Actions Taken at December 5, 2014, Meeting
Federal Register, Volume 79 Issue 247 (Wednesday, December 24, 2014)
Federal Register Volume 79, Number 247 (Wednesday, December 24, 2014)
Notices
Pages 77591-77592
From the Federal Register Online via the Government Printing Office www.gpo.gov
FR Doc No: 2014-30197
=======================================================================
-----------------------------------------------------------------------
SUSQUEHANNA RIVER BASIN COMMISSION
Actions Taken at December 5, 2014, Meeting
AGENCY: Susquehanna River Basin Commission.
ACTION: Notice.
-----------------------------------------------------------------------
SUMMARY: As part of its regular business meeting held on December 5, 2014, in Annapolis, Maryland, the Commission took the following actions: (1) Approved or tabled the applications of certain water resources projects; (2) accepted settlements in lieu of penalty from Lion Brewery, Inc.; LHP Management, LLC; and Southwestern Energy Production Company; and (3) took additional actions, as set forth in the Supplementary Information below.
DATES: December 5, 2014.
ADDRESSES: Susquehanna River Basin Commission, 4423 N. Front Street, Harrisburg, PA 17110-1788.
FOR FURTHER INFORMATION CONTACT: Jason E. Oyler, Regulatory Counsel, telephone: (717) 238-0423, ext. 1312; fax: (717) 238-2436; email: joyler@srbc.net. Regular mail inquiries may be sent to the above address. See also Commission Web site at www.srbc.net.
SUPPLEMENTARY INFORMATION: In addition to the actions taken on projects identified in the summary above and the listings below, the following items were also presented or acted upon at the business meeting: (1) Adoption of a resolution honoring retiring staff member Richard A. Cairo, General Counsel; (2) an informational presentation from SRBC staff member Aaron Henning on recent water quality and biological characterizations SRBC has undertaken for the reservoirs on the lower Susquehanna River; (3) adoption of a resolution urging the President and Congress to provide full funding for the National Streamflow Information Program, thereby supporting the Susquehanna Flood Forecast & Warning System; (4) approval of a rulemaking action pertaining to clarification of the water uses involved in hydrocarbon development that are subject to SRBC's consumptive use regulations, as implemented by the Approval by Rule program; (5) delegation of authority to the Executive Director to enter into certain settlement agreements; (6) approval/ratification of two grants, one grant amendment, and one contract; (7) approval of a request from Sunbury Generation LP for a transfer of approval to Hummel Station LLC; and (8) denial of a request from Future Power PA, LLC for a waiver of 18 CFR 806.3 and 806.4.
Compliance Matters
The Commission approved settlements in lieu of civil penalty for the following projects:
-
Lion Brewery, Inc., City of Wilkes-Barre, Luzerne County, Pa.--
$50,000.
-
LHP Management, LLC (Muncy Creek), Muncy Creek Township, Lycoming County, Pa.--$3,000.
-
Southwestern Energy Production Company (Borough of Bellefonte's Wastewater Treatment Plant), Borough of Bellefonte, Centre County, Pa.--$4,500.
Project Applications Approved
The Commission approved the following project applications:
-
Project Sponsor and Facility: Anadarko E&P Onshore LLC (Pine Creek), Watson Township,
Page 77592
Lycoming County, Pa. Renewal of surface water withdrawal of up to 0.720 mgd (peak day) (Docket No. 20101201).
-
Project Sponsor and Facility: Geary Enterprises (Buttermilk Creek), Falls Township, Wyoming County, Pa. Renewal of surface water withdrawal of up to 0.099 mgd (peak day) (Docket No. 20100907).
-
Project Sponsor and Facility: Heidelberg Township Municipal Authority, Heidelberg Township, Lebanon County, Pa. Renewal of groundwater withdrawal of up to 0.115 mgd (30-day average) from existing public water supply Well 5 (Docket No. 19820602).
-
Project Sponsor and Facility: IBM Corporation, Village of Owego, Tioga County, N.Y. Groundwater withdrawal of up to 0.800 mgd (30-day average) from Well 415.
-
Project Sponsor and Facility: Jay Township Water Authority, Jay Township, Elk County, Pa. Groundwater withdrawal of up to 0.265 mgd (30-day average) from Byrnedale Well #1.
-
Project Sponsor and Facility: LHP Management, LLC (Muncy Creek), Muncy Creek Township, Lycoming County, Pa. Renewal of surface water withdrawal of up to 0.999 mgd (peak day) (Docket No. 20120607).
-
Project Sponsor and Facility: New Morgan Borough Utilities Authority, New Morgan Borough, Berks County, Pa. Groundwater withdrawal of up to 0.275 mgd (30-day average) from Well PW-1.
-
Project Sponsor and Facility: New Morgan Borough Utilities Authority, New Morgan Borough, Berks County, Pa. Groundwater withdrawal of up to 0.108 mgd (30-day average) from Well PW-3.
-
Project Sponsor and Facility: New Oxford Municipal Authority, Oxford Township, Adams County, Pa. Groundwater withdrawal of up to 0.144 mgd (30-day average) from Oxen Country Meadows Well 1.
-
Project Sponsor and Facility: Somerset Regional Water Resources, LLC (Salt Lick Creek), New Milford Township, Susquehanna County, Pa. Renewal of surface water withdrawal of up to 0.720 mgd (peak day) (Docket No. 20100905).
-
Project Sponsor and Facility: Southwestern Energy Production Company (Susquehanna River), Eaton Township, Wyoming County, Pa. Surface water withdrawal of up to 2.000 mgd (peak day).
-
Project Sponsor and Facility: SWEPI LP (Cowanesque River), Nelson Township, Tioga County, Pa. Renewal of surface water withdrawal of up to 0.533 mgd (peak day) (Docket No. 20100604).
-
Project Sponsor and Facility: Talisman Energy USA Inc. (Seeley Creek), Wells Township, Bradford County, Pa. Renewal of surface water withdrawal of up to 0.750 mgd (peak day) (Docket No. 20100914).
-
Project Sponsor and Facility: Talisman Energy USA Inc. (Wyalusing Creek), Stevens Township, Bradford County, Pa. Renewal of surface water withdrawal of up to 1.500 mgd (peak day) (Docket No. 20100915).
-
Project Sponsor and Facility: Tenaska Resources, LLC (Cowanesque River), Westfield Township, Tioga County, Pa. Renewal of surface water withdrawal of up to 0.400 mgd (peak day) (Docket No. 20100910).
-
Project Sponsor and Facility: Upper Halfmoon Water Company, Halfmoon Township, Centre County, Pa. Groundwater withdrawal of up to 0.206 mgd (30-day average) from Well 6.
Project Application Approved Involving a Diversion
The Commission approved the following project application involving a diversion:
-
Project Sponsor: Seneca Resources Corporation. Project Facility: Impoundment 1, receiving groundwater from Seneca Resources Corporation Wells 5H and 6H and Clermont Wells 1, 3, and 4, Norwich Township, McKean County, Pa. Into-basin diversion from the Ohio River Basin of up to 1.473 mgd (peak day).
Project Applications Tabled
The Commission tabled action on the following project applications:
-
Project Sponsor and Facility: EQT Production Company (West Branch Susquehanna River), Greenwood Township, Clearfield County, Pa. Application for surface water withdrawal of up to 0.900 mgd (peak day).
-
Project Sponsor and Facility: Keister Miller Investments, LLC (West Branch Susquehanna River), Mahaffey Borough, Clearfield County, Pa. Application for surface water withdrawal of up to 2.000 mgd (peak day).
-
Project Sponsor: Pennsylvania Department of Environmental Protection--South-central Regional Office, City of Harrisburg, Dauphin County, Pa. Facility Location: Leacock Township, Lancaster County, Pa. Application for groundwater withdrawal of up to 0.590 mgd (30-day average) from Stoltzfus Well.
-
Project Sponsor: Pennsylvania Department of Environmental Protection--South-central Regional Office, City of Harrisburg, Dauphin County, Pa. Facility Location: Leacock Township, Lancaster County, Pa. Application for groundwater withdrawal of up to 0.432 mgd (30-day average) from Township Well.
Authority: Pub. L. 91-575, 84 Stat. 1509 et seq., 18 CFR parts 806, 807, and 808.
Dated: December 17, 2014.
Stephanie L. Richardson,
Secretary to the Commission.
FR Doc. 2014-30197 Filed 12-23-14; 8:45 am
BILLING CODE 7040-01-P