Federal Acquisition Regulation: Federal Acquisition Circular 2005-43; Introduction
Federal Register: July 2, 2010 (Volume 75, Number 127)
Rules and Regulations
Page 38673-38675
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
DOCID:fr02jy10-17
Page 38673
Part IV
Department of Defense
General Services Administration
National Aeronautics and Space Administration
48 CFR Chapter 1
Federal Acquisition Regulations; Final Rules
Page 38674
DEPARTMENT OF DEFENSE
GENERAL SERVICES ADMINISTRATION
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION 48 CFR Chapter 1
Docket FAR 2010-0076, Sequence 5
Federal Acquisition Regulation; Federal Acquisition Circular 2005-43; Introduction
AGENCIES: Department of Defense (DoD), General Services Administration
(GSA), and National Aeronautics and Space Administration (NASA).
ACTION: Summary presentation of rules.
SUMMARY: This document summarizes the Federal Acquisition Regulation
(FAR) rules agreed to by the Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council (Councils) in this Federal
Acquisition Circular (FAC) 2005-43. A companion document, the Small
Entity Compliance Guide (SECG), follows this FAC. The FAC, including the SECG, is available via the Internet at http://www.regulations.gov.
DATES: For effective dates and comment dates, see separate documents, which follow.
FOR FURTHER INFORMATION CONTACT: The analyst whose name appears in the table below in relation to each FAR case. Please cite FAC 2005-43 and the specific FAR case numbers. For information pertaining to status or publication schedules, contact the Regulatory Secretariat at (202) 501- 4755.
List of Rules in FAC 2005-43
Item
Subject
FAR Case
Analyst
I.......... Government Property....
2008-011 Parnell
II......... Registry of Disaster
2008-035 Gary
Response Contractors.
III........ Recovery Act
2010-008 Morgan
Subcontract Reporting
Procedures (Interim).
IV......... Clarification of
2008-023 Cundiff
Criteria for Sole
Source Awards to
Service-disabled
Veteran-owned Small
Business Concerns.
V.......... Trade Agreements
2009-040 Davis
Thresholds (Interim).
SUPPLEMENTARY INFORMATION: Summaries for each FAR rule follow. For the actual revisions and/or amendments made by these FAR cases, refer to the specific item number and subject set forth in the documents following these item summaries.
FAC 2005-43 amends the FAR as specified below:
Item I--Government Property (FAR Case 2008-011)
This final rule amends the FAR to revise FAR part 45 and its associated clauses. Changes are being made to FAR parts 2, 4, 15, 32, 42, 45, and 52. These changes are to clarify and correct the previous
FAR rule for part 45, Government Property, published under Federal
Acquisition Circular 2005-17, FAR case 2004-025, May 15, 2007, (72 FR 27364). Minor changes are made to the proposed rule published August 6, 2009 (74 FR 39262).
The rule specifically impacts contracting officers, property administrators, and contractors responsible for the management of
Government property. The rule does not affect the method of managing
Government property. The rule merely clarifies and corrects the previous FAR rule.
Item II--Registry of Disaster Response Contractors (FAR Case 2008-035)
This final rule adopts, without change, the interim rule implementing Public Law 109-295, the Department of Homeland Security
Appropriations Act, 2007, section 697, which requires the establishment and maintenance of a registry of disaster response contractors. The
Disaster Response Registry is located at http://www.ccr.gov. The
Federal Emergency Management Agency (within the Department of Homeland
Security) has a link to the registry for vendors on its Web site at http://www.fema.gov/business/contractor.shtm. The Registry covers domestic disaster and emergency relief activities.
Item III--Recovery Act Subcontract Reporting Procedures (FAR Case 2010- 008) (Interim)
This interim rule amends the FAR to revise the clause at FAR 52.204-11, American Recovery and Reinvestment Act--Reporting
Requirements. The revised clause will require first-tier subcontractors with Recovery Act funded awards of $25,000 or more, to report jobs information to the prime contractor for reporting into
FederalReporting.gov. It also will require the prime contractor to submit its first report on or before the 10th day after the end of the calendar quarter in which the prime contractor received the award, and quarterly thereafter.
The revised clause will be used for all new solicitations and awards issued on or after the effective date of this interim rule. This clause is not required for any existing contracts, or task and delivery orders issued under a contract, that contain the original clause FAR 52.204-11 (March 2009). Therefore, this interim rule does not require renegotiation of existing Recovery Act contracts that include the clause dated March 2009.
Item IV--Clarification of Criteria for Sole Source Awards to Service-
Disabled Veteran-Owned Small Business Concerns (FAR Case 2008-023)
This final rule amends FAR 19.1406(a) to clarify the criteria that need to be met in order to conduct a sole source service-disabled veteran-owned small business (SDVOSB) concern acquisition. The FAR language is amended to be consistent with the Veterans Benefit Act of 2003 (15 U.S.C. 657f) and the Small Business Administration's regulation (13 CFR 125.20) that implements the Act. This final rule also amends FAR 19.1306(a) to clarify the criteria that need to be met in order to conduct a sole source for Historically Underutilized
Business Zone (HUBZone) small business concern acquisitions. These amendments to the FAR alleviate confusion for contracting officers on the appropriate use of the criteria needed to conduct sole source
HUBZONE small business and SDVOSB concern acquisitions.
Item V--Trade Agreements Thresholds (FAR Case 2009-040) (Interim)
This interim rule adjusts the thresholds for application of the
World
Page 38675
Trade Organization Government Procurement Agreement and the free trade agreements as determined by the United States Trade Representative, according to a pre-determined formula under the agreements.
Dated: June 25, 2010.
Edward Loeb,
Director, Acquisition Policy Division.
Federal Acquisition Circular
Federal Acquisition Circular (FAC) 2005-43 is issued under the authority of the Secretary of Defense, the Administrator of General
Services, and the Administrator for the National Aeronautics and Space
Administration.
Unless otherwise specified, all Federal Acquisition Regulation
(FAR) and other directive material contained in FAC 2005-43 is effective July 2, 2010, except for Items I, II, and IV which are effective August 2, 2010.
Dated: June 24, 2010.
Shay D. Assad,
Director, Defense Procurement and Acquisition Policy.
Dated: June 24, 2010.
Rodney P. Lantier,
Acting Senior Procurement Executive, Office of Acquisition Policy, U.S.
General Services Administration.
Dated: June 23, 2010.
William P. McNally,
Assistant Administrator for Procurement, National Aeronautics and Space
Administration.
FR Doc. 2010-15913 Filed 7-1-10; 8:45 am