Air pollution control: Vermont,

[Federal Register: November 29, 2001 (Volume 66, Number 230)]

[Rules and Regulations]

[Page 59535-59537]

From the Federal Register Online via GPO Access [wais.access.gpo.gov]

[DOCID:fr29no01-3]

ENVIRONMENTAL PROTECTION AGENCY

40 CFR Part 70

[VT-021-1224a; A-1-FRL-7110-2]

Clean Air Act Final Approval of Operating Permits Program; State of Vermont

AGENCY: Environmental Protection Agency (EPA).

ACTION: Final rule.

[[Page 59536]]

SUMMARY: EPA is granting full approval to the Clean Air Act (Act), Operating Permits Program of the State of Vermont (program). Vermont submitted its program for the purpose of complying with the Act's directive that states develop programs to issue operating permits to all major stationary sources and certain other stationary sources. EPA granted interim approval to Vermont's initial operating permit program on October 2, 1996. On September 28, 2001, EPA proposed full approval of Vermont's pending revised program, provided the state finalized the sections of its proposed rules that address EPA's interim approval conditions. On November 15, 2001, EPA received Vermont's adopted revisions to its program. The Agency has determined that Vermont has adequately addressed all interim approval conditions as described in EPA's proposed approval.

DATES: This rule is effective on November 30, 2001 without further notice.

ADDRESSES: Copies of the documents relevant to this action are available for public inspection during normal business hours, by appointment at the Office of Ecosystem Protection, U.S. Environmental Protection Agency, EPA New England Regional Office, One Congress Street, 11th floor, Boston, MA.

FOR FURTHER INFORMATION CONTACT: Donald Dahl, (617) 918-1657.

SUPPLEMENTARY INFORMATION:

  1. What Is EPA Approving?

    EPA is taking final action to approve the changes Vermont made to its regulations (Environmental Protection Regulations, Air Pollution Control Chapter V, Definitions and Subchapter X) regarding the state's title V permitting program. The Agency is granting full approval to Vermont's title V permitting program because Vermont has made all the necessary changes to its program required by EPA's interim approval. Details of the state changes can be found in EPA's proposed rulemaking, 66 FR 49577 (September 28, 2001). EPA did not receive any comments on the proposed rulemaking. In the final adoption, the state legislative council made three minor changes to the proposed rule. These changes that do not effect the substance of the provisions EPA relied on when it proposed to grant full approval to Vermont's program. The exact changes the state made can be found as part of EPA's public record.

    It should be noted that the state regulation, although fully adopted on November 14, 2001, and submitted to EPA on November 15, 2001, is not effective under state law until November 29, 2001. Vermont state law provides that state regulations ``take effect fifteen days after adoption is complete.'' V.S.A. t. section 845(d). This waiting period has no effect on the substance of the fully adopted state regulation that EPA is approving, nor on EPA's authority to sign this action approving the adopted program.

    Unlike the prior interim approval, this full approval has no expiration date. However, the state may revise its program as appropriate in the future by following the procedures of 40 CFR 70.4(i). EPA may also exercise its oversight authority under section 502(i) of the Act to require changes to a state's program consistent with the procedures of 40 CFR 70.10.

  2. What Is the Effective Date of EPA's Full Approval of the Vermont Title V Program?

    EPA is using the good cause exception under the Administrative Procedure Act (APA) to make the full approval of the state's program effective on November 30, 2001. In relevant part, the APA provides that publication of ``a substantive rule shall be made not less than 30 days before its effective date, except--* * * (3) as otherwise provided by the agency for good cause found and published with the rule.'' 5 U.S.C. 553(d)(3). Section 553(b)(3)(B) of the APA provides that good cause may be supported by an agency determination that a delay in the effective date is impracticable, unnecessary, or contrary to the public interest. EPA finds that it is necessary and in the public interest to make this action effective sooner than 30 days following publication. In this case, EPA believes that it is in the public interest for the program to take effect before December 1, 2001. EPA's interim approval of Vermont's prior program expires on December 1, 2001. In the absence of this full approval of Vermont's amended program taking effect on November 30, the federal program under 40 CFR part 71 would automatically take effect in Vermont and would remain in place until the effective date of the fully-approved state program. EPA believes it is in the public interest for sources, the public and the state to avoid any gap in coverage of the state program, as such a gap could cause confusion regarding permitting obligations. Furthermore, a delay in the effective date is unnecessary because Vermont has been administering the title V permit program for 5 years under an interim approval. Through this action, EPA is approving a few revisions to the existing and currently operational program. The change from the interim approved program which substantially met the part 70 requirements, to the fully approved program is relatively minor, in particular if compared to the changes between a state-established and administered program and the federal program.

  3. Administrative Requirements

    Under Executive Order 12866, ``Regulatory Planning and Review'' (58 FR 51735, October 4, 1993), this final approval is not a ``significant regulatory action'' and therefore is not subject to review by the Office of Management and Budget. Under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.) the Administrator certifies that this final approval will not have a significant economic impact on a substantial number of small entities because it merely approves state law as meeting federal requirements and imposes no additional requirements beyond those imposed by state law. This rule does not contain any unfunded mandates and does not significantly or uniquely affect small governments, as described in the Unfunded Mandates Reform Act of 1995 (Pub. L. 104-4) because it approves pre-existing requirements under state law and does not impose any additional enforceable duties beyond that required by state law. This rule also does not have tribal implications because it will not have a substantial direct effect on one or more Indian tribes, on the relationship between the federal government and Indian tribes, or on the distribution of power and responsibilities between the federal government and Indian tribes, as specified by Executive Order 13175, ``Consultation and Coordination with Indian Tribal Governments'' (65 FR 67249, November 9, 2000). This rule also does not have Federalism implications because it will not have substantial direct effects on the states, on the relationship between the national government and the states, or on the distribution of power and responsibilities among the various levels of government, as specified in Executive Order 13132, ``Federalism'' (64 FR 43255, August 10, 1999). This rule merely approves existing requirements under state law, and does not alter the relationship or the distribution of power and responsibilities between the state and the federal government established in the Clean Air Act. This final approval also is not subject to Executive Order 13045, ``Protection of Children from Environmental Health Risks and Safety Risks'' (62 FR 19885, April 23, 1997) or Executive Order 13211, ``Actions

    [[Page 59537]]

    Concerning Regulations That Significantly Affect Energy Supply, Distribution, or Use'' (66 FR 28355 (May 22, 2001), because it is not a significant regulatory action under Executive Order 12866. This action will not impose any collection of information subject to the provisions of the Paperwork Reduction Act, 44 U.S.C. 3501 et seq., other than those previously approved and assigned OMB control number 2060-0243. For additional information concerning these requirements, see 40 CFR part 70. An agency may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.

    In reviewing state operating permit programs submitted pursuant to title V of the Clean Air Act, EPA will approve state programs provided that they meet the requirements of the Clean Air Act and EPA's regulations codified at 40 CFR part 70. In this context, in the absence of a prior existing requirement for the state to use voluntary consensus standards (VCS), EPA has no authority to disapprove a state operating permit program for failure to use VCS. It would thus be inconsistent with applicable law for EPA, when it reviews an operating permit program, to use VCS in place of a state program that otherwise satisfies the provisions of the Clean Air Act. Thus, the requirements of section 12(d) of the National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 note) do not apply.

    The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the Small Business Regulatory Enforcement Fairness Act of 1996, generally provides that before a rule may take effect, the agency promulgating the rule must submit a rule report, which includes a copy of the rule, to each House of the Congress and to the Comptroller General of the United States. EPA will submit a report containing this rule and other required information to the U.S. Senate, the U.S. House of Representatives, and the Comptroller General of the United States prior to publication of the rule in the Federal Register. A major rule cannot take effect until 60 days after it is published in the Federal Register. This action is not a ``major rule'' as defined by 5 U.S.C. 804(2). This rule will be effective on November 30, 2001.

    Under section 307(b)(1) of the Clean Air Act, petitions for judicial review of this action must be filedin the United States Court of Appeals for the appropriate circuit by January 28, 2002. Filing a petition for reconsideration by the Administrator of this final rule does not affect the finality of this rule for the purposes of judicial review nor does it extend the time within which a petition for judicial review may be filed, and shall not postpone the effectiveness of such rule or action. This action may not be challenged later in proceedings to enforce its requirements. (See section 307(b)(2).)

    List of Subjects in 40 CFR Part 70

    Environmental protection, Administrative practice and procedure, Air pollution control, Intergovernmental relations, Operating permits, Reporting and recordkeeping requirements.

    Dated: November 21, 2001. Robert W. Varney, Regional Administrator, EPA New England.

    Part 70, title 40 of the Code of Federal Regulations is amended as follows:

    PART 70--[AMENDED]

    1. The authority citation for part 70 continues to read as follows:

      Authority: 42 U.S.C. 7401, et seq.

    2. Appendix A to part 70 is amended by revising the entry for Vermont to read as follows:

      Appendix A to Part 70--Approval Status of State and Local Operating Permits Programs

      * * * * *

      Vermont

      (a) Department of Environmental Conservation: submitted on April 28, 1995; interim approval effective on November 1, 1996; revised program submitted on November 15, 2001; full approval effective November 30, 2001.

      (b) [Reserved] * * * * *

      [FR Doc. 01-29653Filed11-28-01; 8:45 am]

      BILLING CODE 6560-50-P

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT