------------------------

    \57\ International Marine Contractors Association. ``Guidance on Operational Activity Planning''. November 2012. Pg. 9.

    ---------------------------------------------------------------------------

    Furthermore, the development and maintenance of an ASOC or WSOC could reduce the probability that a DP system incident occurs as a result of a DP reference or DP computer fault. The ASOC or WSOC would define, among other things, ``maximum environmental operating conditions, maximum offsets permissible from the set point position, position reference systems, and auxiliary systems performance limits and failures.'' \58\ These guidelines would program the DP computer to signal to the DPO or DPOQ to cease operations whenever the vessel diverged from the maximum limits set in the ASOC or WSOC.

    ---------------------------------------------------------------------------

    \58\ IMCA. ``Guidance on Operational Activity Planning''. November 2012. Pg. 11.

    ---------------------------------------------------------------------------

    While the majority of DP system incidents are correctly identified and resolved through the DPO or DPOQ manually taking control of the system, inaction or delayed action can have immense consequences. If left unchecked, a DP incident could result in a loss of position or propulsion, a short circuit of the electrical equipment, and/or an emergency disconnect. These events could result in major property damage to the vessel and/or any surrounding vessels and facilities, lost revenue as a result of any downtime caused by damages, injury or loss of life, and/or environmental damage as a result of released oil or other chemicals.

    Table 10 provides greater detail on how each NPRM provision supports one of the four below categories:

    Design Standards and Classification;

    Operations;

    Manning and Training; and

    Reporting.

    Page 70965

    Table 10--Description of Benefits of the NPRM

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    Design standards & Manning & How provision reduces

    Key provision classification Operations training Reporting Description risk

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    33 CFR Part 140--Navigation and Navigable Waters

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    140.310 DP system personnel ................... .................. ............... ............... Requires all Codifies industry

    requirements. vessels that use standards that each

    a DP system to DPO and DPOQ must

    conduct OCS follow while

    activities to performing duties,

    have a DPO or which reduces the

    DPOQ who is likelihood of

    properly trained casualties occurring

    and has no other from operator fatigue,

    responsibilities inattention or

    outside of DP. inexperience.

    140.315 Minimum DP system ................... .................. ............... ............... Defines the Codifies industry

    training requirements. minimum training standards that each

    requirements that DPO and DPOQ must

    each DPO and DPOQ follow while

    must have before performing duties,

    operating a DP which reduces the

    system. likelihood of

    casualties occurring

    from inexperience.

    Requires owners or Enables compliance

    operators to make verification for this

    available their critical area to

    DPO's or DPOQ's ensure that each DPO

    course completion and DPOQ has received

    certificates for the proper training

    DP training. and has the necessary

    experience required to

    correctly operate a DP

    system in routine and

    emergency operations.

    140.320 DP system Manning ................... .................. ............... ............... Defines the Codifies industry

    requirements. minimum manning standards that each

    requirements to DPO and DPOQ must

    which all MODUs follow while

    must adhere while performing duties.

    using DP to Ensures that each DPO

    conduct OCS and DPOQ is

    activities. sufficiently rested

    and prepared to handle

    the challenges of

    operating a DP system.

    Ensures that each DPO

    or DPOQ is in direct

    communication with a

    licensed master and

    navigational watch at

    all times while a MODU

    is using dynamic

    positioning to conduct

    OCS activities,

    enabling correct

    actions for routine

    and emergency

    situations and thus

    reduce the likelihood

    of casualties

    occurring from

    personnel

    miscommunication.

    140.325 Operations.............. ................... .................. ............... ............... Requires all Provides a uniform

    vessels that use operating standard to

    a DP system to which all flag DP

    conduct OCS vessels must adhere.

    activities to This would reduce the

    meet the DP probability of

    Operation operator faults

    Standards in occurring as a result

    paragraph 4.4 IMO of a lack of

    MSC/Circ. 645. familiarity or

    experience with a DP

    operating system.

    140.330 Minimum design standards ................... .................. ............... ............... Requires all Provides design

    and testing. vessels that use standards to ensure a

    a DP system to fault tolerant, fault

    conduct OCS resistant DP vessel

    activities to that minimizes risk of

    meet the DP loss of position if

    Design Standards one component fails.

    in paragraph

    3.4.1 of IMO MSC/

    Circ. 645.

    140.335 Intermediate DP system ................... .................. ............... ............... Requires all Ensures that specifics

    requirements. applicable of system design,

    vessels to construction and

    conduct vessel operation are

    surveys and developed and tested

    maintain an FMEA, to ensure that

    FMEA proving test redundancy is actually

    document, and a achieved and systems

    CAMO. function as intended.

    Page 70966

    In addition to Ensures that all

    meeting the vessels and MODUs have

    minimum DP well documented course-

    Operating of-action and DP

    Requirements, all incident emergency

    MODUs and response plans for all

    applicable non- OCS activities.

    drilling vessels Reduces the

    must also probability that

    maintain a CAMO significant casualties

    and ASOC or WSOC, or property damage

    respectively, as could occur, since the

    described in the DP system would be

    MTS DP Operation programmed, following

    Guidelines. rigorous testing

    during the FMEA, to

    recognize maximum

    environmental

    conditions, maximum

    offsets permissible

    from the set position,

    position reference

    systems, and auxiliary

    systems.

    All applicable Provides Coast Guard

    vessels must officials with

    report a DP information on how

    system status often DP station-

    change from green keeping incidents

    to red or yellow occur and why, and

    to a DPSAO. enables the Coast

    Guard to ensure that

    operations can be

    resumed safely.

    All applicable Ensures that FMEAs,

    vessels must CAMOs, and ASOC or

    conduct a DP WSOC are updated based

    investigation on casualties to

    whenever the DP prevent similar DP

    status changes incidents from

    from green to occurring in the

    yellow or red and future. This would

    submit a summary reduce the probability

    from the that significant

    investigation to casualties or property

    the DPSAO damage could occur in

    indicating the future.

    whether the cause

    of the DP

    incident was

    addressed in the

    vessel's FMEA,

    CAMO, and ASOC or

    WSOC.

    All applicable Provides Coast Guard

    vessels must have officials with

    the DPSAO information on how and

    complete an why DP failures occur.

    annual DP This information

    incident provides valuable

    investigation feedback to ensure

    report. This that future such

    report would be incidents do not

    reviewed annually occur, which would

    by the OCS NCOE. reduce the probability

    of significant

    casualties or property

    damage from occurring

    in the future.

    All applicable Ensures that the Coast

    vessels must Guard is notified

    report a DP immediately of DP

    incident that incidents that result

    resulted in an in catastrophic

    emergency damages and/or

    disconnect and/or injuries and

    serious marine fatalities. This would

    incident to the allow the Coast Guard

    cognizant OCMI. to take immediate

    action if a serious

    event occurred, and to

    ensure that operations

    are not resumed until

    the cause of the

    incident has been

    addressed.

    Creates a new Ensures safe design and

    document, a operation for all

    DPVAD, which vessels that use a DP

    would be issued system while

    by DPSAO to MODUs conducting Critical

    and applicable OCS Activities.

    vessels other Ensures that FMEA and

    than MODUs that CAMO are developed and

    use a DP system maintained, which

    while conducting would reduce the

    Critical OCS likelihood of

    Activities. This significant casualties

    document would be or property damage

    issued after the from occurring in the

    vessel has future.

    completed its DP

    surveys.

    Page 70967

    140.340 Standard DP system ................... .................. ............... ............... Requires all Reduces probability of

    requirements. applicable a DP system failure

    vessels to obtain occurring by adding

    DP notation second component that

    equivalent to would be required to

    Equipment class 2 fail before system

    or higher from an failure.

    authorized

    classification

    society.

    140.345 Enhanced DP system ................... .................. ............... ............... In addition to Provides increased

    requirements. meeting the assuredness of safe

    design and design and operation

    operating for all vessels that

    requirements use a DP system to

    found in 140.335 conduct Critical OCS

    and 140.340, all Activities by

    MODUs and new requiring independent

    vessels other third party

    than MODUs of at verification of design

    least 6,000 GT and planned

    ITC must also operations. Ensures

    submit, and have that FMEA and CAMO are

    approved, the developed and

    vessel's design maintained, which

    and operating would reduce the

    plans by the likelihood of

    DPSAO that significant casualties

    conducted the or property damage

    vessel's initial from occurring in the

    survey. future.

    140.350 Operational control..... ................... .................. ............... ............... Permits the Ensures safe design and

    cognizant OCMI to operation for all

    suspend an vessels that use a DP

    applicable vessel system while

    from using DP, if conducting Critical

    the vessel is OCS Activities. This

    found to be not will reduce the

    in compliance likelihood of

    with the significant casualties

    requirements in or property damage

    this part. from occurring in the

    future.

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    46 CFR Part 61--Periodic Tests and Inspections

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    61.50-2 Surveys................. ................... .................. ............... ............... Requires all MODUs Ensures safe design and

    and applicable operation for all

    vessels other vessels that use a DP

    than MODUs that system to conduct

    use a DP system Critical OCS

    while conducting Activities by

    Critical OCS requiring independent

    Activities, to evaluation of systems.

    complete DP Periodic surveys

    surveys conducted ensure that FMEA and

    by a DPSAO. CAMO are maintained,

    which would reduce the

    likelihood of

    significant casualties

    or property damage

    from occurring in the

    future.

    Requires the DPSAO Allows Coast Guard

    conducting the officials the

    vessel's DP opportunity to

    survey to notify participate in DP

    the OMCI at least system surveys

    30 days prior to providing government

    the survey. oversight and quality

    control for third

    parties. The Coast

    Guards presence will

    verify and complement

    the findings of a

    third-party surveyor,

    thereby ensuring that

    DP system equipment is

    operational and

    properly maintained,

    which would reduce the

    likelihood of a loss

    of position occurring

    in the future.

    61.50-3 Acceptance of dynamic ................... .................. ............... ............... Creates Ensures that DPSAOs are

    positioning system assurance specifications highly qualified at

    organizations. that DPSAO must conducting an FMEA,

    meet in order to testing a vessel's

    receive approval CAMO and ASOC or WSOC,

    from the Coast and conducting DP

    Guard Outer failure

    Continental Shelf investigations. This

    National Center would reduce the

    of Expertise (OCS likelihood that

    NCOE) to conduct significant casualties

    DP surveys, FMEA or property damage

    testing, and plan occur because of a

    reviews. poorly created CAMO or

    ASOC or WSOC.

    Page 70968

    61.50-4 Oversight of dynamic ................... .................. ............... ............... All applicable Provides Coast Guard

    positioning system assurance vessels must have officials with

    organizations. the DPSAO information on how and

    complete an why DP failures occur.

    annual DP failure This information

    investigation provides valuable

    report. This feedback to ensure

    report would be that future such

    reviewed annually incidents do not

    by the OCS NCOE. occur, which would

    reduce the probability

    of significant

    casualties or property

    damage from occurring

    in the future.

    Further, this

    information would

    allow the Coast Guard

    to determine whether

    the DPSAO is still

    under compliance with

    the requirements

    necessary of an

    authorized DPSAO

    specified in 61.50-3.

    61.50-5, 61.50-10, 61.50-15 ................... .................. ............... ............... Requires all Ensures safe design and

    Initial, periodic, and annual vessels that use operation for all

    surveys of DP systems. a DP system to vessels that use a DP

    conduct Critical system to conduct

    OCS Activities to Critical OCS

    have surveys to Activities. Tests a

    ensure compliance vessel's FMEA and CAMO

    with DP system to ensure that they

    requirements. are developed and

    Additionally, maintained, which

    these sections would reduce the

    require that the likelihood of

    authorized DP significant casualties

    assurance or property damage

    organization from occurring in the

    conducting the future. Allows Coast

    survey notify the Guard officials the

    Coast Guard on opportunity to

    the location and participate in DP

    time of the system surveys. The

    survey. Coast Guards presence

    will verify and

    complement the

    findings of a third-

    party surveyor,

    thereby ensuring that

    DP system equipment is

    operational and

    properly maintained,

    which would reduce the

    likelihood of a loss

    of position occurring

    in the future.

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    46 CFR Part 62--Vital System Automation

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    62.20-2 Required plans for DP ................... .................. ............... ............... Requires all MODUs Ensures safe design for

    systems. that conduct all vessels that use a

    Critical OCS DP system to conduct

    Activities and Critical OCS

    all other vessels Activities by

    of at least 6,000 requiring that systems

    GT ITC that have be verified by

    installed a DP independent third

    system on or party, which would

    after the reduce the probability

    effective date of of significant

    this final rule casualties or property

    to submit a DP damage.

    system plan to Classification, plan

    assurance DPSAO. review and

    certification

    requirements serves as

    a fundamental building

    block for safe DP

    operations by ensuring

    a minimum level of

    reliability for a DP

    system verified by a

    qualified third party,

    particularly for

    higher risk vessels.

    Requires the DPSAO The Coast Guard's

    to submit a copy oversight would verify

    of the approved and complement the

    DP system plan, findings of a third-

    as well as the party surveyor,

    Annual Survey thereby ensuring that

    Document in DP system equipment is

    subsequent years, operational and

    to the commanding properly maintained,

    officer of the which would reduce the

    Marine Safety likelihood of a loss

    Center. of position occurring

    in the future. It

    would further provide

    for government

    oversight.

    62.25-40 Environmental design ................... .................. ............... ............... Incorporates IEC Reduces the risk of

    standards on OCS units. environmental pollution or a subsea

    standards into spill by ensuring that

    Title 46. design of DP system

    equipment meets

    environmental

    standards.

    Page 70969

    62.40-3, and 62.40-5, 62.40-10 ................... .................. ............... ............... Requires all Reduces probability of

    Design standards and vessels that use a DP system failure

    classification for DP systems a DP system to occurring, because a

    on OCS. conduct Critical DP-2 system must

    OCS Activities to maintain position at

    meet the DP all times, excluding

    Operation incidents involving

    Standards in IMO the loss of a

    MSC/Circ. 645 and compartment.

    recommend

    following the MTS

    DP Operation

    Guidelines.

    Requires all

    applicable

    vessels to obtain

    DP notation

    equivalent to

    Equipment class 2

    or higher from an

    authorized

    classification

    society.

    All applicable Ensures that all

    vessels must vessels and MODUs meet

    maintain an FMEA their maximum level of

    that demonstrates redundancy,

    compliance with functionality, and

    the applicable operation, and that no

    provisions of IMO single fault would

    MSC/Circ.645 for exceed the identified

    DP equipment worst-case failure.

    class 2 or higher. This would reduce the

    likelihood of

    significant casualties

    or property damage,

    since the DP system

    would alert the DPO or

    DPOQ before a worst-

    case failure occurs.

    62.40-15, 62.40-20 FMEA and FMEA ................... .................. ............... ............... Requires vessel Ensures that each

    proving test documents. owners or vessels' and MODUs' DP

    operators to system failure modes

    create and are assessed and

    maintain a tested to ensure that

    vessel's FMEA and limits are understood

    FMEA test proving and in compliance with

    document. regulations.

    62.40-25 Critical Activity Mode ................... .................. ............... ............... Requires owners or Ensures that all

    of Operation (CAMO). operators to vessels and MODUs meet

    develop and their maximum level of

    maintain a CAMO. redundancy,

    functionality, and

    operation and that no

    single fault would

    exceed the identified

    worst-case failure.

    This would reduce the

    likelihood of

    significant casualties

    or property damage,

    since the DP system

    would alert the DPO or

    DPOQ before a worst-

    case failure occurs.

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    Because DP is an emerging technology and there are no existing requirements for reporting DP incidents, we have casualty reports of uncertain quality, constraining our ability to conduct a casualty review. However, we attempt to quantify the potential benefits that are expected to result from the requirements in this NPRM using the best available information that we have gathered from various segments of industry. These benefits focus on damages only, and not on fatalities, injuries or environmental damage given the limitations in data noted.

    In publicly available documents (2004 through 2010), the IMCA estimates that an average of 1.45 DP incidents occur per vessel every year.\59\ Next, we estimate the number of DP incidents that are expected to occur given the forecasted population figures and the average DP incident rate per vessel per year.

    ---------------------------------------------------------------------------

    \59\ Although reporting to the IMCA is voluntary, we accept this average rate, as it is the best available data currently available.

    ---------------------------------------------------------------------------

    Next, we calculate the number of DP incidents that resulted in a loss of position and damages using IMCA station keeping incident reports provided from 2004 through 2010. The average percentage of incidents that resulted in vessel damages from 2004 through 2010 was 6 percent for non-drilling vessels and 4 percent for drilling vessels.

    Using the average percentage of incidents that result in vessel damage and the total number of incidents forecasted to occur during the 10-year period of our study, we then calculate the total cost that would occur to industry as a result of DP incidents. According to the MTS ``Reliability and Risk Analysis,'' for DP incidents that result in damages, ``the average incident cost for drilling is estimated to be $2 million, which includes rig downtime, possible damage, the possibility of a fishing job, and even the remote possibility of lost well control.'' \60\ We note that this cost does not take into account the possibility of injuries or loss of life that could result from DP incidents, and, therefore, is likely an underestimate. We then adjust this estimate to $2,902,891 to account for inflation that occurred between 1997 and 2013.\61\ For non-drilling vessels, we estimate that the cost per DP incident

    Page 70970

    that results in damages is $132,991.\62\ We calculated this figure by estimating the percentage difference between day rates for non-drilling vessels and drilling vessels, and then multiplying that percentage by the inflation adjusted total damages provided in the MTS ``Reliability and Risk Analysis.'' \63\

    ---------------------------------------------------------------------------

    \60\ Marine Technology Society. ``Reliability and Risk Analysis,'' Dynamic Positioning Conference. October 21-22, 1997. Page 29.

    \61\ Inflation Adjustment Calculation = > 2013 value =. The average annual CPI-U data was obtained from the BLS at http://stats.bls.gov/cpi/cpifiles/cpiai.txt.

    \62\ Calculation used = > x $2,902,891.

    \63\ Day rate for non-drilling vessel = $23,818. ``Dynamic Positioning System Research Task Order,'' by Rolling Bay, LLC August 2012. The average day rate for drilling vessels = $527,506.

    ---------------------------------------------------------------------------

    For DP incidents that do not result in damages, we calculate the cost to investigate the incident, as well as the lost revenue that would occur while the investigation was taking place. According to a Coast Guard Subject Matter Expert, it was determined that it would take an engineer 10 hours on average to investigate a DP incident, at an hourly loaded wage of $57.\64\ Further, the Coast Guard estimates that a non-drilling vessel would lose $10,070 of revenue per DP incident that does not result in any damages, and a drilling vessel would lose $219,794 of revenue per DP incident that does not result in any damages.\65\ This lost revenue would occur as a result of operations having to be stopped while the engineer conducts the DP incident investigation.

    Following this calculation (our baseline), we then calculate the cost of DP incidents following the effective date of our final rule. First, we needed to calculate the rate of DP incidents that are expected to occur after publication of a final rule. Based on roundtable conversations with owners and operators of DP vessels that operate on the U.S. OCS, we estimate that DP incidents would be reduced by 95 percent after adopting the MTS DP Operations guidance.\66\ If we assume that the vessels were experiencing the industry average number of incidents per year, 1.45, prior to adopting the MTS guidance, then a 95-percent reduction in DP incidents would equate to vessels experiencing only 0.0725 DP incidents per year following adoption of the MTS guidance.\67\ Using this new figure, we recalculated the number of DP incidents that are expected to occur given the forecasted population figures. However, we continue to use the original DP incident rate (1.45 incidents per vessel per year) for vessels that would not benefit from this proposed rule, or would not benefit from the proposed rule until the applicable phase-in date.

    ---------------------------------------------------------------------------

    \66\ This reduction is based on a decrease in the frequency of DP position-loss incidents, from a frequency of six DP position-loss incidents in 6 months prior to adoption of the MTS DP Operations guidance, to five position-loss incidents in 8 years following the adoption of the guidance.

    \67\ New DP incident rate per vessel per year = 1.45 x 0.05.

    ---------------------------------------------------------------------------

    After implementation of the NPRM, we estimate that 2,926 DP incidents for vessels other than MODUs (OSVs and crewboats) and 361 DP incidents for drilling vessels (MODUs) would be prevented over the 10-

    year period of our analysis.

    Using the same methodology that we used to calculate the cost of DP incidents that would occur without this proposed rule, we then estimate the total cost of DP incidents after implementation of this proposed rule. We assume that the average percentage of DP incidents that result in damages remains the same.

    We estimate that the reduction in the occurrence of DP failures would result in avoided damages of $115.849 million ($28.375 million to owners or operators of domestic vessels), discounted at a 7-percent rate, and $146.289 million ($37.050 million to owners or operators of domestic vessels), discounted at a 3-percent rate, over the 10-year period of our analysis. The annualized benefits are estimated to be $16.494 million ($4.040 million to owners or operators of domestic vessels), discounted at a 7-percent rate, and $17.150 ($4.343 million to owners or operators of domestic vessels), discounted at a 3-percent rate.

    Table 11 summarizes the total damages avoided that would accrue to industry from issuing this NPRM. These avoided damages would accrue from a reduction in the frequency of DP failures, which would reduce vessel downtime, possible damage, and the possibility of lost well control. These benefits do not reflect the potential reduction in the risk of injuries or fatalities that would likely occur after implementation of this NPRM. Figure 3 supplements Table 11 by providing a graphical representation of the difference between the cumulative total costs incurred by noncompliant vessels prior to the issuance of a final rule, and the cumulative total costs incurred by noncompliant vessels after issuance of a final rule.

    Table 11--Total 10-Year Avoided Damages From NPRM

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    Undiscounted benefits Discounted benefits Annualized benefits

    ---------------------------------------------------------------------------------------------------------------

    Time period Vessels other Drilling

    than MODUs vessels Total 7% 3% 7% 3%

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    Total Damages from DP Incidents prior to $105,234,662 $126,218,084 $231,452,746 $157,200,830 $194,581,898 $22,381,862 $22,810,935

    DP System Rule.........................

    Total Damages from DP Incidents after DP 51,101,224 3,746,191 54,847,415 41,351,452 48,293,037 5,887,517 5,661,417

    System Rule............................

    Estimated Benefits from Following MTS 54,133,438 122,471,893 176,605,331 115,849,378 146,288,861 16,494,345 17,149,517

    Guidance...............................

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    * Numbers may not add due to rounding.

    * Dollar figures are in 2013 terms.

    Page 70971

    GRAPHIC TIFF OMITTED TP28NO14.003

    Request for Comment

    We request additional comments on our benefit model assumptions. Information is specifically requested on the following:

    (1) Frequency of changes in DP status from green to red, and green to yellow;

    (2) The rate of DP incidents that result in damages and the type and amount of these damages;

    (3) The effectiveness of the proposed rule in reducing DP incidents, loss of position, and resulting consequences; and

    (4) Case studies on DP incidents that resulted in a loss of position.

    DATES: Comments and related material must be submitted to the online docket via http://www.regulations.gov or reach the Docket Management Facility on or before February 26, 2015. Comments sent to the Office of Management and Budget (OMB) on collection of information must reach OMB on or before February 26, 2015.

    ADDRESSES: Submit comments using any one of the listed methods, and see SUPPLEMENTARY INFORMATION for more information on public comments.

    Online--http://www.regulations.gov following Web site instructions.

    Fax--202-493-2251.

    Mail--Docket Management Facility (M-30), U.S. Department of Transportation, West Building Ground Floor, Room W12-140, 1200 New Jersey Avenue SE., Washington, DC 20590-0001.

    Hand delivery--mail address, 9 a.m. and 5 p.m., Monday through Friday, except Federal holidays (telephone 202-366-9329).

    Comparison of Costs vs. Benefits

    We estimate that the total annualized net cost of this NPRM is $4.219 million ($6.680 million to domestic owners or operators), discounted at a 7-percent rate, and $3.930 million ($6.653 million to domestic owners or operators), discounted at a 3-percent rate. Tables 12 and 13 summarize the net costs that would be incurred as a result of the publication of this NPRM. Figure 4 then compares the cumulative net present value, using a 7-percent discount rate, as a result of publication of this NPRM to the net present value of not requiring the provisions in this NPRM (i.e., the baseline).

    Table 12--Total Cumulative Net Present Value From NPRM

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    Discounted costs Discounted benefits Net present value

    Year -------------------------------------------------------------------------------------------------------------------

    7% 3% 7% 3% 7% 3%

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    1................................... $11,879,832 $12,809,668 $8,008,721 $8,319,739 ($4,683,985) ($4,865,887)

    2................................... 23,878,206 25,758,050 16,568,099 17,556,832 (8,122,981) (8,577,177)

    3................................... 32,911,477 35,885,141 25,319,946 27,368,422 (8,404,405) (8,892,677)

    4................................... 67,122,135 75,727,738 36,404,432 40,277,695 (31,530,576) (35,826,001)

    5................................... 76,654,716 87,260,764 49,473,907 56,089,844 (27,993,683) (31,546,879)

    6................................... 85,580,403 98,478,907 62,079,796 71,933,404 (24,313,481) (26,921,461)

    7................................... 111,205,850 131,936,702 75,965,563 90,063,319 (36,053,161) (42,249,341)

    8................................... 120,414,846 144,427,343 89,321,957 108,179,291 (31,905,763) (36,624,010)

    9................................... 129,470,866 157,187,510 102,476,664 126,714,614 (27,807,076) (30,848,853)

    10.................................. 144,669,412 179,434,311 115,849,378 146,288,861 (29,632,908) (33,521,407)

    -------------------------------------------------------------------------------------------------------------------

    Total........................... 144,669,412 179,434,311 115,849,378 146,288,861 (29,632,908) (33,521,407)

    -------------------------------------------------------------------------------------------------------------------

    Annualized.......................... 20,597,670 21,035,175 16,494,345 17,149,517 4,219,059 3,929,732

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    Page 70972

    Table 13--Comparison of Annualized Benefits and Costs to Industry and Government

    7-Percent discount rate

    ----------------------------------------------------------------------------------------------------------------

    Rule Cost to industry Total benefits Net benefits

    ----------------------------------------------------------------------------------------------------------------

    DP System NPRM...................................... $20,597,670 $16,494,345 ($4,219,059)

    ----------------------------------------------------------------------------------------------------------------

    * Numbers may not add due to rounding.

    * Dollar figures are in 2013 terms.

    GRAPHIC TIFF OMITTED TP28NO14.004

    These net benefits do not include the potential reduction in the number of injuries or fatalities that would likely occur after publication of this NPRM. As a result, these net benefits are likely to be underestimated.

    Breakeven Analysis

    Based on monetized benefits from reduction in property damage and lost productivity, the NPRM would not result in positive net benefits. However, our monetized estimates do not include benefits that would accrue to society from reducing the risk of fatalities or environmental damage from an oil spill that could result from a catastrophic DP event, such as a collision with a MODU during drilling operations caused by a DP-related loss of position. It is likely then, that we have underestimated the total benefits that would result from this proposed rule. Unfortunately, because of data limitations, we are unable to calculate the risk of a catastrophic event causing fatalities or oil spills that would be prevented as a result of requiring the provisions in this proposed rule. Instead, we estimate the number of fatalities that would need to be prevented per year in order for this proposed rule to be cost neutral, by using the value of a statistical life (VSL).\68\ Using the VSL to monetize the value of fatalities and fatalities prevented, the NPRM would need to prevent 0.5 fatalities per year from occurring during the 10-year period for net benefits to equal the net cost of this NPRM.

    ---------------------------------------------------------------------------

    \68\ Value of a statistical life is currently measured at $9.1 million. ``Guidance on Treatment of the Economic Value of a Statistical Life,'' prepared for the U.S. Department of Transportation, April 2013. http://www.dot.gov/sites/dot.dev/files/docs/VSL%20Guidance%202013.pdf.

    ---------------------------------------------------------------------------

    Table 14 summarizes this breakeven analysis.

    Table 14--Expand DP Systems in OCS NPRM, Breakeven Analysis

    7 percent, annualized

    ------------------------------------------------------------------------

    Fatalities

    NPRM requirement Annualized net prevented to

    cost breakeven

    ------------------------------------------------------------------------

    Total for NPRM requirements........... ($4,219,059) 0.46

    ------------------------------------------------------------------------

    The consequences of a loss of position while using DP can be high. In order to put this breakeven analysis in perspective, we consider and compare the impacts of two events to illustrate potential worst case scenarios that could result from a DP-related loss of position. First, as an example of the fatalities that could result from a loss of position and subsequent collision, we use the SAMUDRA SURAKSHA incident as a reasonable worst case scenario. In order

    Page 70973

    for this proposed rule's benefits to equal its costs, one worst case event on the magnitude of the SAMUDRA SURAKSHA which resulted in 22 fatalities, would need to be prevented approximately every 48 years to breakeven.\69\

    ---------------------------------------------------------------------------

    \69\ We acknowledge that the SAMUDRA SURAKSHA incident would not be avoided or its consequences mitigated as a result of this proposed rule since it involved a foreign flag vessel operating in foreign waters.

    ---------------------------------------------------------------------------

    A loss of position and collision could result in a catastrophic oil spill if a MODU is involved and the blowout preventer does not engage or fails (as was the case during the DEEPWATER HORIZON). The DEEPWATER HORIZON oil spill illustrates the potential environmental damage that could result from an oil spill from an uncontrolled well. The DEEPWATER HORIZON incident resulted in an estimated 4.9 million barrels of oil spilled. To date, the responsible party has spent $14 billion on cleanup costs alone. This estimate of cleanup costs does not include additional restoration costs under the Natural Resource Damage Assessment process or other liabilities or settlements.\70\ Assuming a $14 billion cleanup cost for a reasonable worst case catastrophic oil spill, the proposed rule would have to prevent one such event every 1,000 years to breakeven.

    ---------------------------------------------------------------------------

    \70\ ``Active Shoreline Cleanup Operations from Deepwater Horizon Accident End'', press release from BP, 15 April 2014, available at: http://www.bp.com/en/global/corporate/press/press-releases/active-shoreline-cleanup-operations-dwh-accident-end.html.

    ---------------------------------------------------------------------------

    Alternatives

    We examined several alternatives with varying degrees of vessel applicability and required provisions. Of the alternatives examined, we selected the alternative that provided industry with the largest amount of flexibility without sacrificing maritime safety. The Coast Guard considered the following alternatives:

    Proposed Alternative (NPRM);

    Alternative 2: Grandfathering all existing non-drilling DP vessels;

    Alternative 3: No Grandfathering and No Phase-in Period;

    Alternative 4: Proposed Alternative Plus Additional DP Manning Requirements for non-drilling vessels with new or upgraded DP systems; and

    Alternative 5: Alternative 3 Plus Additional DP Manning Requirements.

    Because of the frequency of DP-related incidents, as well as the potential for severe consequences that could occur as the result of an incident, the Coast Guard decided that the benefits that would be gained through requiring compliance from existing OSVs and crewboats would outweigh any additional costs that would be incurred by industry.

    In order to minimize the impact on existing OSVs and crewboats, the Coast Guard developed the proposed alternative, which uses a phase-in schedule to provide existing non-drilling vessels with some flexibility in meeting the provisions of this proposed alternative. Further, the Coast Guard decided to grandfather existing non-drilling vessels from being required to comply with the most costly provisions in this proposed rule--the provisions that would require a vessel using DP to use a DP-2 system or higher and obtain a DP-2 or high class notation.

    Through providing flexibility to existing OSVs and crewboats, the proposed alternative minimizes costs, without sacrificing benefits that could accrue from a larger population of vessels.

    Table 15 summarizes the alternatives considered. The costs and benefits displayed are for both total 10-year costs and benefits and the annualized cost and benefits discounted at a 7 percent annual rate. Because the net benefits do not include the potential reduction in the number of injuries or fatalities that are likely to occur after issuance of a final rule, Table 15 also includes the number of fatalities that would need to be prevented for the costs of this proposed rule to equal the benefits.

    Table 15--Comparison of Alternatives

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    Annualized cost Annualized Annualized net Number of fatalities

    Proposal (7% discount benefits (7% cost (7% discount needed to be prevented Impact of alternative

    rate) discount rate) rate) per year to breakeven

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    Proposed Alternative.................. $20,597,670 $16,494,345 ($4,219,059) 1 fatality per year..... Offers protection

    for 91% of crew from risk of

    DP failure.

    Mitigates risk for

    462 vessels.

    Reduces costs by

    allowing continued use of

    existing DP-1 systems as

    long as they meet good

    operational practices.

    Minimizes burden by

    allowing phase-in of

    operational requirements

    based on risk.

    Alternative 2......................... 13,307,230 13,688,325 (265,983) 0 fatalities per year... Offers protection

    for 51% of crew from risk of

    DP failure.

    Mitigates risk for

    205 vessels.

    Minimizes burden by

    grandfathering non-drilling

    vessels that have installed

    a DP system prior to the

    effective date of a final

    rule.

    Alternative 3......................... 25,718,386 21,699,818 (4,896,965) 1 fatality per year..... Offers protection

    for 100% of crew from risk

    of DP failure.

    Mitigates risk for

    528 vessels.

    Requires non-

    drilling vessels that have

    installed a DP system prior

    to the effective date of a

    final rule to comply with

    all operational requirements

    before issuance of final

    rule.

    Alternative 4......................... 137,508,218 16,494,345 (121,332,655) 14 fatalities per year.. Offers protection

    for 91% of crew from risk of

    DP failure.

    Page 70974

    Mitigates risk for

    462 vessels.

    Minimizes burden by

    allowing phase-in of

    operational requirements

    based on risk.

    Requires additional

    manning requirements for new

    builds that industry is

    unlikely to meet on its own.

    Alternative 5......................... 625,109,533 21,699,818 (608,728,065) 67 fatalities per year.. Offers protection

    for 100% of crew from risk

    of DP failure.

    Mitigates risk for

    528 vessels.

    Requires non-

    drilling vessels that have

    installed a DP system prior

    to the effective date of a

    final rule to comply with

    all operational requirements

    before issuance of final

    rule.

    Requires additional

    manning requirements for all

    vessels using DP that

    industry is unlikely to meet

    on its own.

    --------------------------------------------------------------------------------------------------------------------------------------------------------

    * Net Cost does not include avoided fatalities or other benefits of this proposed rule.

    * Numbers may not add due to rounding.

    * Dollar figures are in 2013 terms.

    Although Table 15 shows that Alternative 2, which would grandfather all existing non-drilling vessels from having to comply with this proposed rule, minimizes net costs, Alternative 2 would reduce the risk of a fatality the least out of all of the alternatives. This is because fewer vessels would benefit from the proposed requirements, and thus the probability of a DP incident, which could result in a fatality, would remain at its current rate for a majority of existing vessels using DP on the U.S. OCS. Furthermore, given the catastrophic damage potential of DP-related incidents from non-drilling vessels, the additional costs are relatively small. In Table 16, we summarize the risk of fatality addressed and the cost to address that risk in each of the alternatives.

    Table 16--Comparison of the Risk of Fatality Addressed by Alternative

    ----------------------------------------------------------------------------------------------------------------

    Percentage

    Crew with of

    Total crew subject risk of potential Annualized Cost per

    Proposal to risk of fatality fatality cost fatality risk

    fatality--baseline addressed risk addressed

    addressed

    ----------------------------------------------------------------------------------------------------------------

    Alternative 1..................... 5,119 4,675 91 $20,179,651 $4,316.50

    Alternative 2..................... 5,119 2,623 51 13,072,297 4,983.72

    Alternative 3..................... 5,119 5,119 100 24,990,468 4,881.90

    Alternative 4..................... 5,119 4,675 91 137,090,199 29,324.11

    Alternative 5..................... 5,119 5,119 100 624,381,615 121,973.36

    ----------------------------------------------------------------------------------------------------------------

    Table 16 shows that the cost to reduce the risk of a fatality occurring while a vessel is using DP is minimized under the proposed alternative.\71\

    ---------------------------------------------------------------------------

    \71\ To estimate this cost, we first derive the total number of crew members working onboard vessels which currently do not comply with this proposed rule in its entirety. Next, we calculate the number of crew members working on board vessels which would benefit from the provisions in each of the alternatives listed above. The cost to address this risk is then estimated by dividing the annualized cost of each alternative by the number of crew members expected to be on board vessels which would benefit from the provisions in each of the alternatives.

    ---------------------------------------------------------------------------

    Alternative 1: Proposed Alternative

    The analysis for this alternative is discussed in detail previously in this RA.

    Alternative 2: Grandfathering All Vessels Other Than MODUs With Existing DP Systems

    For this alternative, the Coast Guard would grandfather all vessels other than MODUs with existing DP systems, and OSVs and crewboats with an existing DP system would not be required to comply with any of the DP requirements in this NPRM. As a result, this would provide industry with the greatest amount of flexibility in meeting the requirements in the proposed alternative, because it would only require future OSVs and crewboats to comply with the provisions in this proposed rule, in addition to still requiring MODUs with existing and future DP systems to comply immediately with the provisions in the proposed alternative. This approach was created after taking into account the increased risk profile of MODUs, as well as current industry practices. By examining the existing population of MODU's vessel specification sheets, we determined that all existing MODUs operating on the U.S. OCS that utilize DP would comply with the most costly

    Page 70975

    provisions in this NPRM. Because of this, as well as the higher risk profile of MODUs, we elected not to grandfather in MODUs with existing DP systems as outlined in this alternative.

    We considered Alternative 2 because of the large proportion of OSVs and crewboats with existing DP systems that would not be compliant with the most costly DP provisions in this NPRM. However, because of the high risk potential of DP-related incidents, we decided that the benefits that would be gained through requiring compliance from existing OSVs and crewboats would outweigh the additional costs that would be incurred by industry.

    Alternative 3: No Grandfathering and No Phase-in Period

    For this alternative, the Coast Guard would require all vessels other than MODUs with existing DP Systems to comply with the requirements in this proposed rule immediately following issuance of a final rule. This alternative would affect the same number of existing OSVs and crewboats as in proposed alternative, but would not permit existing vessels to phase-in DP requirements.

    We considered this Alternative 3 because of the high probability that significant consequences could occur as a result of a DP failure. However, this alternative places a larger burden on industry that cannot be justified by either the added benefits that would be incurred by requiring the existing population of non-drilling vessels using DP to comply with the requirements in the NPRM immediately following publication of a final rule (the net cost of this alternative is greater than the proposed alternative), or the reducing the risk of death for a greater number of crew members. As a result, we rejected Alternative 3.

    Alternative 4: Additional DP Manning Requirements

    Under Alternative 4, all vessels, with the exception of MODUs, that have a new DP system would be required to have a DPO or DPOQ whose only responsibility is operating the DP system.

    We rejected this alternative because industry is unlikely to comply with the additional DP manning requirements in the absence of this NPRM. As such, industry would incur large costs that would not be justified by the benefits.

    Alternative 5: Additional DP Manning Requirements With No Grandfathering

    Alternative 5 would also require additional DP manning requirements, but would not grandfather vessels other than MODUs that have an existing DP system. Because industry is not currently complying with this requirement and is not expected to comply with it in the future, we expect that this provision would burden industry with large costs that would likely force a large number of vessels out of the market. We, consequently, rejected this alternative.

  26. Small Entities

    In accordance with the Regulatory Flexibility Act (5 U.S.C. 601-

    612), the Coast Guard prepared this Initial Regulatory Flexibility Analysis (IRFA) that examines the impacts of the NPRM on small entities (5 U.S.C. 601 et seq.). Due to the anticipated impacts on small businesses, Coast Guard is including an analysis of the NPRM requirements for informational purposes.

    A small entity may be--

    A small independent business, defined as any independently owned and operated business not dominant in its field that qualifies as a small business per the Small Business Act (5 U.S.C. 632);

    A small not-for-profit organization; and

    A small governmental jurisdiction (locality with fewer than 50,000 people).

    An IRFA addresses the following:

    A description of the reasons why action by the agency is being considered;

    A succinct statement of the objectives of, and legal basis for, the proposed rule;

    A description of and, where feasible, an estimate of the number of small entities to which the proposed rule will apply;

    A description of the projected reporting, recordkeeping and other compliance requirements of the proposed rule, including an estimate of the classes of small entities which will be subject to the requirement and the type of professional skills necessary for preparation of the report or record;

    An identification, to the extent practicable, of all relevant Federal rules which may duplicate, overlap or conflict with the proposed rule; and

    A description of any significant alternatives to the proposed rule which accomplish the stated objectives of applicable statutes and which minimize any significant economic impact of the proposed rule on small entities.

    1. Description of the Reasons Why Action by the Agency Is Being Considered

    Agencies take regulatory action for various reasons, one of which is the failure of markets to reach socially optimal outcomes. The market failures prompting this proposed rule result from the absence of economic incentives that promote an optimal outcome.

    The absence of economic incentives that promote an optimal outcome results in a negative externality. A negative externality is an adverse byproduct of a transaction not accounted for within the transaction. In this case, MODUs and other vessels that use DP to engage in OCS activities that operate with lower safety standards may cause harm or increased risk of harm to human safety and the environment. The cost of these lower safety standards (increased risk) is not completely borne by the OSV or MODU owners, so they are external to the business decisions of these owners. The crew, which may face increased risk from lower safety standards, may not have any say in safety-related decisions. Since the crew may be adversely affected by business decisions which it may not be able to mitigate through increasing its price (labor cost), it absorbs the cost of the externality (increased risk from lower safety standards) which is a market failure. Oil spills that result from OSV or MODU accidents also impose an externality in the form of environmental damage and clean-up costs that are not borne directly by the OSV and MODU owners.

    2. Succinct Statement of the Objectives of, and Legal Basis for, the Proposed Rule

    Establishing these minimum standards is necessary to improve the safety of people and property involved in such operations, and the protection of the environment in which they operate. This proposed rule would decrease the risk of a loss of position by a dynamically-

    positioned MODU or other vessel that could result in a fire, explosion, or subsea spill, and supports the Coast Guard's strategic goals of maritime safety and protection of natural resources.

    Several sections of the Outer Continental Shelf Lands Act (43 U.S.C. 1331-1356a,) provide ``the Secretary of the Department in which the Coast Guard is operating'' with rulemaking authority. The Secretary's authority under all these sections is delegated to the Coast Guard through Department of Homeland Security Delegation No. 0170.1, paragraph II(90).

    43 U.S.C. 1333(d)(1) gives the Secretary ``authority to promulgate and enforce such reasonable regulations with respect to lights and other warning devices, safety equipment, and other matters relating to the promotion of safety of life and property on the

    Page 70976

    artificial islands, installations, and other devices referred to in subsection (a) of this section or on the waters adjacent thereto, as the Secretary may deem necessary.'' The Coast Guard interprets section 1333(d)(1) as conferring authority to regulate any OCS vessel or facility (collectively referred to as ``OCS unit'') attached to the OCS seabed or engaged in OCS activity to support such a unit.\72\

    ---------------------------------------------------------------------------

    \72\ OCS activity is defined in 33 CFR 140.10 to mean ``any offshore activity associated with exploration for, or development or production of, the minerals of the Outer Continental Shelf.''

    ---------------------------------------------------------------------------

    Section 1347(c) requires promulgation of ``regulations or standards applying to unregulated hazardous working conditions related to activities on the outer Continental Shelf when . . . such regulations or standards are determined to be necessary'' and authorizes the modification ``from time to time'' of ``any regulations, interim or final, dealing with hazardous working conditions on the Outer Continental Shelf.'' Section 1348(c) requires promulgation of regulations for onsite scheduled or unscheduled inspections of OCS facilities ``to assure compliance with . . . environmental or safety regulations.'' Additionally, section 1356 calls for regulations requiring, with limited exceptions, all OCS units to be manned by U.S. citizens or resident aliens and to comply with ``such minimum standards of design, construction, alteration, and repair'' as the Secretary or the Secretary of the Interior establishes.

    3. Description of and, Where Feasible, an Estimate of the Number of Small Entities To Which the Proposed Rule Will Apply

    Through review of the Coast Guard's MISLE database, as well as comparing owners' annual revenues to the small business threshold as defined by the Small Business Administration, we determined the number of small entities within drilling and non-drilling owners that would be affected by this proposed rule. We did not find any drilling or non-

    drilling vessels owned by governments or non-profits.

    Table 17 provides the SBA's revenue thresholds for the entities that are affected by this proposed rule. We used these standards in our analysis to determine which entities should be defined as small.

    Table 17--Standard Size of Revenue of Entities Affected by NPRM

    ------------------------------------------------------------------------

    Description of NAICS Standard size of

    NAICS code group revenue

    ------------------------------------------------------------------------

    213112........................ Support Activities $7,000,000

    for Oil and Gas

    Operations.

    487210........................ Water Transportation 7,000,000

    Excursion.

    488330........................ Navigation Services 35,000,000

    to Shipping.

    488390........................ Other Support 35,000,000

    Activities for Water

    Transportation.

    522220........................ Sales Financing...... 7,000,000

    532411........................ Commercial Air, Rail, 7,000,000

    and Water

    Transportation

    Equipment Rentals

    and Leasing.

    541990........................ All Other 14,000,000

    Professional

    Scientific and

    Technical Services.

    ------------------------------------------------------------------------

    Through this analysis, we determined that all existing MODUs, 60 percent of all existing OSVs of at least 500 GT ITC, 58 percent of all existing OSVs less than 500 GT ITC, and 63 percent of all existing crewboats exceed these small business standards.\73\

    ---------------------------------------------------------------------------

    \73\ We have separated our analysis of OSVs into OSVs of at least 500 GT ITC and OSVs under 500 GT ITC in order to account for the phase-in schedule which would only require OSVs of at least 500 GT ITC to meet more stringent DP requirements.

    ---------------------------------------------------------------------------

    The following tables summarize our findings.

    Table 18--Size of MODUs Affected by NPRM

    ------------------------------------------------------------------------

    Number Number

    of of

    owners vessels

    ------------------------------------------------------------------------

    Entities with Data--Above Threshold................. 2 4

    Entities with Data--Below Threshold................. 0 0

    Total Small Entities................................ 0 0

    -------------------

    Total............................................. 2 4

    Percentage of Small Entities........................ 0.0% 0.0%

    ------------------------------------------------------------------------

    The annual revenue for MODU owners that would be affected by this proposed rule is within a range of $875,000,000 to $3,000,000,000. Our results indicate that all drilling vessels using DP and currently operating on the U.S. OCS exceed the small business standards presented in Table 17.

    Next, we examined publicly available revenue data for owners and operators of OSVs of at least 500 GT ITC that use DP while operating on the U.S. OCS. These vessels would be required to comply with a majority of the provisions of this proposed rule by the date specified in Table 2 of this Regulatory Analysis section. Table 19 summarizes our analysis on owners or operators of OSVs of at least 500 GT ITC.

    Table 19--Size of OSVs of at Least 500 GT ITC Affected by NPRM

    ------------------------------------------------------------------------

    Number Number

    of of

    owners vessels

    ------------------------------------------------------------------------

    Entities with Data--Above Threshold................. 21 401

    Entities with Data--Below Threshold................. 14 56

    Total Small Entities................................ 14 56

    -------------------

    Total............................................. 35 457

    Percentage of Entities.............................. 40% 12%

    ------------------------------------------------------------------------

    Through our analysis, we estimate that approximately 40 percent of owners or operators of existing OSVs of at least 500 GT ITC that use DP are defined as small by the SBA threshold. The annual revenue stream of the entities affected by this proposed rule that are defined as small is within a range of $630,000 to $51,834,000.

    We then examined revenue data for owners or operators of OSVs less than 500 GT ITC. Although these owners or operators would incur some cost as a result of this proposed rule, existing vessels in this group would be

    Page 70977

    grandfathered from the most costly provisions.

    Table 20 describes the results of our analysis on the revenue streams of owners or operators of OSVs less than 500 GT ITC.

    Table 20--Size of OSVs Less Than 500 GT ITC Affected by NPRM

    ------------------------------------------------------------------------

    Number Number

    of of

    owners vessels

    ------------------------------------------------------------------------

    Entities with Data--Above Threshold................. 14 48

    Entities with Data--Below Threshold................. 10 23

    Total Small Entities................................ 10 23

    -------------------

    Total............................................. 28 71

    Percentage of Small Entities........................ 42% 32%

    ------------------------------------------------------------------------

    Using annual revenue data from public databases, we estimate that approximately 42 percent of the owners of vessels less than 500 GT ITC are small entities. The annual revenues for owners or operators defined as small entities range from $565,000 to $3,750,000. The median revenue per small entity owner is $3,109,500, while the mean revenue is $2,556,965.

    Lastly, we examined the revenue streams of owners or operators of crewboats that use DP on the U.S. OCS. Table 21 summarizes our findings.

    Table 21--Size of Crewboats Affected by NPRM

    ------------------------------------------------------------------------

    Number Number

    of of

    owners vessels

    ------------------------------------------------------------------------

    Entities with Data--Above Threshold................. 8 36

    Entities with Data--Below Threshold................. 3 7

    Total Small Entities................................ 3 7

    -------------------

    Total Entities.................................... 11 43

    Percentage of Small Entities........................ 27% 16%

    ------------------------------------------------------------------------

    Using annual revenue data from public databases, we estimate that approximately 27 percent of the owners or operators of crewboats are small entities. The annual revenues for crewboat owners or operators defined as small entities range from $162,000 to $2,200,000. The median revenue per small entity owner or operator is $1,081,000, while the mean revenue is $1,147,667. As with OSVs less than 500 GT ITC, however, these vessels would be grandfathered from having to comply with the most costly provisions in this proposed rule.

    4. A Description of the Projected Reporting, Recordkeeping and Other Compliance Requirements of the Proposed Rule, Including an Estimate of the Classes of Small Entities That Would Be Subject to the Requirement and the Type of Professional Skills Necessary for Preparation of the Report or Record

    In general, this proposed rule would require owners or operators of vessels that use DP on the U.S. OCS to--

    Make available to the OCMI upon request a copy of a DPO/

    DPOQ's certificate of completion of DP training courses;

    Use DP-2 or higher systems if conducting Critical OCS Activities; \74\

    ---------------------------------------------------------------------------

    \74\ Or choose to not operate with DP.

    ---------------------------------------------------------------------------

    Receive a DP-2 class notation;

    Conduct an FMEA;

    Develop and maintain a CAMO and ASOC or WSOC;

    Report DP system incidents to an authorized DP assurance organization;

    Conduct DP incidents investigations whenever the DP system status changes from green to yellow or red;

    Report Serious Marine Incidents that result from a DP incident to the OCMI;

    Submit a copy of a DP incident investigation report to the OCMI annually;

    Report the time and location of a DP survey to the OCMI at least 30 days prior to the survey; and

    Submit a copy of the vessel's DP system plan if the vessel is a MODU or of at least 6,000 GT ITC.

    Our research indicates that all MODUs and OSVs that plan on using DP on the U.S. OCS will be built with a DP-2 system even in the absence of this proposed rule. Further, all existing MODUs that use DP on the U.S. OCS already are operating with DP-2 or higher systems. Lastly, because existing OSVs and crewboats would be grandfathered from having to comply with this requirement, we anticipate that only one future crewboat owner per year could potentially incur this cost. Therefore, this provision is expected to have a minimal impact on industry as a whole.

    To determine the impact of this proposed rule on an individual owner or operator, we calculated the expected cost for the vessel categories examined above to comply with all applicable provisions.

    Expected Cost to MODUs

    Because all drilling (MODU) owners or operators exceed the small business threshold and the expected cost to these owners or operators is estimated to be well below their annual revenue streams, we instead begin our analysis with the expected cost to owners or operators of OSVs of at least 500 GT ITC.

    Expected Cost to OSVs of at Least 500 GT ITC

    We estimate that the total first-year cost of this NPRM to noncompliant owners or operators of existing OSVs of at least 500 GT ITC would be $286,835 per vessel. Table 22 summarizes the cost per provision to these noncompliant vessels.

    Table 22--First-Year Costs to an Existing Non-Compliant OSV of at Least

    500 GT ITC

    ------------------------------------------------------------------------

    First year

    Requirement cost

    ------------------------------------------------------------------------

    Make Available DPO/DPOQ Training Certificates........... $114.40

    Replace DP-1 Crewboats.................................. 0.00

    Cost to receive DP-2 Class Notation..................... 0.00

    Conduct an FMEA......................................... 275,000.00

    Develop a CAMO and ASOC................................. 9,120.00

    Report DP System Incidents.............................. 177.87

    Conduct DP Incident Investigation And Write Report...... 2,236.19

    Report Serious Marine Incidents Resulting from DP 3.46

    Incident...............................................

    Submit Annual DP Incident Investigation Report.......... 169.10

    Obtain DPVAD............................................ 10.25

    Report DP Surveys....................................... 4.10

    Page 70978

    Submit DP Systems Plan.................................. 0.00

    ---------------

    Total............................................... 285,835.36

    ------------------------------------------------------------------------

    * Numbers may not add due to rounding.

    * Dollar figures are in 2013 terms.

    After a review of the Coast Guard's MISLE database, as well as vessel profiles that are publicly available on company Web sites, we estimate that roughly 50 percent of existing OSVs that would be phased-

    in to the DP requirements of this proposed rule would incur this entire cost. We estimate that the remaining owners or operators of existing OSVs affected by this proposed rule would incur a cost of $1,062.36 per vessel.\75\

    ---------------------------------------------------------------------------

    \75\ These vessels are expected to already comply with the FMEA, CAMO and ASOC, and DP Investigation requirements.

    ---------------------------------------------------------------------------

    Additionally, through conversations with members of industry, we expect that 50 percent of future OSVs of at least 500 GT ITC would also incur the full cost displayed in Table 22. Like the existing population, the rest are expected to incur a cost of $1,062.

    We then use the population estimates in Table 3 of this Regulatory Analysis section to calculate the expected first-year cost to an owner or operator of an OSV of at least 500 GT ITC.

    Using the expected value formula,

    Expected First-Year Cost =

    ((247 existing DP vessels no compliance x $286,835)

    + (265 existing DP vessels partial compliance x $1,062)

    + (418 existing vessels without DP x $0)

    + (12 future DP vessels no compliance x $286,835)

    + (17 future DP vessels partial compliance x $1,062))/(959 Total Vessels Affected)

    we estimate that the expected average first-year cost as a result of this proposed rule to owners or operators of OSVs of at least 500 GT ITC would be $77,778.88.

    Using this expected average first-year cost, we then estimate the first-year revenue impact to the small entities that we identified in Table 19. During the first-year of implementation, we estimate that 71 percent of these 14 owners or operators would incur a cost less than 5 percent of their annual revenue stream. The remaining 28 percent would incur costs less than 13 percent of their annual revenue stream.

    Table 23--First-Year Revenue Impact to Small Entities That Own OSVs of

    at Least 500 GT ITC

    ------------------------------------------------------------------------

    Impact

    from

    Revenue impact range first

    year

    costs

    ------------------------------------------------------------------------

    Expected cost per vessel..................................... $77,779

    0% IEC 60092-504--Electrical Installation in Ships--Part 504: Special Features--Control and Instrumentation Third Edition, 2001 (``IEC 60092-504'')

    IMO Circular 645--Guidelines for Vessels with Dynamic Positioning Systems, 1994 (``IMO MSC/Circ.645'')

    Marine Technology Society DP Operations Guidance (``MTS DP Operations Guide''), Part 1, October 2010

    Marine Technology Society DP Operations Guidance (``MTS DP Operations Guide''), Part 2, Appendix 1, March 2012

    Marine Technology Society DP Operations Guidance (``MTS DP Operations Guide''), Part 2, Appendix 2, July 2012

    Marine Technology Society DP Operations Guidance (``MTS DP Operations Guide''), Part 2, Appendix 3, July 2012

    The proposed sections that reference these standards and the locations where these standards are available are listed in 33 CFR 140.7, and 46 CFR 61.03-1, and 62.05-1. If you disagree with our analysis of the voluntary consensus standards listed above or are aware of voluntary consensus standards that might apply but are not listed, please send a comment to the docket using one of the methods under ADDRESSES. In your comment, please explain why you disagree with our analysis and/or identify voluntary consensus standards we have not listed that might apply.

  27. Environment

    We have analyzed this NPRM under Department of Homeland Security Management Directive 023-1 and Commandant Instruction M16475.lD, which guide the Coast Guard in complying with the National Environmental Policy Act of 1969 (NEPA)(42 U.S.C. 4321-4370f), and have made a preliminary determination that there are no factors in this case that would limit the use of a categorical exclusion under section 2.B.2 of the Instruction. Therefore, this NPRM is categorically excluded from further environmental documentation under figure 2-1, paragraphs (34)(a),(c),(d), and (e) of the Instruction, which exclude regulations that are editorial or procedural and regulations concerning: Internal agency functions or organization; training, qualifying, licensing and disciplining of maritime personnel; manning, documentation, inspection and equipping of vessels; and equipment approval and carriage requirements. This NPRM is also categorically excluded under paragraph 6(a) of the Appendix to National Environmental Policy Act: Coast Guard Procedures for Categorical Exclusions, Notice of Final Agency Policy, published in the Federal Register on July 23, 2002 (67 FR 48243), which excludes regulations concerning vessel operation and safety standards. The environmental impact associated with requiring additional equipment, training, and improved facilities will be insignificant. An ``Environmental Analysis Check List'' is available in the docket by following the instructions in the ``Viewing comments and documents'' section above.

    List of Subjects

    33 CFR Part 140

    Continental shelf, Incorporation by reference, Investigations, Marine safety, Occupational safety and health, Penalties, Reporting and recordkeeping requirements.

    33 CFR Part 143

    Continental shelf, Marine safety, Occupational safety and health, Vessels.

    33 CFR Part 146

    Continental shelf, Marine safety, Occupational safety and health, Reporting and recordkeeping requirements, Vessels.

    46 CFR Part 61

    Incorporation by reference, Reporting and recordkeeping requirements, Vessels.

    46 CFR Part 62

    Incorporation by reference, Reporting and recordkeeping requirements, Vessels.

    For the reasons discussed in the preamble, the Coast Guard proposes to amend 33 CFR parts 140, 143, and 146, and 46 CFR parts 61 and 62 as follows:

    Title 33--Navigation and Navigable Waters

    PART 140--GENERAL

    0

    1. The authority citation for part 140 continues to read as follows:

    Authority: 43 U.S.C. 1333, 1348, 1350, 1356; Department of Homeland Security Delegation No. 0170.1.

    0

    2. Revise Sec. 140.7 to read as follows:

    Sec. 140.7 Incorporation by reference.

    (a) Certain material is incorporated by reference into this part with the approval of the Director of the Federal Register under 5 U.S.C. 552(a) and 1 CFR part 51. To enforce any edition other than that specified in this section, the Coast Guard must publish a notice of change in the Federal Register and the material must be available to the public. All approved material is available for inspection at the U.S. Coast Guard, Office of Design and Engineering Standards (CG-ENG), 2703 Martin Luther King Jr. Ave., SE., Stop 7509, Washington, DC 20593-

    7509, and is available from the sources listed below. It is also available for inspection at the National Archives and Records Administration (NARA). For information on the availability of this material at NARA, call 202-741-6030, or go to http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.

    (b) American National Standards Institute (ANSI), 11 West 42nd Street, New York, NY 10036, http://www.ansi.org/.

    (1) ANSI A10.14-1975--Requirements for Safety Belts, Harnesses, Lanyards, Lifelines, and Drop Lines for Construction and Industrial Use, IBR approved for Sec. 142.42.

    Page 70986

    (2) ANSI/UL1123-1987--Standard for Marine Buoyant Devices, IBR approved for Sec. 143.405.

    (3) ANSI Z41-1983--American National Standard for Personal Protection-Protective Footwear, IBR approved for Sec. 142.33.

    (4) ANSI Z87.1-1979--Practice for Occupational and Educational Eye and Face Protection, IBR approved for Sec. 142.27.

    (5) ANSI Z88.2-1980--Practices for Respiratory Protection, IBR approved for Sec. 142.39.

    (6) ANSI Z89.1-1981--Safety Requirements for Industrial Head Protection, IBR approved for Sec. 142.30.

    (c) International Maritime Organization (IMO), 4 Albert Embankment, London SE1 7SR, +44 (0)20 7735 7611, http://www.imo.org. (1) IMO Assembly Resolution A.414 (XI) Code for Construction and Equipment of Mobile Offshore Drilling Units, IBR approved for Sec. Sec. 143.207 and 146.205.

    (2) IMO MSC/Circ.645--Guidelines for Vessels with Dynamic Positioning Systems, 1994 (``IMO MSC/Circ.645''), IBR approved for Sec. 140.325.

    (3) The International Convention on Standards of Training, Certification and Watchkeeping for Seafarers, 1978, as amended (the STCW Convention or the STCW), IBR approved for Sec. 140.320.

    (4) The Seafarers' Training, Certification and Watchkeeping Code, as amended (the STCW Code), IBR approved for Sec. 140.320.

    (d) Marine Technology Society (MTS), 1100 H Street NW., Suite LL-

    100, Washington, DC 20005, 202-717-8705, http://www.mtsociety.org.

    (1) MTS DP Operations Guidance for MODUs (March 2012), Project Construction Vessels (July 2012), Logistics Vessels (July 2012), IBR approved for Sec. 140.335.

    (2) Reserved.

    0

    3. Add new subpart D, consisting of Sec. Sec. 140.300 through 140.350, to read as follows:

    Subpart D--Dynamic Positioning Systems

    Sec.

    140.300 Applicability.

    140.305 Definitions.

    140.310 DP system personnel requirements.

    140.315 DP system training requirements.

    140.320 DP system manning requirements.

    140.325 Operations.

    140.330 Minimum DP system requirements.

    140.335 Intermediate DP system requirements.

    140.340 Standard DP system requirements.

    140.345 Enhanced DP system requirements.

    140.350 Operational Control.

    Subpart D--Dynamic Positioning Systems

    Sec. 140.300 Applicability.

    This subpart applies to all MODUs and vessels other than MODUs that use a dynamic positioning (DP) system to engage in Outer Continental Shelf (OCS) activities on the U.S. OCS.

    Sec. 140.305 Definitions.

    The following definitions apply throughout this subpart:

    Activity Specific Operating Criteria (ASOC) means criteria that set out the operational, environmental, and equipment performance limits considered necessary for safe dynamic positioning (DP) system operations while carrying out a specific activity. The ASOC sets out various levels of operator action as these limits are approached or exceeded and varies depending on the activity. The ASOC defines whether the DP system must be configured in its Critical Activity Mode of Operation (CAMO) during that specific activity. If the CAMO is required for that specific activity, the ASOC will require the vessel to cease operations when an equipment failure makes operation in CAMO impossible.

    Critical Activity Mode of Operation (CAMO) means a tabulated presentation of how to configure the vessel's DP system, including power generation and distribution, and propulsion and position reference systems, so that the DP system as a whole is fault-tolerant and fault-resistant. The CAMO is validated by a Failure Modes and Effects Analysis (FMEA) proving test at the initial survey described in Sec. 61.50-5 of this subchapter.

    Critical OCS Activities means OCS activities where maintaining station is critical because a loss of position could cause a personal injury, environmental pollution, or catastrophic damage. See Sec. 140.10 of this subchapter for the definition of OCS activity.

    Critical OCS Activities on a MODU means OCS activities where a loss of position could cause a major process safety incident, such as a loss of well control where flow reaches the MODU, or water. These OCS activities include but are not limited to: Well test and completion operations; running non-sheareables such as drill collars through the Blowout Preventer (BOP); and an OCS activity on a well where hydrostatic balance is lost and BOP rams are used to maintain well control. The Coast Guard may identify other activities that fall within this definition.\83\ Each MODU that engages in Critical OCS Activities must include those activities in the MODU's WSOC.

    ---------------------------------------------------------------------------

    \83\ The Coast Guard would provide industry with advance notice and an opportunity to provide input before determining that additional activities meet the definition of critical OCS activities on a MODU.

    ---------------------------------------------------------------------------

    Critical OCS Activities on Vessels Other than MODUs means OCS activities where a loss of position could cause a serious marine incident as defined by 46 CFR 4.03-2. These OCS activities include but are not limited to: OCS activities where loss of position risks a collision with a production riser; transfer of oil or other hazardous material while underway; personnel transfer between vessels or structures while underway; and engaging in diving support or remotely operated vehicle operations when maintaining station is critical. The Coast Guard may identify other activities that fall within this definition.\84\ Each vessel that engages in Critical OCS Activities must include those activities in the vessel's ASOC.

    ---------------------------------------------------------------------------

    \84\ The Coast Guard would provide industry with advance notice and an opportunity to provide input before determining that additional activities meet the definition of critical OCS activities on vessels other than MODUs.

    ---------------------------------------------------------------------------

    Dynamic Positioning Operator or DPO means a mariner who holds a credential as a rating forming part of the navigational watch, able seafarer-deck, operational-level deck officer, chief mate, master, a rating forming part of the engineering watch, able seafarer-engine, operational-level engineer officer, second engineer, or chief engineer; and has completed the applicable training requirements of 33 CFR 140.310 and, if applicable, 33 CFR 140.315.

    Dynamic Positioning Operator, Qualified or DPOQ means a mariner who holds a credential as a rating forming part of the navigational watch, able seafarer-deck, operational-level deck officer, chief mate, master, rating forming part of the engineering watch, able seafarer-engine, operational-level engineer officer, second engineer, or chief engineer; has completed the applicable training requirements of 33 CFR 140.310 and, if applicable, Sec. 33 CFR 140.315 for that specific vessel; and has obtained the written endorsement of the vessel's DPO and master for that specific DP system.

    Dynamic Positioning System or DP System is defined in 46 CFR 62.10-

    1.

    Direct communication, for purposes of 33 CFR 140.310 only, means being in the direct line of sight of the officer in charge of the navigational watch, or maintaining direct two-way communications by a convenient, reliable means, such as a predetermined

    Page 70987

    working frequency over a handheld radio.

    Dynamic Positioning System Assurance Organization or DPSAO means an organization approved by the Coast Guard under 46 CFR 61.50-3 to conduct independent verification that a MODU or other vessel's DP system is in compliance with applicable requirements contained in this subchapter.

    Vessels include, but are not limited to, Mobile Offshore Drilling Units (MODUs). Vessels other than MODUs that conduct certain activities or possess certain design characteristics means vessels that conduct such activities or possess such characteristics and are not MODUs.

    Well Specific Operating Criteria (WSOC) means criteria that set out the operational, environmental, and equipment performance limits considered necessary for safe DP system operations while operating on a well. The WSOC sets out various levels of operator action as these limits are approached or exceeded, and varies depending on the well or location. The WSOC defines when the DP system must be configured in its CAMO during drilling or production. If the CAMO is required for that specific activity, the WSOC will require the MODU to cease operations when an equipment failure makes operation in CAMO impossible.

    Sec. 140.310 DP system personnel requirements.

    (a) When using a dynamic positioning (DP) system to engage in Outer Continental Shelf (OCS) activities on the U.S. OCS, each mobile offshore drilling unit (MODU) or other vessel to which this subpart applies must have on board a sufficient number of Dynamic Positioning Operators (DPOs) and Dynamic Positioning Operators, Qualified (DPOQs) to meet the following operational requirements:

    (1) DPO and DPOQs must meet the rest hour requirements in 46 CFR 15.1111.

    (2) DPOQs operating the DP system must be under the direct supervision of a DPO.

    (3) A DPO or DPOQ must be available at the DP operating station.

    (b) Determination of the number of DPOs and DPOQs must take into account the nature of the DP operations and the operational requirements of the DP system.

    (c) On a MODU or other vessel using a DP system to engage in OCS activities on the U.S. OCS, navigational watches must be maintained at all times as required in Sec. 140.320 of this subpart. The DPO or DPOQ must be in direct communication with the officer in charge of the navigational watch during DP system operations. Nothing in this section is to be interpreted as relinquishing or lessening the responsibility of the master and watchstanding officer(s) to ensure the safe navigation and/or operation of the vessel.

    (d) When using a DP system to engage in OCS activities on the U.S. OCS, each MODU or other vessel must have a properly trained DPO operating the DP system or directly supervising a DPOQ operating the DP system.

    (e) A DPOQ on each MODU or other vessel using a DP system to engage in OCS activities on the U.S. OCS may operate the DP system on that specific MODU or other vessel only after meeting the training and practical experience requirements for that vessel and being endorsed in writing by the DPO and master of that MODU or other vessel.

    (f) While operating the DP system pursuant to paragraph (d) of this section, the mate or officer of the watch may also serve as the DPO provided the mate or officer holds the appropriate credential and the DP system control systems are collocated with the navigational equipment.

    Sec. 140.315 DP system training requirements.

    (a) The Dynamic Positioning Operator (DPO) must receive training and practical experience in the operation of the dynamic positioning (DP) system and its components. The content of training and experience must include all provisions of paragraph (b) of this section, and the following:

    (1) The DP system components, including the control station, power generation and management, propulsion units, position reference systems, heading reference systems, environmental reference systems, and external force reference systems, such as hawser tension gauges.

    (2) The range of routine DP operations, as well as the handling of DP faults, failures, incidents, and emergencies, to ensure that operations are continued or terminated safely.

    (3) The type and purpose of documentation associated with DP operations, such as operational manuals, Failure Modes and Effects Analysis (FMEAs), and capability plots.

    (b) To be qualified to operate a DP system, the Dynamic Positioning Operator, Qualified (DPOQ) must have--

    (1) Completed training that provides an introduction to the functions and use of a DP system;

    (2) Completed 30 days of DP system training on board a vessel equipped with a DP system, including training on the design, components, related and integrated shipboard systems, system redundancy alarms, and warnings for that specific vessel's DP system;

    (3) Demonstrated thorough knowledge of the DP system operating manual for the specific vessel on which the DPOQ will serve, including procedures for shifting the DP system between all normal operational modes and emergency procedures. A DPOQ who will serve on a vessel engaging in Critical Outer Continental Shelf (OCS) Activities must also demonstrate thorough knowledge of the industrial mission, including the Critical Activity Mode of Operations, and either the Activity Specific Operating Criteria or Well Specific Operating Criteria as defined in 46 CFR 62.10-1.

    (4) Demonstrated a fundamental understanding of the specific DP system's FMEA and its implications; and

    (5) Demonstrated familiarity with the vessel's specific DP system, including participating in a walkthrough of the design and mechanical features with the DPO, to include at a minimum--

    (i) Power generation;

    (ii) Power distribution;

    (iii) Thruster units and associated equipment;

    (iv) Power management/logic; and

    (v) DP system control interfaces and related electronics and computer functions.

    (c) DPOs and DPOQs must carry the original copy of their DP system record of training or be able to provide such a copy to a requesting authority within 48 hours of the request.

    (d) The Coast Guard will accept company letters, course completion certificates from a training institution, letters or course completion certificates from the DP system manufacturer, or certification from an industry-accepted organization as proof of DP system training.

    (e) The owner or operator of a U.S.-documented seagoing vessel using a DP system to maintain station must maintain a copy of each DPO and DPOQ training record in accordance with 46 CFR 15.1107.

    (f) All onboard DP system training must be documented in each mariner's record of training in accordance with 46 CFR 15.1107.

    (g) The master, officers in charge of a navigational watch, and DPOs must be familiar with the characteristics of the vessel and the specific equipment fitted on it prior to operating the equipment as required in 46 CFR 15.405. This

    Page 70988

    familiarization must include reading the DP system equipment and operations manual, DP system incident reports, FMEAs, and any documented history of the DP system. The familiarization must be documented.

    Sec. 140.320 DP system manning requirements.

    (a) All Mobile Offshore Drilling Units (MODUs) and other vessels to which this subpart applies must--

    (1) Be under the command of an individual holding an appropriate certificate of competency as a master issued by the Flag State authority; and

    (2) Maintain navigational watches with an adequate number of mates or officers in charge of a navigational watch holding an appropriate certificate of competency issued by the Flag State authority.

    (b) Each person assigned duties as master, mate, or officer in charge of a navigational watch must meet the hours of rest requirements in Regulation VIII/1 of the STCW Convention and Section A-VIII/1 of the STCW Code (both incorporated by reference, see Sec. 140.7 of this part) .

    (c) All MODUs using a dynamic positioning (DP) system to engage in Outer Continental Shelf (OCS) activities on the U.S. OCS must hold a manning certificate specifying the minimum complement necessary to maintain the navigational watches. The manning complement must meet the requirements in paragraph (a) of this section and Sec. 140.310 of this part. The manning complement may be determined after considering the specialized nature of each MODU, including the limitations and capabilities of the DP system.

    Sec. 140.325 Operations.

    (a) Owners or operators of Mobile Offshore Drilling Units (MODUs) and other vessels to which this subpart applies must maintain a Dynamic Positioning (DP) System Operations Manual that complies with paragraph 4.4 of IMO MSC/Circ.645 (incorporated by reference, see Sec. 140.7).

    (b) The owner, operator, or master of each MODU or other vessel to which this subpart applies must ensure that all DP System Operations Manuals, including manufacturers' manuals, are available to the Dynamic Positioning Operator (DPO) at or near the DP system console when using a DP system to engage in OCS activities.

    (c) When conducting vessel-to-vessel transfer operations using a DP system--

    (1) Operational procedures for conducting oil or hazardous material transfers in DP mode must follow the transfer procedures in 33 CFR 155.750 and must include emergency procedures for securing operations and executing emergency breakaway;

    (2) Vessel masters and, as appropriate, chief engineers must--

    (i) Determine which vessel will be designated to maintain a geographic position;

    (ii) Ensure that all watchstanders of all vessels other than MODUs understand their responsibility to maintain a designated relative position to or remain clear of the vessel maintaining the geographic position;

    (iii) Complete a Declaration of Inspection before beginning transfer operations; and

    (iv) Reconcile any differences between the emergency procedures in each vessel's DP System Operations Manual;

    (3) Vessel personnel must establish voice communications between participants to determine--

    (i) The vessel designated as the controlling station;

    (ii) The controlling station DPO coordination responsibility;

    (iii) Primary and alternate communication channels;

    (iv) An emergency-only channel that can be monitored uninterrupted for the duration of the procedure;

    (v) The acquisition and assessment of regular weather forecast information for the area of operations; and

    (vi) The sharing with other active vessels of weather information, assessment of prevailing conditions, and use of onboard weather forecasting instruments;

    (4) When a MODU or other vessel to which this subpart applies uses a DP system to conduct vessel-to-vessel transfers with a vessel that is using a different DP system equipment class, the criteria for action in any emergency situation will be based on the least redundant DP system;

    (5) Any crew member on a MODU or other vessel conducting a vessel-

    to-vessel transfer operation using a DP system for station keeping must execute a ``stop operations'' command if they identify a situation that warrants such action;

    (6) Each unit's DPO must keep the bridge personnel of the other units, as defined in 33 CFR 140.10, involved in the vessel-to-vessel transfer fully advised of all alarm or emergency situations, including, but not limited to, DP system operations that could affect the operation in progress; and

    (7) During an emergency or the sounding of a general alarm, pumping operations must cease until the problem has been resolved.

    Sec. 140.330 Minimum DP system requirements.

    Vessels to which this subpart applies must, at a minimum, satisfy the provisions of 33 CFR 140.310, 140.315, 140.320, 140.325 and 46 CFR 62.40-3. Vessels that must comply with the intermediate, standard, or enhanced DP system requirements in Sec. Sec. 140.335, 140.340, and 140.345 must also comply with the provisions of this section.

    Sec. 140.335 Intermediate DP system requirements.

    (a) Vessels other than MODUs of more than 500 GT ITC (500 GRT if GT ITC not assigned) that use a dynamic positioning (DP) system installed before 30 DAYS AFTER DATE OF PUBLICATION OF FINAL RULE to engage in Critical Outer Continental Shelf (OCS) Activities on the U.S. OCS must comply with the provisions of this section no later than the applicable date in table 140.335 of this section.

    (b) Vessels that must comply with the standard or enhanced DP system requirements in Sec. Sec. 140.340 and 140.345 must also comply with the provisions of this section.

    Table 140.335--Phase in Schedule for Vessels (Except MODUs) With

    Existing DP Systems

    ------------------------------------------------------------------------

    Tonnage of vessels other than MODUs Date requirements effective

    ------------------------------------------------------------------------

    At least 1,900 GT ITC..................... Date of Final Rule + 3

    years.

    At least 900 GT ITC....................... Date of Final Rule + 6

    years.

    Greater than 500 GT ITC (500 GRT if GT ITC Date of Final Rule + 9

    not assigned). years.

    ------------------------------------------------------------------------

    (c) Vessels to which this section applies must meet the requirements of--

    (1) 46 CFR 61.50 (Survey);

    (2) 46 CFR 62.40-15 (FMEA);

    (3) 46 CFR 62.40-20 (FMEA Proving Test Document); and

    (4) 46 CFR 62.40-25 (CAMO).

    (d) The DP System Operations Manual for a vessel other than a MODU to which this section applies must also meet section 4.8 of the MTS DP Operations Guide (incorporated by reference, see Sec. 140.7) for either project/construction vessels or logistics vessels, as appropriate. The DP System Operations Manual for a vessel other than a MODU must contain Activity Specific Operational Criteria (ASOC) applicable to the operations performed by the vessel.

    (e) The DP System Operations Manual for a MODU to which this section applies must also meet section 4.7 of the MTS DP Operations Guide for MODUs

    Page 70989

    (incorporated by reference, see Sec. 140.7). The DP System Operations Manual on a MODU must contain Well Specific Operational Criteria (WSOC) applicable to the operations performed by the MODU.

    (f) Vessels to which this section applies must define a Critical Activity Mode of Operation (CAMO) for use during Critical OCS Activities. The CAMO must be included in the DP System Operations Manual required by this section.

    (g) Vessels other than MODUs to which this section applies must operate in accordance with the ASOC applicable to its operation every time the DP system is used, regardless of whether or not the particular operation is a Critical OCS Activity. A MODU must use a WSOC when operating on a well.

    (h) Vessels to which this section applies must configure the DP system in its CAMO when engaging in Critical OCS Activities as defined in 33 CFR 140.305.

    (i) In the event that a vessel to which this section applies experiences a reactive change of DP status from green to yellow or red as described in the applicable MTS DP Operations Guidance and defined by the vessel's ASOC or WSOC, the owner or operator of the vessel must report this DP incident to the DPSAO that conducted the DP surveys required under 46 CFR 61.50. For each such DP incident, the owner or operator of the vessel must conduct an investigation as described in section 4.11 of the MTS DP Operations Guide for MODUs or section 4.12 for either project/construction vessels or logistics vessels, as appropriate (incorporated by reference, see Sec. 140.7) and send an investigation summary to the DPSAO that issued the DPVAD to the vessel. Each DP incident investigation summary must include--

    (1) The cause of the DP incident and whether it was addressed by the vessel's FMEA, Well Specific Operating Criteria (WSOC) or Activity Specific Operating Criteria (ASOC), and Critical Activity Mode of Operation (CAMO), and lessons learned for incorporation into revised documents; and

    (2) If the cause of the DP incident was not addressed by the vessel's FMEA, ASOC, WSOC, or CAMO, the changes that were made to those documents to address the cause(s) of the incident. This requirement is applicable whether or not the operation or activity at the time of the incident was a Critical OCS Activity.

    (j) Immediately after addressing safety concerns resulting from a DP incident, the owner or operator of the vessel must notify the cognizant OCMI verbally and by email of any DP incident reported under paragraph (i) of this section if the incident--

    (1) Involved a reactive change of DP status from green to red; and

    (2) Required an emergency disconnect from a well; or

    (3) Was a serious marine incident as defined by 46 CFR 4.03-2.

    (k) A vessel to which this section applies must be issued a Dynamic Positioning Verification Acceptance Document (DPVAD) by a DPSAO. The DPVAD describes the vessel's DP system particulars, the certificate's period of validity, the identification of the DPSAO, the requirements of this subpart that are being certified, the dates of the completed surveys required by paragraph (c) of this section, and the subsequent surveys required to maintain the certificate's validity.

    (l) A DPVAD issued under paragraph (k) of this section is valid for 5 years.

    (m) Alternative guidance may be used in lieu of the MTS DP Operations Guide to meet the requirements of paragraphs (d), (e) and (i) of this section if permitted by the Commandant (CG-ENG) to the extent and under conditions that will ensure a degree of safety comparable to or greater than that provided by use of the MTS DP Operations Guide.

    Sec. 140.340 Standard DP system requirements.

    (a) Vessels other than MODUs of 6000 GT ITC or less that use a DP system installed on or after 30 DAYS AFTER DATE OF PUBLICATION OF FINAL RULE to engage in Critical OCS Activities must comply with the provisions of this section and 33 CFR 140.335 and 140.330.

    (b) Vessels that must comply with the enhanced DP system requirements in Sec. 140.345 must also comply with the provisions of this section.

    (c) Vessels to which this section applies must meet--

    (1) 46 CFR 62.40-5 (Design);

    (2) 46 CFR 62.40-10 (Classification); and

    (3) 46 CFR 62.25-40 (Environmental Design).

    (d) Compliance with paragraphs (a) through (c) of this section must be verified by the DPSAO during the surveys required by 46 CFR 61.50 and documented on the DPVAD.

    Sec. 140.345 Enhanced DP system requirements.

    (a) The following vessels must comply with the provisions of this section:

    (1) Mobile Offshore Drilling Units (MODUs) that use a dynamic positioning (DP) system to engage in Critical Outer Continental Shelf (OCS) Activities on the U.S. OCS; and

    (2) Vessels other than MODUs of more than 6,000 GT ITC that use a DP system installed on or after 30 DAYS AFTER DATE OF PUBLICATION OF FINAL RULE to conduct Critical OCS Activities on the U.S. OCS.

    (b) Vessels to which this section applies must meet the requirements of this section, 33 CFR 140.330, 140.335, 140.340, and 46 CFR 62.20-2 (Required plans for DP systems).

    (c) Vessels to which this section applies must have the surveys required by 46 CFR 61.50 completed and have the plans required by 46 CFR 62.20-2 approved by a DPSAO prior to receiving a Dynamic Positioning Verification Acceptance Document (DPVAD) under 33 CFR 140.335(j).

    Sec. 140.350 Operational Control.

    If the Cognizant OCMI determines that a vessel is not in compliance with this part, the OCMI may require the owner or operator of a vessel to suspend use of DP to conduct an OCS activity until the OCMI determines that the vessel complies with this part.

    PART 143--DESIGN AND EQUIPMENT

    0

    4. The authority citation for part 143 continues to read as follows:

    Authority: 43 U.S.C. 1333(d)(1), 1348(c), 1356; 49 CFR 1.46; section 143.210 is also issued under 14 U.S.C. 664 and 31 U.S.C. 9701.

    0

    5. Revise Sec. 143.15 to read as follows:

    Sec. 143.15 Lights and warning devices.

    (a) OCS facilities, except when using DP systems defined by Sec. 140.305, must meet the lights and warning devices requirements under part 67 of this chapter concerning aids to navigation on artificial islands and fixed structures.

    (b) * * *

    (c) Vessels, including MODUs and attending vessels, using a DP system defined by Sec. 140.305 to maintain station, even when in contact of the seabed of the OCS, are considered underway and should display the lights and shapes for ``vessel restricted in her ability to maneuver'' as defined under Rule 3 of the International Regulations for Preventing Collisions at Sea 1972.

    PART 146-- OPERATIONS

    0

    6. The authority citation for part 146 continues to read as follows:

    Authority: 33 U.S.C. 1223, 1226; 43 U.S.C. 1333, 1348, 1350, 1356; Sec. 109, Pub. L. 109-347, 120 Stat. 1884; Department of Homeland Security Delegation No. 0170.1.

    0

    7. In Sec. 146.405 add paragraph (b)(4) to read as follows:

    Page 70990

    Sec. 146.405 Safety and Security notice of arrival for vessels arriving at a place on the OCS.

    * * * * *

    (b) * * *

    (4) Vessels to which 140.335 applies that use a dynamic positioning (DP) system, as defined by 140.305, must provide the following information from the Dynamic Positioning Verification Acceptance Document (DPVAD):

    (i) DPVAD period of validity; and

    (ii) Identification of the dynamic positioning system assurance organization, as defined in 140.305, that conducted surveys;

    Title 46--Shipping

    PART 61--PERIODIC TESTS AND INSPECTIONS

    0

    8. The authority citation for part 61 is revised to read as follows:

    Authority: 43 U.S.C. 1333; 46 U.S.C. 2103, 3306, 3307, 3703; sec. 617, Pub. L. 111-281, 124 Stat. 2905; E.O. 12234, 45 FR 58801, 3 CFR 1980 Comp., p. 277; Department of Homeland Security Delegation No. 0170.1.

    0

    9. Revise Sec. 61.03-1 to read as follows:

    Sec. 61.03-1 Incorporation by reference.

    (a) Certain material is incorporated by reference into this part with the approval of the Director of the Federal Register under 5 U.S.C. 552(a) and 1 CFR part 51. To enforce any edition other than that specified in this section, the Coast Guard must publish a notice of change in the Federal Register and the material must be available to the public. All approved material is available for inspection at the U.S. Coast Guard, Office of Design and Engineering Standards (CG-ENG), 2703 Martin Luther King Jr. Ave SE., Stop 7509, Washington, DC 20593-

    7509, and is available from the sources listed below. It is also available for inspection at the National Archives and Records Administration (NARA). For information on the availability of this material at NARA, call 202-741-6030 or go to http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.

    (b) ASTM International 100 Barr Harbor Drive, West Conshohocken, PA 19428-2959, http://www.astm.org.

    (1) ASTM D 665-98, Standard Test Method for Rust-Preventing Characteristics of Inhibited Mineral Oil in the Presence of Water, IBR approved for Sec. 61.20-17.

    (2) Reserved

    (c) International Maritime Organization (IMO), 4 Albert Embankment, London SE1 7SR, +44 (0)20 7735 7611, http://www.imo.org. (1) IMO MSC/

    Circ.645--Guidelines for Vessels with Dynamic Positioning Systems, 1994 (``IMO MSC/Circ.645''), IBR approved for Sec. Sec. 61.50-3, 61.50-5, 61.50-10, and 61.50-15.

    (2) Reserved

    (d) Marine Technology Society, 1100 H Street NW., Suite LL-100, Washington, DC 20005, 202-717-8705, http://www.mtsociety.org.

    (1) MTS DP Operations Guidance (``MTS DP Operations Guide''), Part 2, for MODUs (March 2012), Project Construction Vessels (July 2012), Logistics Vessels (July 2012), IBR approved for Sec. Sec. 61.50-5(a) and 61.50-10.

    (2) Reserved

    0

    10. Add new subpart 61.50, consisting of Sec. Sec. 61.50-1 through 61.50-20, to read as follows:

    Subpart 61.50--Dynamic Positioning System (DP System) Surveys and Dynamic Positioning System Assurance Organizations (DPSAO) for Vessels Operating on the Outer Continental Shelf.

    Sec.

    61.50-1 Applicability.

    61.50-2 Surveys of MODUs and vessels, other than MODUs.

    61.50-3 Acceptance of dynamic positioning system assurance organizations.

    61.50-4 Oversight of dynamic positioning system assurance organizations.

    61.50-5 Initial survey.

    61.50-10 Periodic survey.

    61.50-15 Annual survey.

    61.50-20 Appeals

    Subpart 61.50--Dynamic Positioning System (DP System) Surveys and Dynamic Positioning System Assurance Organizations (DPSAO) for Vessels Operating on the Outer Continental Shelf.

    Sec. 61.50-1 Applicability.

    (a) The following vessels must comply with the provisions of this subpart:

    (1) Vessels other than MODUs of more than 500 GT ITC (500 GRT if GT ITC not assigned) that use a dynamic positioning (DP) system installed before 30 DAYS AFTER DATE OF PUBLICATION OF FINAL RULE to conduct Critical Outer Continental Shelf (OCS) Activities, as defined in 33 CFR 140.305, on the U.S. OCS must comply with the provisions of this section no later than the applicable date in 33 CFR table 140.335;

    (2) Vessels other than MODUS that use a DP system installed on or after (30 DAYS AFTER DATE OF PUBLICATION OF FINAL RULE) to engage in Critical OCS Activities, as defined in 33 CFR 140.305, on the U.S. OCS; and

    (3) MODUs that use a DP system to conduct Critical OCS Activities, as defined in 33 CFR 140.305, on the U.S. OCS.

    (4) For purposes of this subpart, ``vessels'' includes, but is not limited to, MODUs. Vessels other than MODUs that conduct certain activities or possess certain design characteristics means vessels that conduct such activities or possess such characteristics and are not MODUs.

    Sec. 61.50-2 Surveys of MODUs and vessels, other than MODUs.

    (a) The owner or operator of a vessel to which this subpart applies must ensure that the dynamic positioning system surveys required by Sec. Sec. 61.50-5, 61.50-10, and 61.50-15 of this subpart are completed by a DPSAO and provide the cognizant Officer in Charge, Marine Inspection an opportunity to attend upon request. The DPSAO that conducts the surveys required by this subpart must notify the cognizant Officer in Charge, Marine Inspection at least 30 days in advance of the survey.

    (b) Alternative guidance may be used in lieu of the MTS DP Operations Guide to meet the survey requirements of Sec. 61.50-5(a) and Sec. 61.50-10(a) of this subpart if permitted by the Coast Guard Office of Design and Engineering Standards (Commandant (CG-ENG)) to the extent and under conditions that will ensure a degree of safety comparable to or greater than that provided by use of the MTS DP Operations Guide.

    Sec. 61.50-3 Acceptance of dynamic positioning system assurance organizations.

    (a) Each DPSAO, as described in Sec. 61.50-2 of this subpart, must be accepted by the Coast Guard Outer Continental Shelf National Center of Expertise (OCS NCOE). To be accepted, such an organization must apply to the OCS NCOE in writing for acceptance. The application must contain information demonstrating that the organization or society--

    (1) Has functioned as a recognized source to the industry of guidance on recommended practice through participation in industry groups (e.g., International Marine Contractors Association, Marine Technology Society, National Offshore Safety Advisory Committee);

    (2) Has functioned as a DP assurance provider to vessel owner, operators, charterers, etc., for at least 5 years in the role of DP Assurance with a documented, auditable history of providing Failure Modes and Effects Analysis (FMEA) and survey services on a wide variety of Mobile Offshore Drilling Units (MODUs) and vessels with different industrial missions;

    (3) Has a history of advising vessel owners, operators, and charterers and

    Page 70991

    providing guidance on appropriate corrective actions to address nonconformities and observations raised during DP trials and otherwise, to include incidents, casualties, and cases of nonconformity with DP class rules;

    (4) Has adequate resources, including research, technical, and managerial staff, to ensure appropriate updates and maintenance of internal DP guidelines, trials procedures, and survey requirements;

    (5) Has adequate resources and processes in place to ensure regular and adequate communications to the Coast Guard concerning recurring DP-

    related issues for purposes of trend analysis, reporting, and continuing development of rules and guidelines;

    (6) Uses personnel with a minimum of 5 years of experience for both FMEA and survey services;

    (7) Directly employs a number of surveyors adequate to meet Coast Guard survey requirements;

    (8) Has adequate criteria for hiring and qualifying surveyors and technical staff;

    (9) Has an adequate program for continued training and development of surveyors and technical staff. Training and development must be structured, measured, monitored, and auditable;

    (10) Maintains an internal quality system based on current industry quality standards (e.g., ANSI/ASQC Q9001, or equivalent);

    (11) Can determine whether MODUs and vessels, other than MODUs, comply with the DP requirements of the Coast Guard during appropriate surveys and DP trials;

    (12) Can monitor all activities related to surveys and plan reviews performed pursuant to 46 CFR parts 61 and 62 for consistency and required end-results;

    (13) Is not under the financial control of owners or builders of MODUs or vessels, other than MODUs, or of others engaged commercially in the manufacture, equipping, repair, or operation of MODUs or vessels, other than MODUs; and

    (14) Does not have any business interest in, or share of ownership of, any MODU or other vessel to which it provides DP assurance services.

    Sec. 61.50-4 Oversight of dynamic positioning system assurance organizations.

    (a) The OCS NCOE may periodically audit the records of DPSAOs with reasonable advance notice to determine whether such organizations continue to comply with the provisions of paragraph Sec. 61.50-3(a) of this subpart. The OCS NCOE may revoke acceptance after determining that such an organization no longer complies with the provisions of paragraph Sec. 61.50-3(a) of this subpart. Acceptance remains in effect until revoked by the OCS NCOE.

    (b) DPSAOs must submit an annual report to the OCS NCOE that contains each DP investigation summary reported to it under 33 CFR 140.335(i). The DPSAO must confirm in the report that each DP investigation summary complies with 33 CFR 140.335(i).

    (c) Where the OCS NCOE is not satisfied with the resolution of any DP incident contained in the report required by paragraph (b) of this section, the OCS NCOE:

    (i) will advise the cognizant OCMI who may exercise operational control under 33 CFR 140.350 and require the DPSAO and the owner or operator of a MODU or vessel other than MODU to satisfactorily resolve the cause of the DP incident; and,

    (ii) may initiate an audit of the DPSAO under paragraph (a) of this section.

    Sec. 61.50-5 Initial survey.

    (a) An initial survey, specified in paragraph 5.1.1.1 of IMO MSC/

    Circ.645 (incorporated by reference, see Sec. 61.03-1) and section 4.6 of the MTS DP Operations Guide for MODUs or section 4.7 for either project/construction vessels or logistics vessels, as appropriate (incorporated by reference, see Sec. 61.03-1), must be conducted on a Mobile Offshore Drilling Unit (MODU) or vessel other than a MODU to which this subpart applies. The initial survey must include a Failure Modes and Effects Analysis (FMEA) proving test using the dynamic positioning (DP) system FMEA proving test document described in Sec. 62.40-20 of this subchapter. The initial survey must identify the Critical Activity Mode of Operation (CAMO) defined in Sec. 62.10-1 of this subchapter.

    (b) DP system software, programmable controls, and alarm system logic must not be altered after satisfactory completion of the initial survey without the approval of the DPSAO described in Sec. 61.50-2 of this subpart. The DPSAO must notify the cognizant Officer in Charge, Marine Inspection of any approved alternation of software after an initial survey. The notification must include any changes to the vessel's FMEA or CAMO that resulted from the software change, if applicable.

    (c) The initial survey must be completed in accordance with Sec. Sec. 61.50-2 of this subpart.

    Sec. 61.50-10 Periodic survey.

    (a) A periodic survey, specified in paragraph 5.1.1.2 of IMO MSC/

    Circ.645 (incorporated by reference, see Sec. 61.03-1) and section 4.6 of the MTS DP Operations Guide for MODUs or section 4.7 for either project/construction vessels or logistics vessels, as appropriate (incorporated by reference, see Sec. 61.03-1), must be conducted on a vessel to which this subpart applies at intervals not exceeding 5 years. This survey is intended to verify compliance with IMO MSC/

    Circ.645 and the applicable requirements of this subchapter.

    (b) The periodic survey must be completed in accordance with Sec. Sec. 61.50-2.

    Sec. 61.50-15 Annual survey.

    (a) An annual survey, described in paragraph 5.1.1.3 of IMO MSC/

    Circ.645 (incorporated by reference, see Sec. 61.03-1), must be conducted on a vessel to which this subpart applies within the 3 months before or after each anniversary date of the initial survey. The annual survey must ensure that the dynamic positioning system has been maintained in accordance with applicable parts of IMO MSC/Circ.645 and is in good working order.

    (b) The annual survey must be completed in accordance with Sec. Sec. 61.50-2 this subpart.

    Sec. 61.50-20 Appeals

    (a) Any person directly affected by an action or decision of the Coast Guard Outer Continental Shelf Center of Excellence (OCS NCOE) taken under the regulations in this subchapter may request reconsideration of that action or decision. If still dissatisfied, that person may appeal the action or decision of the OCS NCOE within 30 days to the U.S. Coast Guard Deputy Commandant for Prevention (CG-5P). The Deputy Commandant for Prevention will issue a decision after reviewing the appeal submitted under this paragraph. Rulings of the Deputy Commandant for Prevention constitute final agency action.

    (b) An appeal to the Deputy Commandant for Prevention:

    (1) Must be made in writing, except in an emergency when a verbal appeal may be accepted;

    (2) Must describe the decision or action being appealed;

    (3) Must state the reasons why the action or decision should be set aside or modified; and

    (4) May contain any supporting documents and evidence that the appellant wishes to have considered.

    (c) Pending determination of any appeal, the action or decision appealed remains in effect, unless suspended by the Deputy Commandant for Prevention.

    Page 70992

    PART 62--VITAL SYSTEM AUTOMATION

    0

    11. The authority citation for part 62 continues to read as follows:

    Authority: 46 U.S.C. 3306, 3703, 8105; sec. 617, Pub. L. 111-

    281, 124 Stat. 2905; E.O. 12234, 45 FR 58801, 3 CFR, 1980 Comp., p. 277; Department of Homeland Security Delegation No. 0170.1.

    0

    12. In Sec. 62.01-5 revise paragraph (a) to read as follows:

    Sec. 62.01-5 Applicability.

    (a) Vessels. Except as described in Sec. 62.40-1 of this part, this part applies to self-propelled vessels of 500 gross tons or more that are certificated under 46 CFR subchapters D, I, or U and to self-

    propelled vessels of 100 gross tons or more that are certificated under 46 CFR subchapter H.

    * * * * *

    0

    13. Revise Sec. 62.05-1 to read as follows:

    Sec. 62.05-1 Incorporation by reference.

    (a) Certain material is incorporated by reference into this part with the approval of the Director of the Federal Register under 5 U.S.C. 552(a) and 1 CFR part 51. To enforce any edition other than that specified in this section, the Coast Guard must publish notice of change in the Federal Register and the material must be available to the public. All approved material is available for inspection at the U.S. Coast Guard, Office of Design and Engineering Standards (CG-ENG), 2703 Martin Luther King Jr. Ave SE., Stop 7509, Washington, DC 20593-

    7509, and is available from the sources below. It is also available for inspection at the National Archives and Records Administration (NARA). For information on the availability of this material at NARA, call 202-

    741-6030 or go to http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.

    (b) American Bureau of Shipping (ABS), ABS Plaza, 16855 Northchase Drive, Houston, TX 77060, http://www.eagle.org.

    (1) Rules for Building and Classing Steel Vessels, Part 4 Vessel Systems and Machinery (2003) (``ABS Steel Vessel Rules''), IBR approved for Sec. Sec. 62.25-30, 62.35-5, 62.35-35, 62.35-40, 62.35-50, and 62.50-30.

    (2) Reserved

    (c) International Electrotechnical Commission (IEC), 3, rue de Varembe, Geneva, Switzerland, +41 22 919 02 11, http://www.iec.ch.

    (1) IEC 60092-504 Electrical Installation in Ships--Part 504: Special Features--Control and Instrumentation (Third Edition, 2001-

    03)(``IEC 60092-504''), IBR approved for Sec. 62.25-40(b).

    (2) Reserved

    (d) International Maritime Organization (IMO), 4 Albert Embankment, London SE1 7SR, +44 (0)20 7735 7611, http://www.imo.org.

    (1) Resolution MSC/Circ.645--Guidelines for Vessels with Dynamic Positioning Systems, 1994 (``IMO MSC/Circ.645''), IBR approved for Sec. Sec. 62.40-3, 62.40-5(b), and 62.40-15.

    (2) Reserved

    (e) Marine Technology Society (MTS), 1100 H Street NW., Suite LL-

    100, Washington, DC 20005, 202-717-8705, http://www.mtsociety.org.

    (1) MTS DP Operations Guidance (``MTS DP Operations Guide''), Part 2, for MODUs (March 2012), Project Construction Vessels (July 2012), Logistics Vessels (July 2012), IBR approved for Sec. Sec. 62.40-5(a), and 62.40-15.

    (2) Reserved

    0

    14. Amend Sec. 62.10-1 by adding, in alphabetical order, the definitions of the terms ``Activity Specific Operating Criteria (ASOC)''; ``Capability Plot''; ``Consequence analyzer''; ``Critical Activity Mode of Operation (CAMO)''; ``Dynamic positioning system (DP system)''; ``Redundancy''; ``Vessels''; and ``Well Specific Operating Criteria (WSOC)'', to read as follows:

    Sec. 62.10-1 Definitions.

    (a) * * *

    Activity Specific Operating Criteria (ASOC) means criteria that set out the operational, environmental, and equipment performance limits considered necessary for safe dynamic positioning (DP) system operations while carrying out a specific activity. The ASOC sets out various levels of operator action as these limits are approached or exceeded and varies depending on the activity. The ASOC defines whether the DP system must be configured in its Critical Activity Mode of Operation (CAMO) during that specific activity. If the CAMO is required for that specific activity, the ASOC will require the vessel to cease operations when an equipment failure makes operation in CAMO impossible.

    * * * * *

    Capability Plot means a document that provides an indication of a vessel's DP station-keeping ability, expressed in a common format.

    Consequence analyzer means a software function that continuously performs an analysis of the vessel's ability to maintain its position and heading after a predefined, worst-case failure during operation. Possible consequences are based on the actual weather conditions, enabled thrusters, and power plant status.

    Critical Activity Mode of Operation (CAMO) means a tabulated presentation of how to configure the vessel's DP system, including power generation and distribution, and propulsion and position reference systems, so that the DP system as a whole is fault-tolerant and fault-resistant. The CAMO is validated by a Failure Modes and Effects Analysis (FMEA) proving test at the initial survey described in Sec. 61.50-5 of this subchapter.

    Dynamic positioning system (DP system) means a complete installation of components and systems that act together and is sufficiently reliable to provide vessel position-keeping capability. Any vessel using a DP system is considered a vessel underway, even if maintaining a fixed position. A DP system is comprised of the following sub-systems:

    (1) Power system, consisting of prime movers with necessary auxiliary systems and associated piping, generators, switchboards, and distribution system.

    (2) Thruster system, consisting of thrusters with drive units and associated auxiliary systems and piping, main propellers, and rudders (if all such thruster system parts are under the control of the DP system), thruster control electronics, manual thruster controls, and associated cabling and cable routing.

    (3) Control system, consisting of computer system, joystick system, sensor system, display system (operator panels), position reference system, and associated cabling and cable routing.

    * * * * *

    Redundancy means the ability of a component or system to maintain or restore its function when a single failure has occurred. For example, redundancy may be achieved by the installation of multiple components, systems, or alternate means that perform the same function.

    * * * * *

    Vessels include, but are not limited to, Mobile Offshore Drilling Units. Vessels other than MODUs that conduct certain activities or possess certain design characteristics means vessels that conduct such activities or possess such characteristics and are not MODUs.

    * * * * *

    Well Specific Operating Criteria (WSOC) means criteria that set out the operational, environmental, and equipment performance limits considered necessary for safe DP system operations while operating on a well. The WSOC sets out various levels of

    Page 70993

    operator action as these limits are approached or exceeded, and varies depending on the well or location. The WSOC defines when the DP system must be configured in its CAMO during drilling or production. If the CAMO is required for that specific activity, the WSOC will require the MODU to cease operations when an equipment failure makes operation in CAMO impossible.

    0

    15. Add new Sec. 62.20-2 to read as follows:

    Sec. 62.20-2 Required plans for DP systems.

    (a) The following vessels must comply with the provisions of this section:

    (1) MODUs that use a dynamic positioning (DP) system to conduct Critical Outer Continental Shelf (OCS) Activities, as defined in 33 CFR 140.305, on the U.S. OCS; and

    (2) Vessels of more than 6,000 GT ITC other than MODUs that use a DP system installed on or after 30 DAYS AFTER DATE OF PUBLICATION OF FINAL RULE to conduct Critical OCS Activities, as defined in 33 CFR 140.305, on the U.S. OCS.

    (b) The owner or operator of each vessel to which this section applies must submit the following DP system plans and information for approval to the dynamic positioning system assurance organization (DPSAO) that performs the surveys under subpart 61.50 of this subchapter and is accepted under Sec. 61.50-3 of this subchapter by the Coast Guard Outer Continental Shelf National Center of Expertise (OCS NCOE):

    (1) A DP system description, including a block diagram and functional relationships of various components.

    (2) Specifications of position reference and environmental monitoring sensors or systems.

    (3) The location of thrusters and control system components.

    (4) Details of the DP system monitoring and alarm system and interconnection with the main centralized monitoring and alarm system.

    (5) DP system Failure Modes and Effects Analysis (FMEA) and FMEA proving test documents as described in Sec. 62.40-15 and Sec. 62.40-

    20 of this part, respectively.

    (6) The Critical Activity Mode of Operation determined from the initial survey required by Sec. 61.50-5 of this subchapter.

    (7) Designer or manufacturer self-certification of the DP system control equipment to the environmental design standards in Sec. 62.25-

    40 of this part. See Sec. 62.20-5 of this part.

    (c) The DPSAO that performs the surveys under subpart 61.50 of this subchapter must submit a copy of the approved plans under paragraph (b) of this section and the results of the initial survey, including the FMEA proving test required by subpart 61.50 of this subchapter to the Commanding Officer, Marine Safety Center, U.S. Coast Guard Stop 7410, 4200 Wilson Blvd., Suite 400, Arlington, VA 20598-7410. The Commanding Officer, Marine Safety Center may elect to review the plans to validate compliance with the requirements of this subpart and advise the DPSAO, the Coast Guard OSCNCOE and the cognizant Officer in Charge, Marine Inspection.

    0

    16. Add new Sec. 62.25-40 to read as follows:

    Sec. 62.25-40 Environmental design standards.

    (a) The following Mobile Offshore Drilling Units (MODUs) and vessels, other than MODUs, must comply with the provisions of this section:

    (1) MODUs that use a dynamic positioning (DP) system to conduct Critical Outer Continental Shelf (OCS) Activities, as defined in 33 CFR 140.305, on the U.S. OCS; and

    (2) Vessels other than MODUs that use a DP system installed on or after 30 DAYS AFTER DATE OF PUBLICATION OF FINAL RULE to conduct Critical OCS Activities, as defined in 33 CFR 140.305, on the U.S. OCS.

    (b) Computer-based systems, microprocessors, storage devices, power supply units, signal conditioners, analog/digital converters, computer monitors (visual display units), keyboards, reference sensors, and related systems (excluding printers), and data recording or logging devices must be designed to the environmental standards in Clause 5 of IEC 60092-504 (incorporated by reference, see Sec. 62.05-1).

    0

    17. Add new subpart 62.40, consisting of Sec. Sec. 62.40-1 through 62.40-25, to read as follows:

    Subpart 62.40--Dynamic Positioning Systems

    Sec.

    62.40-1 Applicability.

    62.40-3 Minimum dynamic positioning system requirements.

    62.40-5 Design for Critical OCS Activities.

    62.40-10 Classification for Critical OCS Activities.

    62.40-15 Failure Modes and Effects Analysis (FMEA).

    62.40-20 Failure Modes and Effects Analysis (FMEA) proving test document.

    62.40-25 Critical Activity Mode of Operation (CAMO).

    Subpart 62.40--Dynamic Positioning Systems

    Sec. 62.40-1 Applicability.

    This subpart applies to all vessels, including Mobile Offshore Drilling Units (MODUs), that use a dynamic positioning (DP) system to conduct Outer Continental Shelf (OCS) activities, as defined in 33 CFR 140.10, on the U.S. OCS. ``Vessels,'' for purposes of this subpart, include but are not limited to MODUs.

    Sec. 62.40-3 Minimum dynamic positioning system requirements.

    Vessels to which this subpart applies must meet the applicable requirements of this part and 46 CFR 62.35-5 and 46 CFR 62.50-30 for remote propulsion control systems with periodically unattended machinery plants, as well as paragraph 3.4.1 of IMO MSC/Circ.645 (incorporated by reference, see Sec. 62.05-1), except subparagraph 3.4.1.4.

    Sec. 62.40-5 Design for Critical OCS Activities.

    (a) The following vessels must comply with the provisions of this section:

    (1) MODUs that use a dynamic positioning (DP) system to conduct Critical Outer Continental Shelf (OCS) Activities, as defined in 33 CFR 140.305, on the U.S. OCS; and

    (2) Vessels other than MODUs that use a DP system installed on or after (30 DAYS AFTER DATE OF PUBLICATION OF FINAL RULE) to conduct Critical OCS Activities, as defined in 33 CFR 140.305, on the U.S. OCS.

    (b) Vessels to which this section applies must meet the provisions of IMO MSC/Circ.645 (incorporated by reference, see Sec. 62.05-1) and the provisions of the applicable MTS DP Operations Guide (incorporated by reference, see Sec. 62.05-1) relevant to equipment class 2 (DP-2) or higher for MODUs, project construction vessels, or logistics vessels, as appropriate.

    Sec. 62.40-10 Classification for Critical OCS Activities.

    (a) The following vessels must comply with the provisions of this section:

    (1) MODUs that use a dynamic positioning (DP) system to conduct Critical Outer Continental Shelf (OCS) Activities, as defined in 33 CFR 140.305, on the U.S. OCS; and

    (2) Vessels other than MODUs that use a DP system installed on or after (30 DAYS AFTER DATE OF PUBLICATION OF FINAL RULE) to conduct Critical OCS Activities, as defined in 33 CFR 140.305, on the U.S. OCS.

    (b) Vessels to which this section applies must obtain an IMO MSC/

    Circ.645 equipment class 2 (DP-2) or

    Page 70994

    higher notation from a classification society that meets the requirements of paragraph (c) of this section.

    (c) The classification society that issues an equipment class 2 (DP-2) or higher notation to vessels under this section applies must--

    (1) Comply with the provisions of 46 CFR, part 8, subpart B;

    (2) Possess DP system rules aligned with IMO MSC/Circ.645 and the MTS DP Operations Guide (incorporated by reference, see Sec. 62.05-1) applicable to the vessel being classed; and,

    (3) Submit evidence that it complies with paragraphs c(1) and c(2) of this section to the Coast Guard Outer Continental Shelf National Center of Expertise (OCS NCOE), which will authorize the classification society to issue notations as described in this section.

    Sec. 62.40-15 Failure Modes and Effects Analysis (FMEA).

    (a) The following vessels must comply with the provisions of this section:

    (1) Vessels other than MODUs of more than 500 GT ITC (500 GRT if GT ITC not assigned) that use a dynamic positioning (DP) system installed before (30 DAYS AFTER DATE OF PUBLICATION OF FINAL RULE) to conduct Critical Outer Continental Shelf (OCS) Activities, as defined in 33 CFR 140.305, on the U.S. OCS;

    (2) Vessels other than MODUs that use a DP system installed on or after (30 DAYS AFTER DATE OF PUBLICATION OF FINAL RULE) to conduct Critical OCS Activities; and

    (3) MODUs that use a DP system to conduct Critical OCS Activities, as defined in 33 CFR 140.305, on the U.S. OCS.

    (b) The owner or operator of each vessel to which this section applies must complete and maintain an FMEA with the details necessary to demonstrate compliance with the applicable provisions of IMO MSC/

    Circ.645 and must demonstrate compliance with the MTS DP Operations Guide (both incorporated by reference, see Sec. 62.05-1) for equipment class 2 (DP-2) or equipment class 3 (DP-3) requirements and this subpart, as applicable.

    (c) Vessels described in paragraph (a)(1) of this section must comply with the provisions of this section no later than the applicable date in 33 CFR table 140.335.

    (d) Alternative guidance may be used in lieu of the MTS DP Operations Guide to meet the requirements of this section if permitted by the Office of Design and Engineering Standards (Commandant (CG-ENG)) to the extent and under conditions that will ensure a degree of safety comparable to or greater than that provided by use of the MTS DP Operations Guide.

    Sec. 62.40-20 Failure Modes and Effects Analysis (FMEA) proving test document.

    (a) The owner or operator of each vessel to which Sec. 62.40-15 of this subpart applies must complete and maintain a dynamic positioning system FMEA proving test document that--

    (1) Provides the necessary test instructions, based on the FMEA required by this subpart, to demonstrate design and operation in accordance with the equipment class of the DP system and this subpart; and

    (2) Is approved by the Marine Safety Center under Sec. 62.20-2 of this part and retained on board.

    Sec. 62.40-25 Critical Activity Mode of Operation (CAMO).

    (a) The owner or operator of each vessel to which Sec. 62.40-15 of this subpart applies must complete and maintain a CAMO as defined in Sec. 62.10-1 of this part.

    Dated: November 13, 2014.

    J.G. Lantz,

    Director of Commercial Regulations and Standards, U.S. Coast Guard.

    FR Doc. 2014-27594 Filed 11-26-14; 8:45 am

    BILLING CODE 9110-04-P

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT