Assessment and Collection of Space and Earth Station Regulatory Fees for Fiscal Year 2024; Review of the Commission's Assessment and Collection of Regulatory Fees for Fiscal Year 2024

Published date25 March 2024
Record Number2024-05996
Citation89 FR 20582
CourtFederal Communications Commission
SectionProposed rules
Federal Register, Volume 89 Issue 58 (Monday, March 25, 2024)
[Federal Register Volume 89, Number 58 (Monday, March 25, 2024)]
                [Proposed Rules]
                [Pages 20582-20603]
                From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
                [FR Doc No: 2024-05996]
                =======================================================================
                -----------------------------------------------------------------------
                FEDERAL COMMUNICATIONS COMMISSION
                47 CFR Part 1
                [MD Docket Nos. 24-85, 24-86; FCC 24-31; FR ID 209752]
                Assessment and Collection of Space and Earth Station Regulatory
                Fees for Fiscal Year 2024; Review of the Commission's Assessment and
                Collection of Regulatory Fees for Fiscal Year 2024
                AGENCY: Federal Communications Commission.
                ACTION: Proposed rule.
                -----------------------------------------------------------------------
                SUMMARY: In this document, the Federal Communications Commission
                (Commission or FCC) adopted a Notice of Proposed Rulemaking (NPRM) that
                seeks comments on revising the regulatory fees for space and earth
                station payors for fiscal year (FY) 2024.
                DATES: Submit comments on or before April 12, 2024; and reply comments
                on or before April 29, 2024.
                ADDRESSES: You may submit comments, identified by MD Docket No. 24-85
                and MD Docket No. 24-86, by any of the following methods:
                 Electronic Filers. Comments may be filed electronically
                using the internet by accessing the ECFS, https://apps.fcc.gov/ecfs.
                 Paper Filers. Parties who choose to file by paper must
                file an original and one copy of each filing.
                 Filings can be sent by commercial overnight courier, or by
                first-class or overnight U.S. Postal Service mail. All filings must be
                addressed to the Commission's Secretary, Office of the Secretary,
                Federal Communications Commission.
                 Commercial overnight mail (other than U.S. Postal Service
                Express Mail and Priority Mail) must be sent to 9050 Junction Drive,
                Annapolis Junction, MD 220701.
                U.S. Postal Service first-class, Express, and Priority
                mail must be addressed to 45 L Street NE, Washington, DC 20554.
                 Effective March 19, 2020, and until further notice, the
                Commission no longer accepts any hand or messenger delivered filings.
                This is a temporary measure taken to help protect the health and safety
                of individuals, and to mitigate the transmission of COVID-19. See FCC
                Announces Closure of FCC Headquarters Open Window and Change in Hand-
                Delivery Policy, Public Notice, DA 20-304 (March 19, 2020). https://www.fcc.gov/document/fcc-closes-headquarters-open-window-and-changes-hand-delivery-policy.
                 People with Disabilities: To request materials in accessible
                formats for people with disabilities (braille, large print, electronic
                files, audio format), send an email to [email protected] or call the
                Consumer & Governmental Affairs Bureau at 202-418-0530 (voice) or 202-
                418-0432 (TTY).
                FOR FURTHER INFORMATION CONTACT: Stephen Duall, Space Bureau, at (202)
                418-1103 or [email protected]; Roland Helvajian, Office of the
                Managing Director, at (202) 418-0444 or [email protected].
                SUPPLEMENTARY INFORMATION: This is a summary of the Commission's Notice
                of Proposed Rulemaking (NPRM), in MD Docket Nos. 24-85 and 24-86; FCC
                24-31, adopted and released on March 13, 2024. The full text of this
                document is available at https://docs.fcc.gov/public/attachments/FCC-24-31A1.pdf.
                 Comment Filing Requirements. Interested parties may file comments
                and reply comments on or before the dates indicated in the DATES
                section above. Comments may be filed using the Commission's Electronic
                Comment Filing System (ECFS).
                 Providing Accountability Through Transparency Act. The Providing
                Accountability Through Transparency Act, Public Law 118-9, requires
                each
                [[Page 20583]]
                agency, in providing notice of a rulemaking, to post online a brief
                plain-language summary of the proposed rule. The required summary of
                the NPRM is available at https://www.fcc.gov/proposed-rulemakings.
                 Ex Parte Presentations. The Commission will treat this proceeding
                as a ``permit-but-disclose'' proceeding in accordance with the
                Commission's ex parte rules. Persons making ex parte presentations must
                file a copy of any written presentation or a memorandum summarizing any
                oral presentation within two business days after the presentation
                (unless a different deadline applicable to the Sunshine period
                applies). Persons making oral ex parte presentations are reminded that
                memoranda summarizing the presentation must (1) list all persons
                attending or otherwise participating in the meeting at which the ex
                parte presentation was made, and (2) summarize all data presented and
                arguments made during the presentation. If the presentation consisted
                in whole or in part of the presentation of data or arguments already
                reflected in the presenter's written comments, memoranda or other
                filings in the proceeding, the presenter may provide citations to such
                data or arguments in his or her prior comments, memoranda, or other
                filings (specifying the relevant page and/or paragraph numbers where
                such data or arguments can be found) in lieu of summarizing them in the
                memorandum. Documents shown or given to Commission staff during ex
                parte meetings are deemed to be written ex parte presentations and must
                be filed consistent with 47 CFR 1.1206(b). In proceedings governed by
                47 CFR 1.49(f) or for which the Commission has made available a method
                of electronic filing, written ex parte presentations and memoranda
                summarizing oral ex parte presentations, and all attachments thereto,
                must be filed through the electronic comment filing system available
                for that proceeding, and must be filed in their native format (e.g.,
                .doc, .xml, .ppt, searchable .pdf). Participants in this proceeding
                should familiarize themselves with the Commission's ex parte rules.
                 Initial Regulatory Flexibility Analysis. The Regulatory Flexibility
                Act of 1980, as amended (RFA), requires that an agency prepare a
                regulatory flexibility analysis for notice and comment rulemakings,
                unless the agency certifies that ``the rule will not, if promulgated,
                have a significant economic impact on a substantial number of small
                entities.'' The Commission has prepared an Initial Regulatory
                Flexibility Analysis (IRFA) concerning the potential impact of the
                proposed rule and policy changes contained in the NPRM. The IRFA is set
                forth in appendix A of the FCC Document https://docs.fcc.gov/public/attachments/FCC-24-31A1.pdf and a summary is included below. Written
                public comments are requested on the IRFA. Comments must be filed by
                the deadlines for comments on the NPRM indicated on the DATES section
                of this document and must have a separate and distinct heading
                designating them as responses to the IRFA.
                Synopsis
                I. Introduction
                 1. Pursuant to section 9 of the Communications Act of 1934, as
                amended, (Communications Act or Act), the Commission undertakes the
                Notice of Proposed Rulemaking (NPRM) to commence the assessment of
                regulatory fees for space and earth station payors for fiscal year (FY)
                2024.
                 2. In January 2023, the Commission reorganized its International
                Bureau into: (1) a Space Bureau to handle policy and licensing matters
                related to satellite communications and other in-space activities under
                the Commission's jurisdiction; and (2) an Office of International
                Affairs to handle issues involving foreign and international regulatory
                authorities as well as international telecommunications and submarine
                cable licensing. When the Commission adopted regulatory fees for Fiscal
                Year (FY) 2023 in the FY 2023 Regulatory Fees Report and Order, 88 FR
                63694 (Sept. 15, 2023), it noted that it would be the last year for
                doing so for the International Bureau, and that the creation of the
                Space Bureau and Office of International Affairs could result in
                changes in the assessment of regulatory fees due to changes in Full
                Time Equivalents (FTEs), due to increased oversight on various relevant
                industries. One FTE, sometimes also referring to a Full Time Employee,
                is a unit of measure equal to the work performed annually by a full-
                time person (working a 40-hour workweek for a full year) assigned to
                the particular job, and subject to agency personnel staffing
                limitations established by the Office of Management and Budget (OMB).
                In particular, the FY 2023 Regulatory Fees Report and Order stated that
                an examination of the regulatory fees and categories for non-
                geostationary orbit (NGSO) space stations would be useful in light of
                changes resulting from the creation of the Space Bureau. The Commission
                anticipated that the changes in the industry that resulted in the
                creation of the Space Bureau would likely also result in changes in the
                relative FTE burdens between and among space and earth station fee
                payors. Accordingly, the Commission found that it would be more
                efficient to seek comment on proposals to examine the categories of
                regulatory fees for NGSO space stations at the same time as other
                proposals that might arise as part of a ``more holistic review'' of the
                fee burden of the Space Bureau in FY 2024.
                 3. The NPRM commences that examination and review of regulatory
                fees for space and earth station payors that are regulated by the new
                Space Bureau. Specifically, the Commission seeks comment on a range of
                proposed changes related to the assessment of regulatory fees for space
                and earth stations under its existing methodology.
                 4. In addition, the Commission proposes an alternative methodology
                for assessing space station regulatory fees. Unlike the proposals made
                to adjust the existing methodology, the alternative methodology is a
                more comprehensive departure from the way that space station regulatory
                fees have been assessed since 1994 in that it eliminates the separate
                categories of regulatory fees for Geostationary Orbit (GSO) and NGSO
                space stations, as well as existing subcategories for NGSO space
                stations. It would retain the existing separate regulatory fee category
                for small satellites and spacecraft licensed under 47 CFR 25.122
                through 25.123. For the reasons discussed in the NPRM, this alternative
                methodology may be more fair, administrable, and sustainable than the
                existing methodology, and the Commission seeks comment on all aspects
                of this alternative approach.
                II. Background
                A. Communications Act Requirements
                 5. Section 9 of the Communications Act of 1934, as amended, 47
                U.S.C. 159, obligates the Commission to assess and collect regulatory
                fees each year in an amount that can reasonably be expected to equal
                the amount of its annual salaries and expenses (S&E) appropriation. In
                accordance with the statute, each year, in an annual fee proceeding,
                the Commission proposes adjustments to the prior fee schedule under 47
                U.S.C. 159(c) to reflect unexpected increases or decreases in the
                number of units subject to the payment of such fees, and result in the
                collection of the amount required by the Commission's annual
                appropriation. Pursuant to 47 U.S.C. 159A(b)(1) of the Act, the
                Commission must notify Congress immediately upon adoption of any
                adjustment. The Commission will also propose amendments to the fee
                [[Page 20584]]
                schedule under 47 U.S.C. 159(d) if the Commission determines that the
                schedule requires amendment so that such fees reflect the full-time
                equivalent number of employees within the bureaus and offices of the
                Commission, adjusted to take into account factors that are reasonably
                related to the benefits provided to the payor of the fee by the
                Commission's activities. Pursuant to 47 U.S.C. 159A(b)(2), the
                Commission must notify Congress at least 90 days prior to making
                effective any amendments to the regulatory fee schedule.
                 6. The Commission initiates the proceeding to seek comment on
                possible changes to the existing methodology for assessing space and
                earth station regulatory fees, ahead of its annual Commission-wide
                regulatory fee proceeding for the fiscal year, to adopt amendments to
                the existing space and earth station regulatory fee categories or to
                adopt new regulatory fee categories in time for those changes to be
                effective for FY 2024. Because changes to the regulatory fee categories
                require 90-day prior notification to Congress to be effective for FY
                2024, any changes to the space and earth station regulatory fee
                categories would have to be adopted and notification of the changes
                would have to be timely provided to Congress to become effective before
                the end of FY 2024. While the Commission initiates the examination and
                review of the existing methodology for assessing regulatory fees for
                space and earth station payors in NPRM, it will propose and finalize
                the regulatory fee rates for space and earth station payors as part of
                its annual Commission-wide regulatory fee proceeding for FY 2024.
                Commenters will have an opportunity in that proceeding to provide
                comments on the proposed regulatory fee rates for space and earth
                station payors.
                B. Space and Earth Station Regulatory Fees and Methodology
                 7. The existing schedule of regulatory fees for space and earth
                station payors is contained in 47 CFR 1.1156. There are four current
                categories of space station payors: Space Stations (Geostationary
                Orbit); Space Stations (Non-Geostationary Orbit)--Less Complex; Space
                Stations (Non-Geostationary Orbit)--Other; and Space Station (Small
                Satellites). ``Less Complex'' NGSO systems are defined as NGSO
                satellite systems planning to communicate with 20 or fewer U.S.
                authorized earth stations that are primarily used for Earth Exploration
                Satellite Service (EESS) and/or Automatic Identification System (AIS).
                ``Small Satellites'' are space stations licensed pursuant to the
                streamlined small satellite process contained in 47 CFR 25.122. The
                Space Stations (Small Satellites) category also includes ``small
                spacecraft'' licensed pursuant to the analogous streamlined procedures
                of 47 CFR 25.123. In addition, there is a single category of earth
                station payors--Earth Stations: Transmit/Receive & Transmit only. Since
                the Commission's fiscal year 2020 proceeding, non-U.S. licensed space
                stations granted market access to the United States through a Petition
                for Declaratory Ruling or through earth station licenses are subject to
                regulatory fees.
                 8. For FY 2023, the regulatory fee amount per category of space and
                earth station payor were as follows:
                ------------------------------------------------------------------------
                 FY 2023 fee
                 Fee category amount
                ------------------------------------------------------------------------
                Space Stations (Geostationary Orbit).................... $117,580
                Space Stations (Non-Geostationary Orbit)--Less Complex.. 130,405
                Space Stations (Non-Geostationary Orbit)--Other......... 347,755
                Space Stations (per license/call sign in non- 12,215
                 geostationary orbit) (Small Satellites)................
                Earth Stations: Transmit/Receive & Transmit only (per 575
                 authorization or registration).........................
                ------------------------------------------------------------------------
                 9. Under the existing methodology of calculating regulatory fees
                for space and earth station payors, the Commission multiplies the space
                station and earth station FTE allocation percentages by the target goal
                of collections (overall total amount to collect), respectively, to
                determine the amount to be collected from each regulatory fee category.
                Since 2020, the space station allocation percentages reflect an 80/20
                split between the GSO and NGSO regulatory fee categories, respectively.
                The amount to be collected by the space station and earth station
                regulatory fee categories, divided by the projected number of units,
                determines the fee rate. There are several space station regulatory fee
                categories--GSO, NGSO--Other, NGSO--Less Complex, and small
                satellites--and each of these regulatory fee categories has its own
                respective FTE allocation percentage to determine the fee rate. The
                small satellite fee rate is calculated by taking the average of the
                calculated fee rate for space stations in the NGSO--Other and
                NGSOSec. Less Complex categories. The average fee rate is then
                multiplied by 5% (1/20) and rounded to the nearest $5 to determine the
                small satellite fee rate. The small satellite fee rate is then
                multiplied by the number of small satellite units, and the amount
                derived is divided by an 80/20 split and reduced from the target goals
                of NGSO--Other and NGSO--Less Complex, respectively. After reducing the
                NGSO--Other and NGSO--Less Complex target goal amounts, the fee rates
                for both of these NGSO regulatory fee categories are re-calculated
                (dividing the revised target goal by its respective unit count) to
                reflect a slightly lower fee rate.
                 10. The units of assessment for GSO and NGSO space station
                regulatory fee categories differ in that the fee for Space Stations
                (Geostationary Orbit) is assessed per satellite in geostationary orbit,
                whereas the fee assessed for Space Stations (Non-Geostationary Orbit),
                either ``less complex'' or ``other,'' is per ``system'' of satellites,
                with no limit on the number of satellites per system. Fees for Space
                Stations (Small Satellites) are assessed per license/call sign, which
                can include up to 10 satellites or spacecraft. This means that the unit
                of regulatory fees for GSO space stations is a single satellite,
                whereas the unit of regulatory fees for NGSO space stations can include
                tens, if not thousands, of satellites. Thus, although the single
                highest regulatory fee for space stations for FY 2023 is $347,755 for
                Space Stations (Non-Geostationary Orbit)--Other, this fee reflects the
                regulatory burden associated with the licensing and oversight of
                numerous space stations in the system, usually subject to processing
                rounds, complex spectrum sharing arrangements, and providing global
                coverage. By contrast, the per unit fee for Space Stations
                (Geostationary Orbit) for FY 2023 is lower at $117,580, but an operator
                providing global coverage may be paying regulatory fees on multiple
                space stations in geostationary orbit, which could result in annual
                regulatory fee payments by a single fee payor in aggregate far greater
                than the regulatory fee for Space Stations (Non-Geostationary Orbit)--
                Other providing similar services and coverage. Earth station regulatory
                fees are assessed ``per license or registration,'' and each license
                [[Page 20585]]
                or registration may include a single earth station, or multiple earth
                stations.
                 11. In addition, regulatory fees are assessed solely on
                ``operational'' space stations. A space station is considered to be
                operational when the operator reports under the Commission's reporting
                requirements for space stations that the space station or stations have
                been successfully placed into orbit and that operations conform to the
                terms and conditions of the space station authorization. Similarly, if
                an earth station's license limits its operational authority to a
                particular satellite system, a regulatory fee payment is not due until
                the first satellite in that system becomes operational.
                 12. For FY 2023, the number of units for the earth station fee
                category was 2,900. The number of units for Space Stations
                (Geostationary Orbit) was 136; the number of units for Space Stations
                (Non-Geostationary Orbit)--Other was nine; the number of units for
                Space Stations (Non-Geostationary Orbit)--Less Complex was six; and the
                number of units for Space Stations (Small Satellites) was seven. These
                unit counts and fees resulted in a total expected regulatory fee
                revenue of $21,656,110 from space and earth station payors for FY 2023,
                which is the sum of $1,667,500 expected to be paid by earth station
                payors (7.69% of all space and earth station regulatory fees),
                $15,990,880 expected to be paid by Space Stations (Geostationary Orbit)
                (73.84%), $3,129,795 expected to be paid by Space Stations (Non-
                Geostationary Orbit)--Other (14.45%), $782,430 expected to be paid by
                Space Stations (Non-Geostationary Orbit)--Less Complex (3.61%), and
                $85,505 expected to be paid by Space Stations (Small Satellites)
                (0.39%).
                III. Discussion
                A. Space Bureau FTEs
                 13. Pursuant to 47 U.S.C. 159(d), the Commission's methodology for
                assessing regulatory fees must reflect the full-time equivalent number
                of employees within the bureaus and offices of the Commission, adjusted
                to take into account factors that are reasonably related to the
                benefits provided to the payor of the fee by the Commission's
                activities. The Commission first sets forth the anticipated number of
                full-time equivalent number of employees, or FTEs, that will be in the
                new Space Bureau for purposes of assessing regulatory fees for FY 2024.
                The Commission previously anticipated that the changes in the satellite
                industry, which led to the reorganization of the International Bureau
                into the Space Bureau and the Office of International Affairs, might
                result in a larger number of FTEs devoted to space and earth station
                licensing, regulation, industry analysis, and oversight due to
                increased regulatory complexity that resulted from technological
                changes in the industry. Accordingly, the Commission stated that it
                would closely review the Space Bureau and Office of International
                Affairs FTEs to determine the appropriate number of FTEs in each entity
                as a result of the reorganization and how they will be apportioned
                among the different services.
                 14. The Commission's Human Resources Management office provided
                initial data identifying 54 FTEs in the Space Bureau to be counted for
                FY 2024. The Commission anticipates that these FTEs will be categorized
                as direct FTEs, with the exception of a small number of FTEs that work
                exclusively, or nearly exclusively, on administrative activities, with
                the staff of the Office of International Affairs on covering
                International Telecommunications Union (ITU) World Radiocommunications
                Conference (WRC) agenda items, or with the staff of the Commission's
                Office of Engineering & Technology on experimental licenses involving
                space or earth stations. The Commission expects such FTEs to be
                categorized as indirect FTEs, since such work does not focus on the
                oversight and regulation of a specific category of regulatory fee
                payors, but instead benefits the Commission, the telecommunications
                industry, or the public as a whole, or in the case of work done on
                experimental licenses, is in furtherance of licenses that are not
                subject to a regulatory fee. The Commission also anticipates that a
                small number of FTEs from the Office of Economic and Analytics and the
                Public Safety and Homeland Security Bureau will be attributed as direct
                FTEs to the Space Bureau. For the sake of efficiency, the Commission
                will make its final proposals regarding the Space Bureau's total share
                of all Commission direct FTEs, as part of a notice of proposed
                rulemaking to be released at a later date for the Commission-wide
                assessment of regulatory fees for FY 2024.
                 15. Nonetheless, the Commission anticipates that the number of
                direct FTEs in the Space Bureau for FY 2024 will be greater than the 28
                direct FTEs that were allocated to the International Bureau for FY
                2023. Based on initial estimates, the Space Bureau FTEs could account
                for 10.76% of all Commission direct FTEs for FY 2024, compared with the
                International Bureau accounting for 7.77% in FY 2023. The Commission
                also expects that space and earth station payors will pay significantly
                more in regulatory fees in FY 2024 than in FY 2023. This is chiefly
                because the Commission anticipates there will be more direct FTEs in
                the Space Bureau attributable to space and earth station fee payors
                than there were in the International Bureau, due to the increased
                regulatory complexity and oversight required, which will result in a
                larger percentage of overall regulatory fees being allocated to the
                Space Bureau, assuming there is no offsetting increase in the number of
                FTEs in other core bureaus and offices. Accordingly, there is increased
                importance in examining how FTEs are apportioned among the categories
                of Space Bureau fee payors to ensure that the fee apportionment
                methodology is administrable, fair, and sustainable.
                B. Space Station Fee Proposals
                1. Allocation Between GSO and NGSO Space Stations
                 16. If the existing methodology for assessing regulatory fees for
                space stations is maintained, the Commission proposes to change the
                allocation of the regulatory fees between GSO and NGSO fee payors to
                reflect more accurately the apportionment of current FTE work between
                these two classes of regulatory fee payors. Under the existing
                allocation adopted in 2020, 80% of space station regulatory fees are
                allocated to GSO space station fee payors and 20% of the space station
                regulatory fees to NGSO space station fee payors. For the reasons
                stated in the NPRM, the Commission proposes to change this allocation
                to 60% of space station regulatory fees being allocated to GSO space
                station payors and 40% to NGSO space station payors.
                 17. In proposing this change in allocation, the Commission employs
                the same methodology that was used by the Commission in 2020 in
                adopting the ``80/20'' split between GSO and NGSO space station fee
                payors. Specifically, the Commission focuses on three factors that
                collectively reflect its oversight of GSO and NGSO operators: the
                number of applications processed, the number of changes made to the
                Commission's rules, and FTEs devoted to oversight of each category of
                operators.
                 18. First, using the advanced search function of the International
                Communications Filing System (ICFS), the Commission identified all
                applications for space stations (service type: SAT) filed during the
                three most recent fiscal years (that is, FY 2021-2023) for both GSO
                (class of service:
                [[Page 20586]]
                SSG) and NGSO (class of service: SSN). A total of 526 distinct
                applications for space stations were filed during this time period,
                with 322 applications being filed for GSO space stations (61%) and 204
                applications for NGSO space stations (39%). Thus, the number of
                applications received during this three-year period supports a larger
                allocation of FTE time to GSO fee payors than to NGSO fee payors, but
                in a narrower range than the current 80/20 split.
                 19. Second, using compiled data through a search of the FCC's
                Electronic Comment Filing System (ECFS) and a cross check of items on
                the web pages of the FCC and the International Bureau/Space Bureau for
                the last three fiscal years, the Commission identified docketed
                proceedings originating from the International Bureau's Satellite
                Division, or from the Space Bureau, and considered to the involvement
                of GSO and NGSO space stations in each proceeding. The Commission
                analyzed the data to estimate whether a particular docketed proceeding
                involved GSO or NGSO space station payors, or both. It did not count
                docketed proceedings for transfer of control or assignment applications
                or other docketed proceedings that did not make changes to the
                Commission's rules. It included, however, a docketed proceeding to
                modify the conditions relating to the International Telecommunications
                Satellite Organization placed on the licenses of a GSO space station
                operator, even though it was not a rulemaking proceeding, because it
                involved changes to the conditions on a large number of space station
                licenses that required significant FTE resources to process.
                 20. The Commission identified 16 proceedings during FY 2021-2023,
                of which 8 substantively involved GSO space stations (50%) and 12
                substantively involved NGSO space stations (75%). Accordingly, the data
                presented suggests that there were more rulemakings substantively
                involving NGSO space stations than GSO space stations. The Commission
                notes that quantifying only the most recent rulemaking activities does
                not take into account past rulemakings that are of continued relevance
                to space stations and are administered by Commission FTEs either
                through licensing, interpretation and application of those rules in
                other proceedings, or in consultation with the space station
                regulatees. Thus, attributing a value to rulemaking activities directly
                is not an exercise in scientific precision, but rather an exercise in
                reasonable analysis and a mechanism to verify the other data the
                Commission reviews. On balance, however, the Commission tentatively
                concludes that these rulemaking data support a greater allocation of
                regulatory fees to NGSO space station payors than is currently the
                case.
                 21. Third, the Commission considered whether it could examine FTE
                activities directly, but although there has been a change in the number
                of FTEs attributable to satellite regulatory activities due to the
                creation of the Space Bureau, it remains challenging to segregate the
                time spent by FTEs on work done on GSO versus NGSO matters. As was the
                case in the International Bureau, staff time spent in the Space Bureau
                on authorizations and rulemakings may benefit both categories of
                satellite operations. Based on its experience and judgement, the
                Commission estimates as closely as possible the relative percentage of
                FTEs that are attributable to benefitting either GSO or NGSO systems
                based on the factors above.
                 22. While there are issues of fact, law, engineering, and the
                physics of electromagnetic propagation that may be unique to GSO or
                NGSO space stations, many issues that Space Bureau staff work on are
                not segregable in a manner that is beneficial to clearly apportioning
                FTE time between GSO and NGSO regulatory fee categories. Taking all of
                the foregoing factors and data into consideration, the Commission
                tentatively concludes, however, that the GSO/NGSO ratio should be
                adjusted to reflect that GSO space stations derived roughly 60% of the
                benefit from the Commission's regulatory efforts and NGSO space
                stations derived roughly 40%. Accordingly, for FY 2024, the Commission
                proposes that GSO and NGSO space stations will be allocated 60% and 40%
                of space station regulatory fees, respectively. The Commission seeks
                comment on this tentative conclusion and proposal.
                2. Allocation Between NGSO--Other and NGSO--Less Complex
                 23. If the existing methodology for assessing regulatory fees for
                space stations is maintained, the Commission proposes to maintain the
                existing allocation of the regulatory fee burden between ``Space
                Stations (Non-Geostationary Orbit)--Less Complex'' and ``Space Stations
                (Non-Geostationary Orbit)--Other.'' Currently, 20% of NGSO space
                station regulatory fees are allocated to Space Stations (Non-
                Geostationary Orbit)--Less Complex and 80% are allocated to Space
                Stations (Non-Geostationary Orbit)--Other fee payors. As discussed
                elsewhere in the NPRM, the Commission has defined ``less complex'' NGSO
                systems as NGSO satellite systems planning to communicate with 20 or
                fewer U.S. authorized earth stations that are primarily used for EESS
                and/or AIS. The Commission has concluded that EESS systems are less
                burdensome to regulate than other types of services when the systems
                plan to communicate with 20 or fewer earth stations. NGSO satellite
                systems outside of this definition are included in the NGSO ``other''
                fee category, unless they qualify as ``small satellites'' under
                Commission rules and are included in the regulatory fee category for
                small satellites.
                 24. The Commission tentatively concludes that there have not been
                any significant changes to the amount of FTE burdens allocated between
                these two fee categories since the ``20/80'' split of regulatory fees
                between NGSO ``less complex'' and NGSO ``other'' subcategories was
                adopted in 2021. As was the case in 2021, the Commission considers its
                experience and analysis of the time that FTEs in the International
                Bureau and the Space Bureau devote to oversight and regulation of
                ``less complex'' and ``other'' NGSO systems. Specifically, now--as
                then--the Commission considers the number of applications processed,
                the number of changes made to the Commission's rules, and the number of
                FTEs working on oversight for each category of operators. This
                methodology is the same as used for determining the allocation of
                regulatory fees among GSO and NGSO space station fee payors. In
                evaluating the FTE time devoted to the ``less complex'' and ``other''
                subcategories, the Commission considers its adjudicatory role in
                connection with different types of NGSO systems, which is typically
                more intensive for those systems authorized as part of processing
                rounds. The Commission also considers the number of rulemakings over
                the last three fiscal years, as well as current rulemakings, and which
                types of NGSO systems are implicated in those rulemaking activities.
                 25. Based on its experience and judgement, the Commission estimates
                as close as possible the relative percentage of FTE time attributable
                to oversight of each subcategory of NGSO space stations. Its
                examination does not reveal any rulemaking proceedings in the last
                three fiscal years that are specific to EESS space stations eligible
                for the ``less complex'' NGSO subcategory, but did reveal several
                rulemakings in that same period specific to NGSO ``other'' systems.
                Similarly, an examination of applications filed over the previous three
                fiscal years (FY 2021-2023) shows that 44 NGSO applications out of 204
                NGSO applications were by systems
                [[Page 20587]]
                categorized as NGSO ``less complex'' (22%). The Commission's
                consideration of activities engaged in by staff and the time spent on
                oversight of different NGSO systems does not indicate any change from
                its consideration in 2021, which resulted in a determination that NGSO
                ``other'' were the majority beneficiaries of FTE efforts.
                 26. The Commission recognizes the considerable challenge of
                segregating the time spent by Space Bureau staff among the
                subcategories of NGSO space stations, nonetheless the considerations
                above support the tentative conclusion that more FTE time is spent on
                the NGSO ``other'' subcategory than on the NGSO ``less complex''
                subcategory. The number of applications in the NGSO ``less complex''
                subcategory received over the last three fiscal years supports a
                tentative conclusion that the relative regulatory burden of such ``less
                complex'' space stations remains consistent with the current 20%
                allocation. The Commission seeks comment on this tentative conclusion.
                 27. The Commission does not propose at this time to revisit the
                definition of ``less complex'' NGSO space stations, which has been
                adopted and affirmed over the course of several regulatory fee
                rulemaking proceedings. As expressly recognized, however, the
                Commission does not foreclose the possibility of designating other
                categories of NGSO systems as ``less complex'' systems in the future if
                the Commission's experience supports a finding that its regulatory work
                for such systems is significantly less than those for other NGSO
                systems. The Commission's experience to date has not supported such a
                designation for other types of NGSO systems, and the Commission does
                not have a sufficient record to make proposals for such designations at
                this time.
                3. Creation of Tiers of NGSO--Other
                 28. If the existing methodology for assessing regulatory fees for
                space stations is maintained, the Commission proposes to divide the
                existing regulatory fee subcategory of ``Space Stations (Non-
                Geostationary Orbit)--Other'' into two tiers: ``Large Constellations''
                of more than 1,000 authorized space stations; and ``Small
                Constellations'' of 1,000 or fewer authorized space stations.
                Currently, there is a single subcategory for NGSO ``other'' space
                station systems, which assesses the same annual regulatory fee--
                $347,755 for FY 2023--for all NGSO space station systems that are not
                categorized as ``less complex'' or ``small satellites.'' NGSO space
                station payors have argued that this ``one fee fits all'' assessment is
                unfair, as it assesses the same regulatory fee on an NGSO system
                consisting of 100 space stations as the fee assessed for an NGSO system
                consisting of potentially 10,000 or more space stations. The current
                single regulatory fee for all NGSO ``other'' space station payors
                resulted in requests by fee payors of smaller NGSO systems seeking to
                be assessed regulatory fees as NGSO ``less complex'' systems, even
                though the record at the time did not support a finding that the
                regulatory work for such systems was significantly less than other
                types of NGSO systems. The Commission uses this proceeding to explore
                whether its existing regulatory fee structure can be better tailored to
                the varying nature of NGSO systems and differing levels of licensing
                and regulatory oversight burdens required for these various systems,
                while maintaining a system that is fair, administrable, and
                sustainable.
                 29. The unit of assessment for Space Stations (Non-Geostationary
                Orbit), either ``less complex'' or ``other,'' is ``per system'' of
                satellites. This unit of assessment reflects the ability of applicants
                to apply for, and be authorized to operate, a ``system'' of NGSO space
                stations, with no limit on the number of space stations per system.
                Each initial application for authority is granted under a single ``call
                sign'' as a regulatory identifier. In many cases the Commission has
                assessed a single regulatory fee for an NGSO system consisting of space
                stations requested and authorized under different call signs. The
                assessment of regulatory fees for NGSO space stations on a ``per
                system'' basis extends back to the first time that the Commission
                assessed regulatory fees for ``Low Earth Orbit (LEO) Satellite
                Systems'' in 1996. The choice of a ``system'' as the unit of assessment
                for LEO satellites was based in the original text of 47 U.S.C. 159,
                which included a ``Schedule of Regulatory Fees'' that the FCC was
                required to assess and collect, until amended by the Commission. The
                Schedule of Regulatory Fees included fee categories for ``Space Station
                (per operational station in geosynchronous orbit)'' and ``Space Station
                (per system in low-earth orbit).'' The Schedule of Regulatory Fees,
                however, was deleted from 47 U.S.C. 159 by the RAY BAUM's Act of 2018.
                 30. The sole exception made to assessment of NGSO space station
                regulatory fees on a ``per system'' basis is for small satellites, for
                which the Commission adopted a separate regulatory fee category in
                which small satellites are assessed on a ``per license/call sign''
                basis. The Commission found that adopting the regulatory fee on a per-
                license basis would not only accurately reflect the increased oversight
                and regulation for these small satellite systems when an operator has
                multiple small satellite licenses, but also it would be more efficient
                and administrable because it avoids potential complications and
                additional FTE time spent in determining whether various sets of small
                satellites are part of the same system.
                 31. In creating the separate fee categories of ``less complex''
                NGSO space stations and small satellites operating in non-geostationary
                orbit, the Commission has previously recognized that not all NGSO space
                stations are the same, and that different NGSO space stations can be
                assessed different regulatory fees based on the differing amount of FTE
                regulatory work is devoted to them, consistent with the statutory
                obligations of 47 U.S.C. 159. Accordingly, the default unit of fee
                assessment for NGSO space stations--the ``system''--by itself does not
                indicate the amount of regulatory fees to be recovered from a
                particular NGSO space station payor. Instead, the Commission has used
                other factors as proxies for the amount of regulatory work required for
                a category of fee payors. For ``less complex'' space stations, the
                Commission relied on the primary service to be provided (EESS or AIS)
                and the number if U.S.-licensed earth station planned for
                communications (20 or fewer) as proxies for other factors for
                determining whether a category of NGSO space station system involved
                less staff resources to license and regulate than NGSO space station
                ``other'' systems: whether processing rounds are required, whether the
                system will have a global presence, the range and intensity of spectrum
                needs, and the variety of frequency bands, technical issues, and
                services presented.
                 32. The Commission in the NPRM seeks to explore whether the number
                of space stations requested for an NGSO system could serve as a proxy
                for the Commission's regulatory burden, when combined with other
                factors that went into determining whether an NGSO system is, or is
                not, ``less complex'' for regulatory fee assessment purposes. Does a
                greater number of space stations authorized per system equate to
                greater staff burdens to license and regulate, if the greater number of
                space stations per system also correlates to the other factors relevant
                to NGSO systems that do not qualify for inclusion in the NGSO space
                stations ``less complex'' subcategory (that is, they fall within the
                ``other'' NGSO fee category because they
                [[Page 20588]]
                are subject to processing rounds, have a global presence, have
                significant spectrum needs, and present a variety of frequency bands,
                technical issues, and services)? If so, is it reasonable to assume that
                a greater number of space stations authorized per system would equate
                to greater amount of FTE time to license and regulate? Although the
                Commission has previously stated that number of space stations in an
                NGSO system does not always correspond to increased regulatory
                complexity, those statements were based on consideration of the
                regulatory impact of the number of space stations in isolation, not
                when considered in connection with the other factors relevant to non-
                ``less complex'' NGSO space station systems. Is it a reasonable
                expectation that, if an NGSO space station system is not found to be
                ``less complex'' for regulatory fee assessment purposes, the amount of
                FTE resources needed to license and regulate that system increases as
                the number of space stations increases because, on average, the greater
                the number of space station considered, the greater the amount of
                spectrum resources required for the system, the greater complexity of
                spectrum sharing with other systems, the more complicated the orbital
                debris mitigation plan will be, and the greater number of earth
                stations required to support the space station system? The Commission
                seeks comment on this expectation.
                 33. Accordingly, if the Commission maintains the existing space
                station regulator fee methodology, it proposes to transform the
                existing ``Space Stations (Non-Geostationary Orbit)--Other'' category
                into a two-tiered category, with one tier for ``Large Constellations''
                and one tier for ``Small Constellations.'' The proposal to create tiers
                of NGSO space station regulatory fees is not new, being first made in
                1999. As recently as 2021 and 2020, the Commission was presented with
                proposals to assess NGSO space station regulatory fees based on the
                total number of satellites deployed, but it declined to do so because
                the evidence in the record at the time was insufficient to establish
                different fees for different sized NGSO space station systems. The
                Commission proposes to use the NPRM to establish such a record to
                evaluate the appropriateness of adopting regulatory fees for large and
                small NGSO systems. Although the Commission acknowledges that it is
                inherently challenging to establish the dividing line between such
                tiers, it proposes 1,000 space stations as the dividing number for
                large and small systems. The Commission seeks comment on this proposal.
                Is 1,000 the right number, or is there a different number, greater or
                less than 1,000, that better reflects the delineation in the amount of
                FTE burdens to license and regulate NGSO systems of variable sizes (for
                example, 500 space stations)?
                 34. If the Commission adopts the tiered approach for the NGSO space
                station ``other'' category under its existing methodology, it proposes
                to create two tiers, rather than three or more tiers, in order to
                facilitate administrability, because there are relatively few units
                within the existing NGSO space station ``other'' category, and dividing
                that category into many tiers with a narrow range of space stations per
                tier may result in only one payor being responsible for the entire cost
                of the tier, or there being no payor for a particular tier in a fiscal
                year, shifting the costs of that tier to payors in other tiers.
                Importantly, it may be harder to justify the difference in FTE burdens
                when tiers are more narrowly defined. The Commission tentatively
                concludes that a two-tiered approach will not only appropriately
                account for differences in regulatory burdens between NGSO space
                station systems of different sizes, but also provide a measure of
                consistency from one year to the next in the number of payors and the
                per unit fee. The Commission seeks comment on the proposal to use two
                tiers in its approach and its tentative conclusion that a two-tiered
                approach will result in greater administrability than a multi-tiered
                approach. The Commission also proposes that its tiered approach be
                based on the number of authorized space stations in a system, rather
                than the number of space stations that are operational in a system at
                the moment that regulatory fees for a particular fiscal year are
                assessed. This proposal is consistent with its proposal elsewhere in
                the NPRM that all regulatory fees be assessed on authorized, rather
                than operational, space and earth stations. The Commission seeks
                comment on this proposal.
                 35. The Commission proposes to divide the total NGSO--``other''
                fees between the two subcategories on a 50/50 basis (that is, half of
                the NGSO ``other'' fees paid by ``large constellations'' and half paid
                by ``small constellations''). It acknowledges the difficulty in
                allocating regulatory fee burdens between ``large constellations'' and
                ``small constellations,'' because staff in the Space Bureau may work on
                both types of constellations and rulemaking proceedings often do not
                differentiate between large and small constellations. The Commission
                accordingly seeks comment on its proposal to divide the total NGSO--
                ``other'' fees between small and large constellations on a 50/50 basis.
                If the fees are not divided on a 50/50 basis, what would be a more
                appropriate division and why? The Commission notes that although the
                total costs would be allocated evenly between ``large'' and ``small''
                constellations, it expects that there will be a greater number of units
                in the ``small constellations'' tier than the ``large constellations''
                tier, and that that number of units in the ``small constellations''
                tier will increase in the future, thereby resulting in a smaller per
                payor fee for the ``small constellations'' tier for future years. By
                contrast, the Commission expects that there will be only two to three
                payors in the large constellation tier for FY 2024, and that it is
                unlikely that that number will increase substantially in the
                foreseeable future. The Commission seeks comment on this proposed
                division and its expectations.
                 26. The Commission finds that the proposal to create fee categories
                for NGSO large and small constellations would be an amendment as
                defined in 47 U.S.C. 159. Such an amendment must be submitted to
                Congress at least 90 days before it becomes effective pursuant to 47
                U.S.C. 159A(b)(2).
                 27. The Commission also seeks comment on other possible proxies
                that might reasonably equate with the share of FTE burdens associated
                with each system within the ``Space Stations (Non-Geostationary
                Orbit)--Other'' category, as alternatives to the 50/50 two-tiered
                approach proposed elsewhere in the NPRM. Other possible proxies include
                assessing regulatory fees for NGSO space station ``other'' using any of
                the following individual metrics: (1) per space station; (2) per
                subscriber; (3) per unit of spectrum authorized; (4) per class of
                service provided; and (5) per unit of on-orbit mass. The NPRM describes
                each possible proxy.
                 38. Per Space Station. Under this metric, the overall FTE burden of
                a NGSO ``other'' system would be proxied on the basis of the number of
                authorized space stations in the system, without utilizing a tiered
                system. The fee would be assessed on a per space station basis, with
                the total fee amount attributable to Space Stations (Non-
                Geostationary)--Other being divided by the number of space stations
                authorized in that category to establish a per space station fee unit.
                Each space station in the system would add incrementally to the amount
                of regulatory fees paid by the system. This alternative avoids the
                situation where a system may exceed the number of space stations
                eligible for
                [[Page 20589]]
                the small constellation tier by only a few space stations, which will
                result in the system paying the substantially higher fee for large
                constellations. The alternative potentially presents the situation,
                however, where systems with a very large number of authorized space
                stations (for example, 20,000 or more) could effectively end up paying
                all, or nearly all, the regulatory fees for the NGSO ``other''
                category, since the number of space stations in that system could be
                more than all other systems combined in that category. Such an outcome
                may not accurately reflect the FTE burdens imposed by the various
                payors of the NGSO space stations ``other'' category by substantially
                underrepresenting the amount of FTE resources spent on all other fee
                payors in the NGSO ``other'' category. Could this concern be addressed
                by setting a ``cap'' or ``ceiling'' on the number of authorized space
                stations for which regulatory fees would be assessed or having a
                decreasing fee for each additional space station? Although the
                Commission has previously disagreed with proposals to assess space
                station regulatory fees on a per space station basis, it nonetheless
                seeks comment on the use of number of space stations as an alternative
                metric for assessing the regulatory fee burden for each NGSO ``other''
                system.
                 39. Per Subscriber. Under this alternative, regulatory fees for
                NGSO space stations ``other'' would be assessed on a per subscriber
                basis, possibly using tiers of subscribers. The Commission observes,
                however, that not all NGSO systems have subscribers, and it does not
                currently collect information regarding subscriber numbers. Thus, to
                utilize subscriber information a review of an additional information
                collection may be required in order to assess regulatory fees on this
                basis. The time required to obtain the approval and collect the
                information would make the possibility of assessing fees on this basis
                for FY 2024 unlikely. The Commission also expects that it would require
                substantial FTE resources to calculate and assign fees for individual
                systems based on yearly subscriber numbers, which could in turn result
                in more FTEs being attributed to space station systems for regulatory
                fee recovery purposes. Furthermore, the Commission seeks comment on
                whether subscriber numbers are considered confidential by regulatees
                and, if so, how would that impact this approach?
                 40. Per Unit of Spectrum Authorized. An alternative proxy for the
                amount of FTE burden associated with a system in the NGSO space station
                ``other'' category could be the amount of spectrum resources authorized
                for the system. Systems that involve the use of a large amount of
                spectrum can require more FTE resources to license and regulate due to
                the likelihood of the increased need to coordinate with, and to address
                the interference concerns of, other spectrum users, compared to systems
                with smaller spectrum requirements. Thus, regulatory fees for NGSO
                space stations ``other'' could be assessed per unit of authorized
                spectrum, for example, per megahertz of spectrum authorized for the
                system. The Commission observes that the distinction between NGSO
                ``other'' and NGSO ``less complex'' already takes into account spectrum
                usage and ease of coordination in delineating between these two fee
                categories, so it is unclear what further delineation could be made
                within the NGSO space station ``other'' category based on authorized
                spectrum. In addition, not all spectrum is uniform in its complexity to
                license and regulate. For example, it may be easier to license and
                regulate an NGSO system operating in 500 megahertz of spectrum
                allocated to NGSO space station use on a primary basis than licensing
                and regulating an NGSO system operating in 20 megahertz of spectrum
                operating on a secondary or non-interference basis. The Commission has
                previously found that total bandwidth is not consistently indicative of
                the complexity of NGSO regulation. The NPRM seeks comment, however, on
                this alternative proxy and whether there any basis to question the
                Commission's previous conclusion that total bandwidth does not
                consistently reflect the complexity of NGSO regulation.
                 41. Per Class of Service Provided. Commenters in previous
                regulatory fee assessment proceedings have suggested that the type of
                services provided by NGSO space station systems could be used as a
                proxy for the amount of FTE resources dedicated to licensing and
                regulating such systems. In addition to the orbit used (GSO or NGSO),
                space stations are regulated by the type of service that they provide,
                for example mobile-satellite service (MSS), fixed-satellite service
                (FSS), direct broadcast satellite service (DBS), and satellite digital
                audio radio service (SDARS). The Commission has previously found that
                the type of service primarily being provided (EESS and/or AIS) was a
                relevant factor in determining whether an NGSO system was ``less
                complex'' for purposes of regulatory fee assessments, when combined
                with another factor (the number of earth stations authorized by the
                United States with which the system plans to communicate). The
                Commission has not found, however, that other types of satellite
                services warrant a determination that a NGSO system is ``less complex''
                for regulatory fee purposes, although it did not rule out the
                possibility of doing so if the record supported such a finding.
                Although the Commission does not propose that any particular additional
                service be considered as a factor that an NGSO system is ``less
                complex'' for regulatory fee purposes, it may be possible to use the
                type of service provided as a proxy for FTE resources to delineate
                additional fee subcategories within the ``Space Stations (Non-
                Geostationary Orbit)--Other'' category. The NPRM seeks comment on this
                possibility. Comments should focus on the specific licensing and
                regulatory factors that differentiate the services and explain how the
                Commission would be able to allocate FTE time among these services.
                Comments should also address the administrability and sustainability of
                subcategories of regulatory fees in the NGSO space station ``other''
                category based on the services provided by the space stations. For
                example, if a space station is authorized to provide multiple types of
                services, such as both FSS and MSS, how would it be determined which
                regulatory fee subcategory it belongs to? If it is determined based on
                the primary service that is authorized for a system, how should the
                Commission determine which service is primary? Would fee categories
                based on the service provided be relatively stable from year to year,
                or is it possible that there could be substantial changes in the number
                of fee payors in a service category year to year? Would every single
                service provided by a system need to be taking into account, or just
                the primary service? Would substantial FTE resources be needed to
                calculate and assign fees for individual systems based on primary
                services provided, which could in turn result in more FTEs being
                attributed to space station systems for regulatory fee recovery
                purposes?
                 42. Per Unit of On-Orbit Mass. Comments in previous years'
                regulatory fee assessment proceedings have suggested to use the mass of
                space stations as one proxy for an NGSO system's complexity. This
                suggestion is similar to the proposal in the NPRM to use of number of
                authorized space stations in an NGSO system as a proxy for regulatory
                burdens of systems in the NGSO space station ``other'' category, but
                considers the mass of the space stations in an NGSO system rather than
                the number of space stations. Thus, an NGSO system with 10 space
                stations with a mass of 1,000 kilograms each would pay more in
                regulatory fees than
                [[Page 20590]]
                a system of 100 space stations with a mass of 10 kilograms each. Under
                this proposal, it is assumed that space station mass is a proxy for
                other factors relevant to the amount of FTE work required for the
                licensing and regulation of the system, such as how much spectrum the
                system will use, the number of earth stations that the space stations
                will communicate with, and the complexity of a system's orbital debris
                mitigation plan. Although the Commission has previously found that
                space station mass is not a key driver of NGSO system complexity, the
                NPRM seeks comment on using space station mass as a proxy for the
                regulatory burden involved with an NGSO system. Is it correct that
                regulatory complexity increases in proportion to the mass of the space
                stations in an NGSO system? If so, should mass be assessed on a per
                space station or on an aggregate basis for all space stations in the
                system? Would mass be addressed on a ``wet'' basis (that is, including
                the mass of fuel and other consumables) or ``dry'' basis (that is, the
                mass of the space station without fuel and consumables)? Which basis--
                wet or dry--would more accurately reflect regulatory burdens for that
                system? Furthermore, the Space Bureau no longer collects information
                regarding the mass of a space station as part of the technical
                information required as part of an application for a space station
                authorization or a petition for U.S. market access. Thus, to utilize
                this information in assessing regulatory fees may require a review of
                an additional information collection under the Paperwork Reduction Act.
                The Commission also observes that the time required for such review,
                together with the time needed to collect the information, would rule
                out the possibility of assessing fees on this basis for FY 2024. The
                NPRM seeks comment on the consequences of this observation. Although
                the mass of a space station may be a factor disclosed in the orbital
                debris mitigation plan provided as a part of a space station
                application, the spacecraft mass is disclosed for the specific purpose
                of that analysis, and it is not clear whether it should be relied on
                for the purpose of assessing regulatory fees. Even if it may be
                possible to obtain information about the mass of space stations from
                third party sources, the Commission questions whether it is reasonable
                to rely on information obtained from such sources rather than from the
                fee payors themselves. The NPRM seeks comments on these issues. In
                addition, would substantial FTE resources be needed to calculate and
                assign fees for individual systems based on on-orbit mass, which could
                in turn result in more FTEs being attributed to space station systems
                for regulatory fee recovery purposes?
                 43. The Commission finds that the creation of fee categories for
                ``other'' NGSO space stations based on any of these other possible
                proxies would be an amendment as defined in 47 U.S.C. 159(d). Such an
                amendment must be submitted to Congress at least 90 days before it
                becomes effective pursuant to 47 U.S.C. 159A(b)(2).
                4. Small Satellites
                 44. The Commission seeks comment on a proposal to set the
                regulatory fee for ``Space Stations (per license/call sign in non-
                geostationary orbit) (47 CFR part 25) (Small Satellite)'' for FY 2024
                and future fiscal years at the level set for FY 2023 ($12,215), with
                only an annual adjustments to reflect the percentage change in the FCC
                appropriation, unit count, and FTE allocation percentage from the
                previous fiscal year. As explained elsewhere in the NPRM, the small
                satellite fee rate is calculated by taking the average of the
                calculated fee rate for space stations in the NGSO other and NGSO
                ``less complex'' categories, multiplying this average by 5% (1/20) and
                rounding it to the nearest $5. The small satellite fee rate is then
                multiplied by the number of small satellite units and deducted from the
                NGSO share of space station regulatory fees. This remaining amount is
                then divided between NGSO ``other'' and NGSO ``less complex'' based on
                an 80/20 split and reduced from the target goals of NGSO'' ``other''
                and NGSO ``less complex'' respectively. Because the small satellite fee
                is based on the fees assessed for NGSO other and NGSO ``less complex''
                categories, the increased fees expected for these two categories would
                lead to greatly increased fees for the small satellite regulatory fee
                category beginning in FY 2024.
                 45. The Commission's examination reveals that the number of
                applications, rulemaking procedures, and FTE staff working on small
                satellite matters has not increased greatly since the original
                methodology of assessing regulatory fees for small satellites was
                adopted. To the contrary, the Commission expects that the additional
                FTE resources allocated to the Space Bureau as a result of the
                reorganization of the International Bureau are not intensively involved
                in the licensing and regulatory oversight of small satellites, so that
                the overall percentage of FTE burden for small satellites may be less
                than the 1/20th burden of NGSO space stations. The NPRM seeks comment
                on this expectation and whether it supports the reduction of fees paid
                by small satellites. In addition, the proposals made in the NPRM to
                create subcategories within the NGSO ``other'' category for ``small''
                and ``large'' constellations will add to the complexity of determining
                the appropriate marker for determining the appropriate share of FTE
                resources allocated to small satellites. The Commission proposes the
                administrability and sustainability of its regulatory fees for small
                satellites would be better served by treating them as it has
                historically treated the regulatory fees for earth stations--that is, a
                fixed regulatory fee that is adjusted from year-to-year on, rather than
                as a percentage of the Space Bureau's overall share of regulatory fee
                allocation, or as a percentage of other categories of space station fee
                payors. The NPRM seeks comment on all these proposals, examinations,
                and expectations.
                5. Treatment of RPO, OOS, and OTV
                 46. The Commission proposes, on an interim basis, to assess
                regulatory fees on spacecraft primarily performing Rendezvous and
                Proximity Operations (RPO) and On-Orbit Servicing (OOS) by including
                them in the existing regulatory fee category ``Space Stations (per
                license/call sign in non-geostationary orbit) (Small Satellites)''
                regardless of the orbit in which they are designed to operate in. OOS
                and RPO missions can include satellite refueling, inspecting and
                repairing in-orbit spacecraft, capturing and removing debris, and
                transforming materials through manufacturing while in space. Due to the
                nascent nature of OOS and RPO industry, or more generally ``in-space
                servicing'' industries, there is not a distinct regulatory fee category
                for such operations, despite that fact that spacecraft have begun to
                operate under 47 CFR part 25 for radiocommunications while conducting
                these types of operations. Although the Commission has previously
                determined that the record is not sufficiently complete to adopt a
                separate regulatory fee category for spacecraft performing OOS and RPO,
                it tentatively concludes in the NPRM that it is appropriate to assess
                regulatory fees on RPO and OOS space stations as the Commission does
                for small satellites, rather than as Space Stations (Geostationary
                orbit) or Space Stations (Non-Geostationary Orbit)--Other. The
                Commission also tentatively concludes that it is appropriate to assess
                regulatory fees on Orbital Transfer Vehicles (OTV) in the same manner.
                 47. The Commission first considered adopting additional fee
                categories for RPO and OOS in the notice initiating
                [[Page 20591]]
                the FY 2022 regulatory fee assessment proceeding. At that time,
                commenters proposing such additional fee categories cited the
                similarities between the characteristics of small satellites and RPO
                and OOS. The commenters distinguished between OOS spacecraft and
                traditional NGSO satellites in that OOS spacecraft have limited
                duration and scope of use, as well as a limited number of earth
                stations; require a smaller investment in OOS technology; require less
                ongoing regulation owing to the shorter duration of OOS spacecraft;
                will likely be licensed on a shared use of spectrum basis, and without
                the need for processing round procedures or post-processing round
                disputes over matters such as interference protection and spectrum
                priority. Commenters also submitted that a fee category for RPO
                services would provide much need permanency and clarity to support this
                nascent infrastructure.
                 48. The Commission found, however, that it was premature at that
                time to adopt new fee categories for OOS and RPO operations. It
                observed that there have been a limited number of such operations and
                these were treated on a case-by-case basis, without a specific license
                processing regime. It also expressed the expectation that most OOS and
                RPO operations would involve NGSO space stations, but tentatively
                concluded that it was too early to identify exactly where operations
                such as those in low-Earth orbit might fit into the regulatory fee
                structure in the future. Accordingly, it found that the record was
                insufficient to propose to establish fee categories or a methodology
                for assessing fees to such categories. The Commission sought comment on
                those tentative conclusions, as well as whether and how to assess fees
                for RPO and OOS spacecraft that operate near the GSO arc.
                 49. Since that time, the Commission has continued to find that the
                record was insufficient to adopt a new regulatory fee category for in-
                space servicing operations, such as OOS and RPO. In the order adopting
                regulatory fees for FY 2022, the Commission determined that the record
                was insufficient to support adopting new regulatory fee categories for
                OOS and RPO due to the nascent nature of these systems and the need for
                more experience with the operations of such systems and the FTE time
                required to support them. For the same reasons, the Commission declined
                to adopt separate fee categories for OOS and RPO in the FY 2023
                regulatory fee proceeding, again finding that the record remained too
                incomplete and concluding that there was insufficient understanding of
                the nature and regulation of such spacecraft to consider concrete
                proposals for assessing regulatory fee categories for OOS and RPO space
                stations at that time. The Commission noted that it was still in the
                early stages of considering the regulatory environment for such
                services as a whole, and the definitions of which services would fit
                into OOS and RPO were yet to be adopted. Instead, the Commission stated
                it would continue to develop a record that would inform possible
                establishment of a fee category for OOS and RPO and an appropriate
                methodology for assessing fees for such a category.
                 50. In the NPRM, the Commission proposes that it should no longer
                delay adopting a regulatory fee category for OOS and RPO space
                stations, even if it has not yet adopted a separate regulatory
                environment for such services. In 2022, the Commission initiated a
                Notice of Inquiry, 87 FR 56365 (Sept. 14, 2022), regarding the
                regulatory needs related to in-space servicing, assembly, and
                manufacturing--or ``ISAM''--that could include such services as RPO and
                OOS. The Commission has since adopted a Notice of Proposed Rulemaking,
                89 FR 18875 (Mar. 15, 2024), seeking comment on a framework for
                licensing ISAM space stations. That proceeding is still in the early
                stages of considering the regulatory environment for such services.
                Nonetheless, the Space Bureau has considered applications for space
                stations performing RPO and OOS and issued licenses for such space
                stations under the existing regulatory framework of 47 CFR part 25, and
                such stations are already operational and subject to payment of
                regulatory fees. The Space Bureau anticipates that it will receive
                additional applications for such services in the near future, likely
                before the conclusion of any proceeding that may consider a separate
                licensing regime for such systems. Accordingly, there is a need to
                propose a method for assessing regulatory fees on spacecraft primarily
                performing RPO and OOS now, even while the consideration of the
                regulatory environment for such services is ongoing.
                 51. Although the record remains insufficient to propose a new
                category of regulatory fees for these services, the Commission
                proposes, on an interim basis, to include RPO and OOS within an
                existing category of regulatory fees. In this respect, the Commission
                tentatively concludes that the regulatory fee categories of Space
                Stations (Geostationary Orbit) and Space Stations (Non-geostationary
                Orbit)--Other do not reflect the amount of regulatory work required by
                these nascent RPO and OOS services. Those fee categories are reflective
                of the greater FTE burden associated with regulation of more numerous
                and more complex space stations that primarily provide ``always on''
                communication services, using spectrum and orbital resources on a
                protected basis, subject to processing rounds or ``first-come, first-
                served'' procedures, and requiring the use of a large number of
                associated earth stations. The Commission also tentatively concludes
                that the regulatory fee category of ``Space Stations (Non-geostationary
                Orbit)--Less complex'' is not the most appropriate fit, since space
                stations providing primarily RPO and OOS do not fall within the
                existing definition of ``less complex'' NGSO space stations, which is
                limited to space stations primarily providing EESS and/or AIS and the
                regulatory framework for RPO and OOS space stations is not sufficiently
                clear at this time. The Commission does not propose to use the existing
                NGSO ``less complex'' fee category for RPO or OOS space stations, since
                it tentatively concludes that the regulatory burden of RPO and OOS
                space stations is currently far less than that of ``less complex'' NGSO
                space stations. The Space Bureau has received relatively few
                applications for RPO or OOS space stations, and although it anticipates
                receiving more in the near future, the amount of FTE resources required
                at the present time to regulate these services is not comparable to the
                resources required for regulation of NGSO ``less complex'' space
                stations. It is possible that, in the future, the regulatory burden of
                RPO and OOS may significantly increase and justify revisiting this
                tentative conclusion, but at the present moment the regulatory burden
                of RPO and OOS space stations is more similar to that presented by
                small satellite space station licensees, which are also few in number
                and involve a relatively small number of space stations that have
                limited duration and scope of use and operate using shared spectrum
                resources.
                 52. Although the Commission previously declined to adopt an interim
                fee for RPO and OOS space stations, including one equivalent to the fee
                assessed for small satellites, it did so due, in part, to time
                constraints that would not allow for the adoption of a new fee and the
                desire for more experience before adopting a separate fee for RPO and
                OOS space stations. In the NPRM, the Commission is not proposing to
                adopt a new fee for RPO and OOS space stations, but rather, on an
                interim basis, to assess fees using the
                [[Page 20592]]
                existing Space Stations (Small Satellites) fee category. Given the
                immediate need to assess regulatory fees on RPO and OOS space stations
                now and in the near future, the Commission tentatively concludes that
                the purposes of 47 U.S.C. 159 would be best met by erring on the side
                of caution and assessing regulatory fees under the category of fees
                associated with the least-burdensome set of space station regulatees,
                rather than waiting for additional experience and in the interim
                potentially subjecting existing RPO and OOS space stations subject to
                regulatory fees for Space Stations (Geostationary Orbit) or Space
                Stations (Non-Geostationary Orbit)--Other, that may not reflect the
                amount of regulatory work required by these nascent services. As the
                Commission gains more experience with the regulation of RPO and OOS
                space stations, it will be in a better position to adopt a separate fee
                category for RPO and OOS space stations, if appropriate. The NPRM seeks
                comment on this proposal and tentative conclusions.
                 53. The Commission also proposes to assess RPO and OOS space
                stations using the small satellite fee category on an interim basis,
                regardless of the orbit utilized. Small satellites are limited to NGSO
                operations under 47 CFR part 25, and the Commission stresses that it is
                not proposing or suggesting that RPO or OOS space stations would meet
                the definition of a ``small satellite'' or ``small spacecraft'' under
                47 CFR part 25. Instead, solely for the purpose of assessing regulatory
                fees, the Commission proposes to include RPO or OOS space stations
                within the existing Space Stations (Small Satellite) regulatory fee
                category, rather than creating a new regulatory fee category for RPO
                and OOS space stations. The Commission tentatively concludes that the
                rational above for using the small satellite regulatory fee category to
                assess fees on RPO and OOS space stations applies regardless of whether
                the RPO or OOS space stations operate in GSO or NGSO. The Commission
                also proposes to assess the regulatory fee for RPO or OOS space
                stations on a ``per license/call sign'' basis as is the case for small
                satellites payors, rather than on the ``per system'' basis used for
                Space Stations (Non-geostationary Orbit). In addition, the Commission
                proposes to assess regulatory fees on OTV space stations in the same
                manner; that is, to assess regulatory fees for OTV space stations using
                the existing regulatory fee category of small satellite space stations
                on a per license/call sign basis. Like RPO and OOS space stations, OTVs
                are also few in number and involve a relatively small number of space
                stations that have limited duration and scope of use and operate using
                shared spectrum resources in a manner that reduces the amount of FTE
                resources needed for their licensing and regulation. The Commission has
                already licensed OTV space stations under its existing 47 CFR part 25
                regulatory framework, and it anticipates that additional applications
                for OTV will be filed in the near future. Accordingly, the same
                rationale applies to erring on the side of caution and assessing
                regulatory fees under the category of fees associated with the least-
                burdensome set of space station regulatees, at least until the
                Commission gains more experience in this matter. The NPRM seeks comment
                on these proposals and tentative conclusions. It also seeks comment on
                whether this proposed approach for assessing regulatory fees for RPO,
                OOS, and OTV could also be applied to all space stations that fall
                within the definition of ISAM.
                 54. The Commission finds that the proposal to assess regulatory
                fees for RPO, OOS, and OTV space stations using the existing fee
                category for small satellites would be an amendment as defined in 47
                U.S.C. 159(d). Such an amendment must be submitted to Congress at least
                90 days before it becomes effective pursuant to 47 U.S.C. 159A(b)(2).
                 55. Finally, the Commission proposes that RPO or OOS space stations
                that are attached to another space station as part of servicing or
                mission extension operations be assessed regulatory fees separate from,
                and in addition to, any regulatory fees assessed on the space station
                that is being serviced or that is having its mission extended. The
                Commission acknowledges that this tentative conclusion is the opposite
                of the Commission's prior tentative conclusion that RPO and OOS space
                stations joined to GSO space stations during servicing or mission
                extension operations should not be assessed separate regulatory fees,
                despite the RPO or OOS space stations being assigned their own call
                signs, which is the unit usually used to assess regulatory fees for
                space stations. This tentative conclusion was never adopted, and as
                such was only tentative in nature. Upon further consideration, the
                Commission tentatively concludes that the requirements and purpose of
                47 U.S.C. 159 would be better met by assessing regulatory fees on such
                attached RPO or OOS space stations.
                 56. The premise underlying the prior tentative conclusion was that
                the RPO or OOS space station is operating as part of an existing GSO
                space station, rather than as a separate independent space station, and
                therefore there is no independent operating space station for a
                separate fee assessment and that the regulatory fee burden for the RPO
                or OOS space station would be included in the fees collected from the
                GSO space station fee payors. Upon further consideration, the
                Commission tentatively concludes that this premise is not correct. As
                long as a RPO or OOS space station retains a separate authorization,
                with its own call sign, it is a separate space station for the
                Commission's regulatory purposes, so that there is a space station for
                a separate fee assessment independent of the space station being
                serviced or having its mission extended. Regulatory work is associated
                with the licensing and regulation of the RPO or OOS space station that
                is separate and independent from the regulatory work associated with
                the space station that is being serviced or having its mission
                extended. FTE work expended on reviewing license applications, issuing
                licenses, and exercising regulatory supervision of the RPO or OOS space
                stations is completely separate from the FTE work associated with the
                licensing and regulation of the space station being serviced or having
                its mission extended. In addition, the Commission observes that it
                would be difficult to administer regulatory fees for RPO or OOS space
                stations under the Commission's prior tentative conclusion, since the
                status of the RPO or OOS space station for regulatory fee purposes
                would depend on whether the RPO or OOS space station is attached to
                another space station on the date when regulatory fees are assessed, or
                whether it may be operating unattached, for example, between servicing
                missions, which could lead to uncertainty as to whether regulatory fees
                are due or not, as well as potential gaming of regulatory fees through
                the timing of missions. Pursuant to 47 U.S.C. 159, the Commission is
                required to assess regulatory fees to recover all of its FTE work based
                on how FTE time is used. The Commission tentatively concludes that it
                would not be able to meet that requirement if it was to consider the
                RPO or OOS to be part of the serviced space station, and not subject to
                separate regulatory fees. The Commission seeks comment on its proposal
                and the reasoning in support of it.
                6. Assessment of Fees on Authorized, But Not Operational, Space
                Stations
                 57. The Commission proposes to assess regulatory fees on all
                authorized
                [[Page 20593]]
                space and earth stations, not only on stations that are
                ``operational.'' Currently, regulatory fees for space stations are
                payable only when the space stations are certified by their operator to
                be operational. An earth station payor is required to pay a fee once it
                has certified that the earth station's construction is complete, but in
                the rare instances in which a license limits an earth station's
                operational authority to a particular satellite system, the fee is not
                due until the first satellite of the related system becomes
                ``operational'' within the meaning of the Commission's rules. A space
                station is authorized, in contrast, after an application or petition
                has been reviewed and granted by the Commission and the grant is
                effective. Because significant FTE resources are involved with the
                licensing of space and earth stations, the Commission tentatively
                concludes that the objectives of 47 U.S.C. 159 would be better met by
                assessing regulatory fees once a space or earth station is licensed,
                rather than when a space station becomes operational.
                 58. The origin for assessing regulatory fees on space stations when
                they become operational, rather than when licensed, was the statutory
                text of 47 U.S.C. 159 from 1993. The Omnibus Budget Reconciliation Act
                of 1993 that created 47 U.S.C. 159 and proposed regulatory fees in 47
                U.S.C. 159(g), which identified two fee categories and amounts for
                space stations: (1) ``Space Station (per operational station in
                geosynchronous orbit) (47 CFR part 25)'' and (2) ``Space Station (per
                system in low-earth orbit) (47 CFR part 25)''. The Commission adopted
                the requirement that GSO space stations be operational before
                regulatory fees are assessed as part of 1994 regulatory fee proceeding,
                basing that decision on the statutory language. In that same
                proceeding, the Commission also applied to NGSO space stations the
                requirement that space stations be operational before regulatory fees
                are payable, even though the text of 47 U.S.C. 159(g) did not include
                the word ``operational'' for systems in low-earth orbit, as it did for
                GSO space stations. The Commission has kept the ``operational''
                requirement for assessing regulatory fees on space stations through
                subsequent annual regulatory fee assessment proceedings without comment
                or reevaluation.
                 59. The Commission tentatively concludes that there is no statutory
                bar to assessing regulatory fees on authorized, but not yet
                operational, space and earth stations. Pursuant to 47 U.S.C. 159, the
                Commission is explicitly given authority to adjust its regulatory fees
                by rule if it determines that the schedule of fees requires amendment,
                and such adjustment by rule is what is being proposed in the NPRM. In
                addition, Congress deleted 47 U.S.C. 159(g), which was the textual
                basis for the operational requirement for assessing regulatory fees on
                space stations, in the 2018 RAY BAUM's Act. Accordingly, the original
                textual language of 47 U.S.C. 159(g) appears no longer relevant to the
                Commission's amendments of regulatory fee schedules. The NPRM seeks
                comment on this tentative conclusion and the reasons underlying it.
                 60. In the NPRM, the Commission tentatively concludes that now is
                an appropriate time to reevaluate the current policy that a space
                station must be operational before regulatory fees can be assessed. The
                recent creation of Space Bureau provides an opportune time to revisit
                past conclusions about the regulatory burdens associated with space and
                earth station fee payors and how those fees should be assessed. The
                increased burdens of regulating space stations as a result of the
                changes in the satellite industry and the creation of the Space Bureau
                will increase the share of regulatory fees to be assessed on space and
                earth station regulatees, compared to the number of FTEs regulating
                space stations in the International Bureau, so the Commission should
                look to have as broad a base as possible for its regulatory fees in a
                manner that accounts for all regulatees that benefit from Space Bureau
                oversight as a matter of making its regulatory fees more fair.
                 61. The Commission observes that a licensee or grantee already
                benefits from the substantial FTE resources used to review and grant
                the application or petition, as well as from the FTE resources used to
                protect the benefits conferred by the grant of a license or of U.S.
                market access, such as use of spectrum and orbital resources and
                protection from interference, which convey upon issuance of the license
                or grant. Moreover, given the bespoke nature of many satellite systems,
                Space Bureau staff expertise is utilized by the industry before, during
                and after an application (including modifications thereof) or petitions
                for rulemaking are filed. In addition, as observed elsewhere in the
                NPRM, NGSO space stations are taking an increased share of FTE burdens
                relative to GSO space stations and are being assessed higher regulatory
                fees, so there is also increased importance to make sure that all NGSO
                beneficiaries of those FTE burdens are assessed fees. For example, if
                five NGSO FSS systems are licensed through a single processing round,
                FTE licensing work is necessitated by all five systems, but under the
                current policy only the operational systems would be required to pay
                regulatory fees, and the entire regulatory burden for that category of
                space stations would be paid only by operational systems. Systems that
                become operational later, or not at all, would not be assessed
                regulatory fees associated with that FTE work for potentially many
                years, or perhaps never. As a result, systems that become operational
                earlier than other licensed systems would bear the entire fee burden of
                regulatory work done on behalf of all regulated systems. The NPRM seeks
                comment on these observations.
                 62. The Commission proposes that the intent of Congress in 47
                U.S.C. 159 would be better fulfilled by recovering the costs of
                licensing and regulatory oversight based on authorized space stations,
                rather than operational space stations. Congress has directed the FCC
                to recover its annual S&E appropriation through regulatory fees, and
                the S&E appropriation includes funding for FTE time spent reviewing and
                granting applications, which is accrued regardless of when a space
                station becomes operational. In most cases, the amount of FTE spent on
                reviewing applications corresponds to the number of space stations
                requested to be authorized, rather than the number that become
                operational, since Commission staff must spend resources assessing the
                space station system as proposed in the application, regardless of
                whether all the space stations actually become operational. In
                addition, once a space station is authorized, it is subject to
                regulatory oversight by the Space Bureau and is entitled to all the
                benefits and privileges that come with an FCC license or market access
                grant. The NPRM seeks comment on this proposal.
                 63. The Commission also proposes that assessing regulatory fees
                based on authorized space stations, rather than operational space
                stations, should not present challenges to administer. No additional
                information collection would be needed to determine whether a space
                station is authorized (as opposed to operational), since the FCC's
                license or grant of market access displays the authorization
                particulars, including the date of grant and the number of space
                stations authorized, and the grants and the information contained
                within the grants are readily available to the Commission and the
                public. The Commission proposes to continue its practice of publishing
                a list of the space stations and systems that would be subject to
                regulatory fees as U.S. licensed space stations or non-U.S.
                [[Page 20594]]
                licensed space station that have been granted U.S. market access. As is
                the case now, the Commission proposes that any party identifying errors
                will be able to advise Commission staff of the error and seek
                correction. The Commission also proposes that NGSO licensees may seek
                to modify their licenses under existing 47 CFR part 25 requirements to
                have the number of authorized space stations modified to reflect the
                number of actual operational space stations if not as many space
                stations become operational as were applied for, or the number of
                authorized space stations diminishes due to the retirement of space
                stations at the end of their missions. The Commission acknowledges that
                permitting payors to reduce the number of authorized space stations
                after an application is granted could be inconsistent with the proposal
                that regulatory fees should be based on the number of space station
                licensed, rather than the number of operational space stations, but the
                Commission tentatively concludes that it is easier to administer its
                fees if they are based on the number of space stations authorized in
                the current license, rather than having to look back at previous
                iterations of license grants in order to fix the fee at the highest
                number of space stations licensed. Furthermore, the Commission does not
                anticipate that licensees or grantees will seek to reduce the number of
                authorized satellites significantly after authorization to avoid
                regulatory fees; rather, it anticipates that such reductions will be
                marginal and be due to business or operational considerations, rather
                than due to regulatory fee considerations. The Commission seeks comment
                on these proposals. It also seeks comment on whether, if the proposal
                to assess regulatory fees based on authorized, rather than operational,
                space stations is adopted, the Commission should assess fees on this
                basis in the current fiscal year, or whether it would be more
                appropriate to assess fees on this basis beginning in FY 2025.
                 64. The Commission recognizes that assessing regulatory fees before
                a GSO space station, or a system of NGSO space stations, is operational
                could lead to collateral effects that are outside the FTE-focused
                methodology required under 47 U.S.C. 159. For example, assessing
                regulatory fees on authorized, but non-operational, space stations
                could provide an incentive for applicants to request the Space Bureau
                to defer action on applications until after the period has passed for
                assessing which payors owe regulatory fees for the fiscal year, so as
                to defer the assessment of regulatory fees until the subsequent fiscal
                year. Alternatively, it could provide an incentive for space station
                operators to seek licensing outside the United States, and to apply for
                U.S. market access only once the system has become operational, thereby
                deferring the assessment of regulatory fees in a manner not available
                to U.S.-licensed space station operators. It could also increase the
                costs to the operator at the initial funding phases of a space station
                or system of space stations. The Commission seeks comment on these, or
                any other, potential collateral effects, and whether they weigh against
                assessing regulatory fees on authorized, but not yet operational, space
                stations. In addition, if the Commission does not adopt the proposal to
                begin to assess regulatory fees when a space station, or system of
                space stations, is authorized, could the benefits for the proposal
                still be realized in part by assessing regulatory fees on the number of
                authorized space stations in the system, once the system has been
                notified as operational, as defined under 47 CFR 25.121(d)(2)?
                 65. The Commission finds that the proposal to assess regulatory
                fees on authorized, rather than operational, space and earth stations
                would be an amendment as defined in 47 U.S.C. 159. Such an amendment
                must be submitted to Congress at least 90 days before it becomes
                effective pursuant to 47 U.S.C. 159A(b)(2).
                 66. Summarizing the proposed changes to the existing regulatory fee
                methodology for space stations, the Commission proposes to modify the
                fee categories for space stations contained in 47 CFR 1.1156 to read as
                follows:
                ------------------------------------------------------------------------
                 Fee category Fee amount
                ------------------------------------------------------------------------
                Space Stations (per authorized station in geostationary [TBD]
                 orbit) (47 CFR part 25)................................
                Space Stations (per authorized system in non- [TBD]
                 geostationary orbit) (47 CFR part 25) (Other--Large
                 Constellations)........................................
                Space Stations (per authorized system in non- [TBD]
                 geostationary orbit) (47 CFR part 25) (Other--Small
                 Constellations)........................................
                Space Stations (per authorized system in non- [TBD]
                 geostationary orbit) (47 CFR part 25) (Less Complex)...
                Space Stations (per license/call sign) (Small Satellite) [TBD]
                ------------------------------------------------------------------------
                C. Earth Station Fee Proposals
                 67. The Commission proposes to increase the amount of regulatory
                fees assessed on earth stations in order to reflect more accurately the
                amount of FTE resources dedicated to their regulatory oversight.
                Currently, there is a single regulatory fee category for earth
                stations--Transmit/Receive & Transmit only (per authorization or
                registration). For FY 2023, the fee amount for this category per
                authorization or registration was $575. For the reasons set forth in
                the NPRM, the methodology used to assess regulatory fees for earth
                station payors may underestimate the FTE burdens associated with
                regulatory oversight of this category of fee payors, and the Commission
                seeks comment on proposals to adjust its regulatory fees to more
                accurately recover the amount of FTE resources devoted to licensing and
                regulation of earth stations.
                 68. The unit for assessing regulatory fees for earth stations--per
                authorization or registration--is not uniform. In some cases, an
                authorization can be for a single earth station, such as a feeder link
                station in the mobile-satellite service. In other cases, a single
                authorization could be for several thousand earth stations under what
                is often called a ``blanket license.'' When first established in 1994,
                the fee category for earth stations had four sub-categories with
                different fee amounts. These sub-categories were: (1) VSAT & Equivalent
                C-band antennas (per 100 antennas)--$6; (2) Mobile Satellite Earth
                Stations (per 100 antennas)--$6; (3) Less than 9 meters (per 100
                antennas)--$6; and (4) 9 Meters or More--Transmit/Receive and Transmit
                Only (per meter)--$85; Receive Only (per meter)--$55. In 1995, the
                Commission deleted receive-only earth stations as a service subject to
                regulatory fee requirements and determined that assessing fees on a per
                authorization or registration basis was more equitable method than on a
                per meter or per 100 earth station basis. The Commission set the earth
                station regulatory fee per authorization or registration at $330 for
                all three remaining sub-categories (i.e., VSAT, Mobile-Satellite Earth
                Stations, Fixed Earth Stations--Transmit/Receive & Transmit Only). 47
                CFR 25.1156, however, lists only a single category and fee for earth
                station payors: Earth Stations: Transmit/Receive & Transmit only (per
                authorization or registration).
                [[Page 20595]]
                 69. The Commission has not assessed earth station regulatory fees
                as a percentage of overall bureau regulatory burdens. Rather, the
                assessment of regulatory fees for earth stations has been based on the
                initial per unit fee for earth stations--Transmit/Receive & Transmit
                only (per authorization or registration) that was established by the
                Commission in 1995. This initial fee has been adjusted on a year-to-
                year basis, but usually only in terms of a percentage change in the fee
                to reflect the changes in the amount of appropriated S&E each year and
                the number of anticipated units of payors. Since 1995, the Commission
                has periodically discussed earth station regulatory fees or considered
                adjusting earth station regulatory fees for factors beyond a change in
                the annual S&E appropriation or the number of units of earth station
                fee payors. In 2014, the Commission increased the earth station
                regulatory fee per unit by 7.5%, from $275 in FY 2013 to $295 for FY
                2014, in order to reflect more appropriately the number of FTEs devoted
                to the regulation and oversight of the earth stations in response to
                concerns raised by commenters that space stations paid an unreasonably
                high portion of the regulatory fees for the regulation of the satellite
                industry. The following year, in 2015, the Commission sought comment on
                whether to raise the earth station regulatory fees again but declined
                to do so finding that the issue required further analysis. In
                particular, due to comments suggesting that the Commission adopt
                different regulatory fees for different types of earth stations and an
                ongoing proceeding that held the possibility of affecting the
                distribution of FTE work, the Commission deferred the issue for the
                next year's proceeding. The Commission ceased consideration of
                different regulatory fees for different types of earth stations in
                2016, however, when the commenter chiefly advocating for such
                consideration ceased to back its earlier proposal and no other entity
                commented on the record in favor of the proposal to assess different
                levels of regulatory fees on different types of earth station
                licensees. In 2020, commenters in the annual regulatory fee assessment
                proceeding proposed that the Commission review the apportionment of
                regulatory fees between earth and space station payors and implement
                different earth station subcategories for regulatory fee purposes. The
                Commission declined to do so, finding that there was insufficient
                evidence in the record at that time to increase apportionment of fees
                paid by earth station licensees or on which to base the creation of
                subcategories of earth station fees.
                 70. The Commission's focused examination of space and earth station
                fees as a result of the creation of the Space Bureau provides an
                opportunity to reconsider whether its regulatory fees adequately
                reflect the amount of FTE resources devoted to licensing and regulation
                of earth stations. The Commission tentatively conclude that they do
                not, and that a change in methodology in assessing regulatory fees for
                earth stations is required. Specifically, for the reason set forth in
                the NPRM, the Commission proposes to adopt an apportionment of the
                total regulatory fees allocated to the Space Bureau between space and
                earth station payors on a percentage basis, similar to the manner that
                space station fees are apportioned between GSO and NGSO space stations,
                and proposes that the apportionment be 20 percent for earth stations
                and 80 percent for space stations. The NPRM seeks comment on this
                proposal and apportionment.
                 71. For FY 2023, earth station licensees were assessed a total of
                $1,667,500 in regulatory fees, which amounted to 7.69% of the
                $21,656,110 in regulatory fees assessed for all space and earth station
                payors. Several factors lead to the Commission's tentative conclusion
                that this percentage underestimates the amount of FTE resources
                dedicated to earth station licensing and regulation. First, unlike the
                case for apportionment of space station fees between GSO and NGSO space
                stations, or among various subcategories of NGSO space stations, it may
                be feasible to attribute Space Bureau FTE resources that are dedicated
                exclusively, or nearly exclusively, to earth station licensing and
                regulation. Within the Space Bureau is the Earth Station Licensing
                Division (ESLD), which lists eleven staff members that work almost
                exclusively on earth station licensing and regulation and that are not
                routinely involved in matters of space station licensing or regulation.
                If each staff member were to account for an FTE, these eleven staff
                members would account for approximately 20% of the 54 FTEs that could
                be categorized as direct FTEs for the Space Bureau for FY 2024, minus a
                small number of FTEs that may be categorized as indirect FTEs as
                discussed elsewhere in the NPRM. The Commission tentatively concludes
                that apportioning regulatory fee percentages between earth and space
                station payors based on the percentage of direct FTEs involved the
                licensing and regulation of each category, where feasible to do so, is
                a reasonable way to fulfill Congress' mandate in 47 U.S.C. 159 that the
                Commission's regulatory fees must reflect the full-time equivalent
                number of employees within the bureaus and offices of the Commission,
                adjusted to take into account factors that are reasonably related to
                the benefits provided to the payor of the fee by the Commission's
                activities. The Commission seeks comment on whether using FTEs in the
                ESLD to determine the proportion of earth station fees relative to
                space station fees is reasonable and reflective of Congressional
                intent. Are there other factors that are reasonably related to the FTE
                resources provided to earth station licensees that are not reflected in
                the Commission's proposal? Are there alternatives to using the
                percentage of direct FTEs involved in earth station licensing and
                regulation that should be considered?
                 72. The Commission recognizes that the proposal to apportion 20% of
                all Space Bureau regulatory fees to earth station licensees beginning
                in FY 2024 will result in a substantial increase in the per unit
                regulatory fee paid by earth station licensees, both because the
                percentage share of Space Bureau regulatory fees is likely to increase
                as a whole due to the increased number of direct FTEs in the Space
                Bureau compared to the International Bureau, and because the percentage
                share of earth station fees of Space Bureau fees would increase from
                around from around 8% to 20% under the Commission's proposal.
                Nonetheless, the Commission tentatively concludes that the increase in
                earth station regulatory fees is consistent with the mandate given by
                Congress in 47 U.S.C. 159 for the Commission to recover its costs of
                regulation through fees that reflect the full-time equivalent number of
                employees within the Commission that provide the regulatory benefits to
                the payors. The NPRM seeks comment on this tentative conclusion and
                observation.
                 73. In light of the tentative conclusion that earth station
                licensees should be apportioned 20% of all fees allocated to Space
                Bureau fee payors, the Commission seeks to revisit the question of
                whether to create subcategories of earth station regulatory fee payors
                to better differentiate the amount of regulatory burdens associated
                with different types of earth station licenses. For example, should
                Very Small Aperture Terminal (VSAT), Mobile-Satellite Earth Stations,
                and Fixed Earth Stations--Transmit/Receive & Transmit Only be
                reinstated as distinct fee categories, each with a separate fee
                assessment? The Commission also seeks to develop a
                [[Page 20596]]
                record as to whether there are types of earth station licenses that
                require more FTE resources to license and regulate, and that account
                for a higher share of FTE burdens than other categories of earth
                station licensees, for which a higher regulatory fee should be
                assessed. Likewise, are there categories of earth station licensees
                that require less FTE resources to license and regulate and therefore
                should be assessed a lower regulatory fee? For example, in the past
                commenters have suggested that blanket-licensed earth station licensees
                involving multiple antennas under a single authorization should pay
                higher fees than other earth station licensees because blanket-licensed
                earth stations require more regulatory oversight. The NPRM asks
                commenters to provide evidentiary support for their propositions and to
                provide specific proposals for what these categories should be and how
                to allocate fees among any categories. Furthermore, comments should
                address the administrability of any proposed categories and whether the
                Space Bureau would be able to assign costs of specific regulatory
                activities to any proposed categories of earth station regulatory fees.
                 74. The Commission finds that the creation of any new fee
                categories for earth stations would be an amendment as defined in 47
                U.S.C. 159. Such an amendment must be submitted to Congress at least 90
                days before it becomes effective pursuant to 47 U.S.C. 159A(b)(2).
                 75. If the proposals made in the NPRM are not adopted, the
                Commission seeks comment on whether it should, at a minimum, increase
                the amount of the per unit fee for the existing fee category of ``Earth
                Station--Transmit/Receive & Transmit only (per authorization or
                registration)'' in order to reflect the increase of the Space Bureau's
                share of overall Commission regulatory fees as compared to the
                International Bureau's share in FY 2023. If so, how should this
                increase be calculated and what should be the percentage increase over
                the FY 2023 fee?
                D. Alternative Methodology for Assessing Space Station Regulatory Fees
                 76. The proposals made elsewhere in the NPRM are amendments or
                adjustments to the existing methodology of assessing regulatory fees
                for space stations. This existing methodology was founded on the
                original regulatory fees proposed by Congress in 1994, which provided
                for earth station regulatory fees and separate categories of space
                station fees depending on the orbit used by the space station(s):
                geostationary or non-geostationary. Since then, the Commission has
                created subcategories for NGSO space stations and has continuously
                tried to adjust the allocation of FTE burdens among GSO space stations
                and the various subcategories of NGSO space stations. The Commission
                now seeks comment on an alternative methodology for assessing space
                station regulatory fees that eliminates the distinction between GSO,
                NGSO, and all the subcategories of NGSO, while preserving a separate
                fee category for small satellites. For the reasons discussed in the
                NPRM, the Commission seeks comment on whether this alternative
                methodology would be more administrable, fair, and sustainable than the
                existing methodology, even if all the proposals made elsewhere in the
                NPRM are adopted.
                 77. The initial stages of the alternative methodology are the same
                as under the existing methodology. The Commission would first determine
                the Space Bureau's share of the total FCC annual S&E appropriation for
                the given fiscal year using the existing methodology used by the
                Commission. After the Space Bureau's share is determined, the
                Commission proposes that the share be allocated between earth station
                and space station fee payors proportional to the Space Bureau FTE
                resources that are involved in the licensing and regulation of each
                segment. As stated elsewhere in the NPRM, the Commission tentatively
                concludes that it is feasible to attribute Space Bureau FTE resources
                that are dedicated exclusively, or nearly exclusively, to earth station
                licensing and regulation. The Commission anticipates that the FTE
                resources attributed to earth stations will be 20 percent of the total
                Space Bureau share, resulting in 80 percent of regulatory fees to be
                attributed to space station regulatory fees. Earth station fees would
                be determined by dividing the total share attributable to earth station
                licensing and regulation by the number of units for the fiscal year,
                which were 2900 in FY 2023.
                 78. The Commission's alternative methodology also would preserve a
                separate fee category for Space Stations (per license/call sign) (Small
                Satellite), with the inclusion of RPO, OOS, OTV, and potentially other
                ISAM space stations in this category on an interim basis, as was
                proposed elsewhere in the NPRM. It would also retain the proposal to
                set this regulatory fee at the level set for FY 2023, with only an
                adjustment each year to reflect the percentage change in the FCC
                appropriation from the previous fiscal year. This fixed regulatory fee
                for Space Stations (Small Satellite) would be multiplied by the number
                of small satellite licenses/call signs required to pay regulatory fees
                for the fiscal year, and this total amount would be subtracted from the
                amount of space station regulatory fees to be assessed on all remaining
                space station payors. Fees would be assessed on authorized space
                stations, not just operational space stations, as proposed in the NPRM.
                This treatment of small satellite regulatory fees would be consistent
                with the Commission's existing methodology for assessing space station
                regulatory fees, taking into account the proposals made in the NPRM.
                 79. The main change from the existing methodology is a proposal to
                establish a common initial unit of regulatory fee payment for all space
                stations, regardless of which orbit they are designed to operate in,
                and to eliminate separate fee categories for Space Stations
                (Geostationary Orbit), Space Stations (Non-Geostationary Orbit)--Less
                complex, and Space Stations (Non-Geostationary Orbit)--Other. The
                alternative methodology would have a single space station fee category
                for ``Space Stations (Per Call Sign in Geostationary Orbit or Per
                System in Non-Geostationary Orbit).'' The category would be tiered,
                with a single GSO space station or a NGSO system with up to 100
                authorized space stations constituting this initial tier and being
                counted as one unit for assessment of space station regulatory fees.
                Additional tiers would be created to account for NGSO systems with more
                than 100 authorized space stations, for example 500 or 1,000 space
                stations per NGSO system per additional tier. Each tier would be
                counted as an additional unit for assessment of space station
                regulatory fees. The total number of units (initial and additional
                units) would be added together and the total space station allocation
                of the Space Bureau share would be evenly divided among the total
                number of units, resulting in a per unit regulatory fee for the fiscal
                year.
                 80. If the unit tiers are defined per 500 additional authorized
                space stations, the initial unit range will be 1-100 authorized space
                stations, the first additional unit will be assessed to systems with
                101-500 authorized space stations, and an additional unit will then be
                assessed for each additional block of 500 authorized space stations.
                Similarly, if the additional unit tiers are defined per 1,000
                additional authorized space stations, the initial unit range will be 1-
                100 authorized space stations, the first additional unit will be
                assessed to systems with 101-1,000 authorized
                [[Page 20597]]
                space stations, and an additional unit will then be assessed for
                additional block of 1,000 authorized space stations. For example, a
                single GSO space station or a NGSO system of 100 authorized space
                stations or fewer would be assessed one unit's share of space station
                regulatory fees. If that NGSO system were to have 500 authorized space
                stations, it would be assessed an additional unit's share of regulatory
                fees, regardless of whether the additional tiers are based on 500 or
                1,000 additional space stations per NGSO system. If that NGSO system
                were to have 1,000 authorized space stations, it would either be
                assessed one additional unit's share (if the additional tiers are based
                per 1,000 authorized space stations) or two additional units' share (if
                the additional tiers are based per 500 authorized space stations).
                Accordingly, GSO payors and NGSO systems of 100 authorized space
                stations or fewer would be assessed the lowest regulatory fees, while
                payors with multiple authorized GSO space stations or with NGSO systems
                with more than 100 authorized space stations would be assessed higher
                regulatory fees, with the highest regulatory fees assessed to payors
                with a large number of GSO space stations and to payors with NGSO
                systems consisting of thousands of authorized space stations.
                 81. The Commission seeks comment on whether this alternative
                methodology would be more administrable, fair, and sustainable than the
                existing methodology. First, it could be more administrable because it
                does not require the Space Bureau to make the challenging determination
                of how FTE resources are allocated among space station payors. The
                Commission has previously recognized the considerable challenge of
                apportioning regulatory fees among space stations fee categories. Under
                the alternative methodology, tiered units are used as a proxy for the
                amount of FTE resources that are attributable to the system without
                having to repeatedly make challenging determinations of the amount of
                FTE resources attributable to particular categories or subcategories of
                space station regulatory fee payors. Furthermore, unless the number of
                authorized space stations substantially decreases over a year, the
                amount of regulatory fee assessed to a system on a per unit basis is
                unlikely to increase and is likely to remain stable (or possibly
                decrease) year to year. The alternative methodology does not utilize
                any characteristics of a space station system other than the number of
                authorized space stations in the system and is not dependent on
                potentially difficult evaluations of the complexity of a system under
                the Commission's licensing and regulatory framework. It would not
                require the Commission to collect more information from operators.
                Thus, the Commission anticipates that the alternative methodology can
                remain stable longer than the existing methodology for assessing space
                station regulatory fees. The NPRM seeks comment on these issues.
                 82. The Commission seeks comment on whether the alternative
                methodology is more fair than the existing methodology, because it
                better corresponds FTE resources spent on licensing and regulating
                space stations with the types of space station systems that benefit
                from the FTE resources, thereby decreasing the per unit regulatory fees
                for space station payors that benefit less from FTE resources. Under
                the alternative methodology, higher aggregate fees will be assessed to
                systems with large numbers of authorized space stations, GSO or NGSO,
                but the Commission expects those higher fees will be borne by payors
                that benefit from more FTE resources in support of licensing and
                regulating their systems. The alternative methodology also increases
                the number of units over which space station regulatory fees are
                spread, thereby decreasing the per unit regulatory fees for all space
                station payors as additional units are added, regardless of their
                orbital configuration. The tiered system also avoids the situation
                where systems with a very large number of authorized space stations
                could effectively end up paying all, or nearly all, space station
                regulatory fees, and where the fee per unit for a single GSO space
                station or a NGSO system of up to 100 authorized space stations would
                be diluted to an amount that may not adequately reflect the amount of
                FTE resources allocated to such fee payors.
                 83. In addition, under the existing methodology, regulatory fees
                for a particular category of fee payors go down per payor as more space
                stations or systems become operational in that category. Although such
                a decrease is beneficial for payors in that category, it may not
                reflect the increased amount of FTE resources required for that
                category of fee payors because of the additional resources needed for
                authorizing and regulating an increasing number of space stations or
                systems. This can lead to a discrepancy in that a category with rapidly
                increasing number of space stations or systems becoming operational is
                assessed lower regulatory fees than a category where the number of
                payors remains steady or even declines. This discrepancy continues
                until the Commission makes the challenging determination to alter the
                allocation of regulatory fees among the fee categories, which could
                take years to implement. For example, if additional NGSO systems become
                operational under the existing methodology, the regulatory fee per
                system for that particular subcategory of NGSO system would decrease
                because of the broader base over which the fees for that category would
                be spread, but it would not decrease the fees assessed on GSO space
                station payors or on NGSO space station payors in other NGSO
                subcategories--unless the Commission reallocates the percentage of
                space station regulatory fees among the GSO and NGSO categories. Under
                the alternative methodology this discrepancy is eliminated, because the
                addition of units of authorized space stations will automatically
                decrease the per unit regulatory fee for all space station regulatory
                fee payors, because the denominator used to divide the overall space
                station regulatory fee amount becomes larger. For example, the per unit
                regulatory fee for GSO space stations will decrease if the number of
                units assessed to NGSO space station systems increases, even if the
                number of units assessed to GSO space stations remains the same. Under
                this example, the per unit regulatory fee for all NGSO space stations
                would decrease as well. Furthermore, the alternative system avoids
                assessing the same regulatory fee on systems with a small number of
                authorized space stations as the fee assessed on systems with a large
                number of authorized space stations, as is the case under the existing
                NGSO space stations ``other'' subcategory. The NPRM seeks comment on
                these issues.
                 84. Finally, the Commission seeks comment on whether the
                alternative methodology is more sustainable than the existing
                methodology. The Commission has reason to expect that the number of
                authorized space stations will increase in the future, rather than
                decrease, which will result in an even broader base on which to assess
                space station regulatory fees and which will lower per unit fees for
                all space station payors, regardless of the orbit in which the space
                station operates or the services it provides. Because fees are spread
                across all space station payors, it avoids the situation where the loss
                of a single payor in an existing fee category could result in
                significant increases to the regulatory fees paid by the remaining
                payors in that category, absent Commission action to reexamine fee
                [[Page 20598]]
                allocations. The NPRM seeks comment on these issues.
                 85. The Commission observes that this alternative methodology
                relies exclusively on the number of authorized space stations to assess
                space station regulatory fees, rather than the more nuanced approach of
                the existing methodology of assessing the complexity of a system (and
                thus the amount of FTE resources required to regulate the system) based
                on a number of factors. The Commission also acknowledges that it has
                previously found that the number of space stations in a system is not
                the key driver of the amount of FTE time devoted to regulatory
                oversight of such systems. For example, an NGSO system consisting of a
                single space station that is designed to operate in a novel manner,
                subject to a processing round, and in a way that requires extensive
                coordination of spectrum and orbital resources may require
                significantly more regulatory oversight than a NGSO system of hundreds
                of space stations having non-exclusive use of spectrum and operating
                under well-established parameters. But is it reasonable to assume that
                NGSO systems with hundreds or thousands of authorized space stations
                require more FTE resources, on average and ignoring outliers, than NGSO
                systems with 100 authorized space stations or fewer, since as the
                number of space stations in a system increases, the complexity of
                spectrum sharing, frequency usage, and orbital debris mitigation plans
                also increases, generally speaking? While the number of space stations
                in a system may not be the key driver of the amount of FTE devoted to
                regulatory oversight of such systems, the Commission expects that it
                may be a driver, and one that is easier to administer than the more
                nuanced approach of the existing methodology or the use of other
                possible proxies for complexity, such as spectrum usage, services
                provided, or on-orbit mass. In order to gain the potential advantages
                of the alternative methodology, the number of space stations authorized
                may be the more administrable metric to serve as a proxy for the amount
                of FTE resources devoted to a system in order to accomplish the
                objectives 47 U.S.C. 159, rather than to continue the challenging task
                of determining which categories or aspects of NGSO systems are more or
                less complex to regulate on a recurring basis, particularly as new
                technologies, services, and orbital operations rapidly develop. The
                NPRM seeks comment on these issues.
                 86. Although the regulatory fees that would be assessed under the
                alternative methodology for most space station fee payors may be
                roughly the same or potentially lower than those that would be assessed
                using the existing methodology, even with the changes proposed in the
                NPRM, the fees assessed for some space station payors could be
                substantially higher under the alternative methodology. For example,
                NGSO systems with more than 500 authorized space stations that are
                categorized as ``less complex'' under the existing methodology could
                pay more under the alternative methodology. For NGSO systems that are
                categorized as ``less complex'' under the Commission's existing
                methodology, it may be possible to reflect that categorization by
                allowing a greater number of space stations to be included in the first
                or second tier for those systems. For example, an NGSO system used
                primarily for EESS and/or AIS communicating with 20 or fewer U.S.-
                licensed earth stations with up to 500 authorized space stations could
                be assessed only the initial unit of fees, even though it exceeds the
                proposed limit of up to 100 authorized space stations for the initial
                unit. The NPRM seeks comment on these issues.
                 87. Furthermore, if NGSO systems have a significantly larger number
                of authorized space stations than is the case today, it is possible
                that tiers of units based on 500 or 1,000 space stations could result
                in such NGSO systems being assessed a very large percentage share of
                all space station regulatory fees. In this case, the concern is similar
                to using a ``per space station'' basis as a proxy for the complexity of
                a space station system that was discussed elsewhere in the NPRM. As
                discussed, the NPRM seeks comment on whether a ``cap'' or ``ceiling''
                on the number of authorized space stations on which regulatory fees are
                assessed could alleviate this concern.
                 88. The use of tiers also presents the situation where a system
                with only a handful of authorized space stations over the cut off
                number of space stations in a tier would be assessed fees under the
                next higher tier. For example, under a tiered system where an
                additional unit of fees is assessed per 500 additional authorized space
                stations, an NGSO system with 501 authorized space stations would be
                assessed fees for three units (the initial tier of up to 100 authorized
                space stations, the second tier of up to 500 authorized space stations,
                and the third tier of 501-1,000 authorized space stations), even though
                it crossed the second tier threshold by a single authorized space
                station. While the payor in such a case could seek authorization for
                one less space station, or modify an existing space station license to
                remove an authorized space station from its license, this may not make
                sense from a systems engineering perspective, particularly if the
                ``spill over'' is 50 or 100 additional authorized space stations. A
                potential remedy for this situation is to allow partial units for
                assessing regulatory fees. For example, if the additional authorized
                space stations per unit is set at 500, and an NGSO system has 508
                authorized space stations, it could be assessed 1.016 additional units
                (508/500) instead of rounding up and being assessed two additional
                units. If the same NGSO system had 580 authorized space stations, it
                could be assessed 1.16 additional units (580/500) instead of two
                additional units. This fractional approach could result in more
                granular assessments of regulatory fees than a tiered system using cut
                offs. The NPRM seeks comment on these issues, particularly on the
                feasibility of implementing such an approach and whether it requires
                too much precision in assessing the number of authorized space stations
                in a system.
                 89. The Commission seeks comment on all aspects of this alternative
                methodology for assessing space station regulatory fees. Would it be
                more administrable, fair, and sustainable than the existing
                methodology? Is it reasonable to use the number of authorized space
                stations in a system to reflect the amount of FTE resources devoted to
                a system, as proposed in the alternative methodology? Is the regulatory
                burden of one GSO space station approximate to the regulatory burden of
                an NGSO system of up to 100 authorized space stations? If tiers of
                units are utilized, what should the number of additional authorized
                space stations per tier be set at? Would 500 or 1,000 additional
                authorized space stations be a reasonable number? Should there be a cap
                on the number of space stations on which tiers of units are assessed,
                in order to prevent NGSO systems with tens of thousands of authorized
                space stations from potentially being assessed a fee that is
                disproportionate to the amount of FTE resources devoted to licensing
                and regulating such systems? Should partial units be utilized instead
                of cut offs for tiers, as discussed in the previous paragraph? Under
                the alternative methodology, should small satellite fees be fixed, as
                proposed for changes to the existing methodology elsewhere in the NPRM?
                 90. Summarizing the proposed changes under the proposed alternative
                regulatory fee methodology for space
                [[Page 20599]]
                stations above, 47 CFR 1.1156 would be proposed to read as follows:
                ------------------------------------------------------------------------
                 Fee category Fee amount
                ------------------------------------------------------------------------
                Space Stations (Per Call Sign of Authorized Space [TBD]
                 Station in Geostationary Orbit or Per System of 100 or
                 Fewer Authorized Space Stations in Non-Geostationary
                 Orbit).................................................
                Space Stations (Per Tier of Up to 500 [or 1,000] [TBD]
                 Additionally Authorized Space Stations in Non-
                 Geostationary Orbit)...................................
                Space Station (per license/call sign) (Small Satellites) [TBD]
                ------------------------------------------------------------------------
                 91. The Commission finds that the proposal to use the alternative
                methodology to assess regulatory fees for space and earth stations
                would be an amendment as defined in 47 U.S.C. 159(d). Such an amendment
                must be submitted to Congress at least 90 days before it becomes
                effective pursuant to 47 U.S.C. 159A(b)(2).
                E. Other Matters
                 92. Changing the Title of 47 CFR 1.1156. The Commission proposes to
                change the title of 47 CFR 1.1156 to make it clear that it contains
                space and earth station regulatory fees. Currently, satellite
                regulatory fees are contained in 47 CFR 1.1156, which is titled,
                ``Schedule of regulatory fees for international services.'' The
                Commission proposes to rename this section as ``Schedule of regulatory
                fees for space and international services'' to reflect more accurately
                that the section contains the regulatory fees for space and earth
                stations, as well as the fees for international bearer circuits and
                submarine cables regulated by the Office of International Affairs. The
                current title of 47 CFR 1.1156 was accurate when all categories of fees
                within it were regulated by the International Bureau. After the
                reorganization of the International Bureau into the Space Bureau and
                the Office of International Affairs, the current title can cause
                confusion by suggesting that only the fees for regulatees of the Office
                of International Affairs are contained within 47 CFR 1.1156. The
                Commission tentatively concludes that it would be easier to change the
                title of 47 CFR 1.1156 than to create a new section in 47 CFR part 1,
                subpart G, containing space and earth station regulatory fees. The
                Commission seeks comment on this tentative conclusion and proposal.
                 93. Digital Equity and Inclusion. The Commission, as part of its
                continuing effort to advance digital equity for all, including people
                of color, persons with disabilities, persons who live in rural or
                Tribal areas, and others who are or have been historically underserved,
                marginalized, or adversely affected by persistent poverty or
                inequality, invites comment on any equity-related considerations and
                benefits (if any) that may be associated with the proposals and issues
                discussed in the NPRM. Specifically, the Commission seeks comment on
                how its proposals may promote or inhibit advances in diversity, equity,
                inclusion, and accessibility, as well the scope of the Commission's
                relevant legal authority. The NPRM notes that diversity and equity
                considerations, however, do not allow the Commission to shift fees from
                one party of fee payors to another, nor to use fees under 47 U.S.C. 159
                for any purpose other than as an offsetting collection in the amount of
                the Commission's annual S&E appropriation.
                 94. Space Innovation Agenda. The Commission has an open proceeding
                on advancing opportunities for innovation in the new space age by
                taking measures to expedite the application processes for space
                stations and earth stations, consistent with the Commission's objective
                to promote a competitive and innovative global telecommunications
                marketplace via space services'' In September 2023, the Commission
                adopted a Report and Order (Dec. 6, 2023, 88 FR 84737) that further
                streamlined its application review process, including establishing
                clear timeframes for placing space and earth station applications on
                public notice. The Commission also sought comment on several proposed
                changes to further streamline the licensing process and reduce
                applicant and staff burdens in a Further Notice of Proposed Rulemaking
                (Dec. 8, 2023, 88 FR 85553). Finally, the Commission announced a
                Transparency Initiative with the goal of providing information and
                guidance, in a variety of forms, to interested parties so they can
                understand the Commission's procedures and what is needed to obtain
                authorization for their proposed space station and earth station
                operations. The Commission seeks comment, generally, how that
                proceeding and initiative might inform its consideration of the issues
                raised in the NPRM.
                IV. Initial Regulatory Flexibility Analysis
                 95. As required by the Regulatory Flexibility Act of 1980, as
                amended (RFA), the Commission has prepared an Initial Regulatory
                Flexibility Analysis (IRFA) of the possible significant economic impact
                on small entities by the policies and rules proposed in the NPRM.
                Written comments are requested on the IRFA. Comments must be filed by
                the deadlines for comments on the NPRM indicated on the DATES section
                of this document and must have a separate and distinct heading
                designating them as responses to the IRFA. The Commission will send a
                copy of the NPRM, including the IRFA, to the Chief Counsel for Advocacy
                of the Small Business Administration (SBA).
                A. Need for, and Objective of, the Proposed Rules
                 96. The Commission is required by Congress pursuant to 47 U.S.C.
                159 to assess and collect regulatory fees each year to recover the
                regulatory costs associated with the Commission's oversight and
                regulatory activities in an amount that can reasonably be expected to
                equal the amount of its annual appropriation. As part of last year's
                adoption of regulatory fees, the Commission noted that FY 2023 would be
                the last year where the Commission will do so for the International
                Bureau, given the creation of the Space Bureau, and Office of
                International Affairs. The Commission also noted that an examination of
                the regulatory fees, and categories for NGSO space stations would be
                useful in light of changes resulting from the creation of the Space
                Bureau, and as part of a more holistic review of the FTE burden of the
                Space Bureau in FY 2024.
                 97. The NPRM commences the examination and review of regulatory
                fees for space and earth station payors regulated by the new Space
                Bureau, specifically seeking comment on a range of proposed changes to
                the assessment of regulatory fees for space and earth stations under
                the existing methodology. It proposes to: (1) change the allocation of
                fee burdens between GSO and NGSO space stations and maintain the
                existing allocation of fee burdens between the categories of ``less
                complex'' and ``other'' NGSO space stations; (2) create new fee
                categories within the existing fee category of ``Space Station (Non-
                Geostationary
                [[Page 20600]]
                Orbit)--Other'' to make assessment of the Commission's regulatory fees
                fairer, more administrable, and more sustainable; (3) set the
                regulatory fee for ``Space Stations (per license/call sign in non-
                geostationary orbit) (47 CFR part 25) (Small Satellite)'' for FY 2024
                and future fiscal years at the level set for FY 2023, annually adjusted
                to reflect the percentage change in the appropriation from the previous
                fiscal year; (4) include, on an interim basis, space stations that are
                principally used for RPO or OOS, including OTV, in the existing fee
                category for ``small satellites'' until the Commission can develop more
                experience in how these space stations will be regulated; (5) assess
                regulatory fees on all authorized space stations, not just on
                operational space stations, in order to adhere more closely to the
                framework of 47 U.S.C. 159, and to make the Commission's fees fairer,
                more administrable, and more sustainable; and (6) increase the
                allocation of fees payable by earth station licensees in order to
                reflect more accurately the fee burden attributable to their licensing
                and regulation and seek comment on whether additional earth station fee
                categories should be created.
                 98. Additionally, the NPRM proposes to amend the title of 47 CFR
                1.1156, currently titled ``Schedule of regulatory fees for
                international services,'' to clarify that the rule includes space and
                earth station regulatory fees, following the reorganization of the
                Commission's International Bureau. The NPRM also proposes an
                alternative methodology for assessing space station regulatory fees by
                eliminating the separate categories of regulatory fees for GSO and NGSO
                space stations, as well as existing subcategories for NGSO space
                stations, while retaining the existing separate regulatory fee category
                for small satellites and spacecraft licensed under 47 CFR 25.122
                through 25.123. The goal of these proposals is to update the regulatory
                fees and categories for earth and space stations in light of changes
                resulting from the creation of the Space Bureau and as part of a more
                holistic review of the regulatory fees for earth and space stations in
                FY 2024.
                B. Legal Basis
                 99. The proposed action is authorized pursuant to 47 U.S.C. 154(i)
                and (j), 159, 159A, and 303(r).
                C. Description and Estimate of the Number of Small Entities to Which
                the Proposed Rules Will Apply
                 100. The RFA directs agencies to provide a description of, and
                where feasible, an estimate of the number of small entities that may be
                affected by the proposed rules, if adopted. The RFA generally defines
                the term ``small entity'' as having the same meaning as the terms
                ``small business,'' ``small organization,'' and ``small governmental
                jurisdiction.'' In addition, the term ``small business'' has the same
                meaning as the term ``small business concern'' under the Small Business
                Act. A ``small business concern'' is one which: (1) is independently
                owned and operated; (2) is not dominant in its field of operation; and
                (3) satisfies any additional criteria established by the SBA.
                 101. Small Businesses, Small Organizations, Small Governmental
                Jurisdictions. The Commission's actions, over time, may affect small
                entities that are not easily categorized at present. The Commission
                therefore describes, at the outset, three broad groups of small
                entities that could be directly affected herein. First, while there are
                industry specific size standards for small businesses that are used in
                the regulatory flexibility analysis, according to data from the Small
                Business Administration's (SBA) Office of Advocacy, in general a small
                business is an independent business having fewer than 500 employees.
                These types of small businesses represent 99.9% of all businesses in
                the United States, which translates to 33.2 million businesses.
                 102. Next, the type of small entity described as a ``small
                organization'' is generally ``any not-for-profit enterprise which is
                independently owned and operated and is not dominant in its field.''
                The Internal Revenue Service (IRS) uses a revenue benchmark of $50,000
                or less to delineate its annual electronic filing requirements for
                small exempt organizations. Nationwide, for tax year 2020, there were
                approximately 447,689 small exempt organizations in the U.S. reporting
                revenues of $50,000 or less according to the registration and tax data
                for exempt organizations available from the IRS.
                 103. Finally, the small entity described as a ``small governmental
                jurisdiction'' is defined generally as ``governments of cities,
                counties, towns, townships, villages, school districts, or special
                districts, with a population of less than fifty thousand.'' U.S. Census
                Bureau data from the 2017 Census of Governments indicate that there
                were 90,075 local governmental jurisdictions consisting of general
                purpose governments and special purpose governments in the United
                States. Of this number there were 36,931 general purpose governments
                (county, municipal and town or township) with populations of less than
                50,000 and 12,040 special purpose governments--independent school
                districts with enrollment populations of less than 5ll governmental
                jurisdictions.''
                 104. Direct Broadcast Satellite (DBS) Service. DBS service is a
                nationally distributed subscription service that delivers video and
                audio programming via satellite to a small parabolic ``dish'' antenna
                at the subscriber's location. DBS is included in the Wired
                Telecommunications Carriers industry which comprises establishments
                primarily engaged in operating and/or providing access to transmission
                facilities and infrastructure that they own and/or lease for the
                transmission of voice, data, text, sound, and video using wired
                telecommunications networks. Transmission facilities may be based on a
                single technology or combination of technologies. Establishments in
                this industry use the wired telecommunications network facilities that
                they operate to provide a variety of services, such as wired telephony
                services, including VoIP services, wired (cable) audio and video
                programming distribution; and wired broadband internet services. By
                exception, establishments providing satellite television distribution
                services using facilities and infrastructure that they operate are
                included in this industry.
                 105. The SBA small business size standard for Wired
                Telecommunications Carriers classifies firms having 1,500 or fewer
                employees as small. U.S. Census Bureau data for 2017 show that 3,054
                firms operated in this industry for the entire year. Of this number,
                2,964 firms operated with fewer than 250 employees. Based on this data,
                the majority of firms in this industry can be considered small under
                the SBA small business size standard. According to Commission data
                however, only two entities provide DBS service--DIRECTV (owned by AT&T)
                and DISH Network--which require a great deal of capital for operation.
                DIRECTV and DISH Network both exceed the SBA size standard for
                classification as a small business. Therefore, the Commission must
                conclude, based on internally developed Commission data, in general DBS
                service is provided only by large firms.
                 106. Fixed Satellite Small Transmit/Receive Earth Stations. Neither
                the SBA nor the Commission have developed a small business size
                standard specifically applicable to Fixed Satellite Small Transmit/
                Receive Earth Stations. Satellite Telecommunications is the closest
                industry with an SBA small business size standard. The SBA size
                standard for this industry classifies a business as small if it has
                $38.5 million or less in annual receipts. For this industry, U.S.
                Census Bureau data for 2017 show that there was a total of 275
                [[Page 20601]]
                firms that operated for the entire year. Of this total, 242 firms had
                revenue of less than $25 million. Additionally, based on Commission
                data in the 2022 Universal Service Monitoring Report, as of December
                31, 2021, there were 65 providers that reported they were engaged in
                the provision of satellite telecommunications services. Of these
                providers, the Commission estimates that approximately 42 providers
                have 1,500 or fewer employees. Consequently, using the SBA's small
                business size standard, a little more than half of these providers can
                be considered small entities.
                 107. Fixed Satellite Very Small Aperture Terminal (VSAT) Systems.
                Neither the SBA nor the Commission have developed a small business size
                standard specifically applicable to Fixed Satellite VSAT Systems. A
                VSAT is a relatively small satellite antenna used for satellite-based
                point-to-multipoint data communications applications. VSAT networks
                provide support for credit verification, transaction authorization, and
                billing and inventory management. Satellite Telecommunications is the
                closest industry with an SBA small business size standard. The SBA size
                standard for this industry classifies a business as small if it has
                $38.5 million or less in annual receipts. For this industry, U.S.
                Census Bureau data for 2017 show that there were a total of 275 firms
                that operated for the entire year. Of this total, 242 firms had revenue
                of less than $25 million. Additionally, based on Commission data in the
                2022 Universal Service Monitoring Report, as of December 31, 2021,
                there were 65 providers that reported they were engaged in the
                provision of satellite telecommunications services. Of these providers,
                the Commission estimates that approximately 42 providers have 1,500 or
                fewer employees. Consequently using the SBA's small business size
                standard, a little more than half of these providers can be considered
                small entities.
                 108. Home Satellite Dish (HSD) Service. Home Satellite Dish (HSD)
                or the large dish segment of the satellite industry is the original
                satellite-to-home service offered to consumers and involves the home
                reception of signals transmitted by satellites operating generally in
                the C-band frequency. Unlike DBS, which uses small dishes, HSD antennas
                are between four and eight feet in diameter and can receive a wide
                range of unscrambled (free) programming and scrambled programming
                purchased from program packagers that are licensed to facilitate
                subscribers' receipt of video programming. Because HSD provides
                subscription services, HSD falls within the industry category of Wired
                Telecommunications Carriers. The SBA small business size standard for
                Wired Telecommunications Carriers classifies firms having 1,500 or
                fewer employees as small. U.S. Census Bureau data for 2017 show that
                there were 3,054 firms that operated for the entire year. Of this
                total, 2,964 firms operated with fewer than 250 employees. Thus, under
                the SBA size standard, the majority of firms in this industry can be
                considered small.
                 109. Mobile Satellite Earth Stations. Neither the SBA nor the
                Commission have developed a small business size standard specifically
                applicable to Mobile Satellite Earth Stations. Satellite
                Telecommunications is the closest industry with a SBA small business
                size standard. The SBA small business size standard classifies a
                business with $38.5 million or less in annual receipts as small. For
                this industry, U.S. Census Bureau data for 2017 show that there were
                275 firms that operated for the entire year. Of this number, 242 firms
                had revenue of less than $25 million. Thus, for this industry under the
                SBA size standard, the Commission estimates that the majority of Mobile
                Satellite Earth Station licensees are small entities. Additionally,
                based on Commission data as of February 1, 2024, there were 16 Mobile
                Satellite Earth Stations licensees. The Commission does not request nor
                collect annual revenue information and is therefore unable to estimate
                the number of mobile satellite earth stations that would be classified
                as a small business under the SBA size standard.
                 110. Satellite Master Antenna Television (SMATV) Systems, also
                known as Private Cable Operators (PCOs). SMATV systems or PCOs are
                video distribution facilities that use closed transmission paths
                without using any public right-of-way. They acquire video programming
                and distribute it via terrestrial wiring in urban and suburban multiple
                dwelling units such as apartments and condominiums, and commercial
                multiple tenant units such as hotels and office buildings. SMATV
                systems or PCOs are included in the Wired Telecommunications Carriers'
                industry which includes wireline telecommunications businesses. The SBA
                small business size standard for Wired Telecommunications Carriers
                classifies firms having 1,500 or fewer employees as small. U.S. Census
                Bureau data for 2017 show that there were 3,054 firms in this industry
                that operated for the entire year. Of this total, 2,964 firms operated
                with fewer than 250 employees. Thus, under the SBA size standard, the
                majority of firms in this industry can be considered small.
                 111. Satellite Telecommunications. This industry comprises firms
                ``primarily engaged in providing telecommunications services to other
                establishments in the telecommunications and broadcasting industries by
                forwarding and receiving communications signals via a system of
                satellites or reselling satellite telecommunications.'' Satellite
                telecommunications service providers include satellite and earth
                station operators. The SBA small business size standard for this
                industry classifies a business with $38.5 million or less in annual
                receipts as small. U.S. Census Bureau data for 2017 show that 275 firms
                in this industry operated for the entire year. Of this number, 242
                firms had revenue of less than $25 million. Additionally, based on
                Commission data in the 2022 Universal Service Monitoring Report, as of
                December 31, 2021, there were 65 providers that reported they were
                engaged in the provision of satellite telecommunications services. Of
                these providers, the Commission estimates that approximately 42
                providers have 1,500 or fewer employees. Consequently, using the SBA's
                small business size standard, a little more than half of these
                providers can be considered small entities.
                 112. All Other Telecommunications. This industry is comprised of
                establishments primarily engaged in providing specialized
                telecommunications services, such as satellite tracking, communications
                telemetry, and radar station operation. This industry also includes
                establishments primarily engaged in providing satellite terminal
                stations and associated facilities connected with one or more
                terrestrial systems and capable of transmitting telecommunications to,
                and receiving telecommunications from, satellite systems. Providers of
                internet services (e.g., dial-up ISPs) or Voice over internet Protocol
                (VoIP) services, via client-supplied telecommunications connections are
                also included in this industry. The SBA small business size standard
                for this industry classifies firms with annual receipts of $35 million
                or less as small. U.S. Census Bureau data for 2017 show that there were
                1,079 firms in this industry that operated for the entire year. Of
                those firms, 1,039 had revenue of less than $25 million. Based on this
                data, the Commission estimates that the majority of ``All Other
                Telecommunications'' firms can be considered small.
                [[Page 20602]]
                D. Description of Projected Reporting, Recordkeeping and Other
                Compliance Requirements for Small Entities
                 113. The NPRM does not propose any changes to the Commission's
                current information collection, reporting, recordkeeping, or compliance
                requirements for small entities. Small and other regulated entities are
                required to pay regulatory fees on an annual basis. The cost of
                compliance with the annual regulatory assessment for small entities is
                the amount assessed for their regulatory fee category and should not
                require small entities to hire professionals to comply.
                 114. Small entities that qualify can take advantage of the
                exemption from payment of regulatory fees allowed under the de minimis
                threshold. In addition, small entities may request a waiver, reduction,
                deferral, and/or installment payment of their regulatory fees. The
                waiver process is an easier filing process for smaller entities that
                may not be familiar with the Commission's procedural filing rules.
                E. Steps Taken To Minimize Significant Economic Impact on Small
                Entities, and Significant Alternatives Considered
                 115. The RFA requires an agency to describe any significant,
                specifically business, alternatives that it has considered in reaching
                its proposed approach, which may include the following four
                alternatives, among others: (1) the establishment of differing
                compliance or reporting requirements or timetables that take into
                account the resources available to small entities; (2) the
                clarification, consolidation, or simplification of compliance or
                reporting requirements under the rule for such small entities; (3) the
                use of performance, rather than design, standards; and (4) an exemption
                from coverage of the rule, or any part thereof, for such small
                entities.
                 116. The NPRM seeks comment on a number of amendments to the
                existing methodology of assessing regulatory fees paid by space and
                earth station payors. While the NPRM initiates the examination and
                review of regulatory fees for space and earth station payors under the
                existing regulatory fee methodology, the Commission will propose and
                finalize the regulatory fee rates for space and earth station payors as
                part of its annual Commission-wide regulatory fee proceeding for FY
                2024. Commenters will have an opportunity in that proceeding to provide
                comments on the proposed regulatory fee rates for space and earth
                station payors. The NPRM gives parties an opportunity to file comments
                on possible changes to the existing methodology for assessing space and
                earth station regulatory fees. If any of these proposals are adopted,
                it may reduce the regulatory fee burden on some satellite entities.
                 117. Specifically, the NPRM seeks comment on a proposal to divide
                the existing regulatory fee subcategory of ``Space Stations (Non-
                Geostationary Orbit)--Other'' into two tiers: ``Large Constellations''
                of more than 1,000 authorized space stations; and ``Small
                Constellations'' of 1,000 or fewer authorized space stations. The
                current single regulatory fee for all NGSO ``other'' space station
                payors has resulted in requests by fee payors of smaller NGSO systems
                seeking to be assessed regulatory fees as NGSO ``less complex''
                systems. If adopted, the proposal for the tiered approach for the NGSO
                space station ``other'' category would likely reduce the regulatory fee
                burden on smaller satellite constellations, and likely on smaller
                entities.
                 118. As another example, the NPRM notes that, based on preliminary
                calculations, the fee amount for the small satellite category for FY
                2024 could be substantially greater than the fee assessed for FY 2023.
                The NPRM proposes that the administrability and sustainability of
                regulatory fees for small satellites would be better served by treating
                them as the Commission has historically treated the regulatory fees for
                earth stations--that is, a fixed regulatory fee that is adjusted from
                year-to-year on, rather than as a percentage of the Space Bureau's
                overall share of regulatory fee allocation, or as a percentage of other
                categories of space station fee payors. This proposal if adopted would
                significantly minimize the economic impact of regulatory fees
                potentially faced by small satellites.
                 119. The NPRM also proposes, on an interim basis, to assess
                regulatory fees on spacecraft primarily performing RPO and OOS by
                including them in the existing regulatory fee category ``Space Stations
                (per license/call sign in non-geostationary orbit) (Small Satellites)''
                regardless of the orbit in which they are designed to operate in. The
                Space Bureau has received relatively few applications for RPO or OOS
                space stations, and although it anticipates receiving more in the near
                future, the amount of FTE resources required at the present time to
                regulate these services is more similar to that presented by small
                satellite space station licensees, which are also few in number, and
                involve a relatively small number of space stations that have limited
                duration and scope of use and operate using shared spectrum resources.
                Therefore, the NPRM tentatively concludes that the purposes of 47
                U.S.C. 159 would be best met by erring on the side of caution and
                assessing regulatory fees under the category of fees associated with
                the least-burdensome set of space station regulates which would result
                in lower regulatory fees, and have less economic impact.
                 120. The NPRM also seeks comment on possibly creating subcategories
                of earth station regulatory fee payors to better differentiate the
                amount of regulatory burdens associated with different types of earth
                station licenses. This may reduce the regulatory fee burden on some
                smaller earth station payees who could face a substantial increase in
                the per unit regulatory fee if the Commission adopts the proposal in
                the NPRM to apportion 20% of all Space Bureau regulatory fees to earth
                station licensees beginning in FY 2024.
                 121. Finally, the NPRM seeks comment on an alternative methodology
                for assessing space station regulatory fees that eliminates the
                distinction between GSO, NGSO, and all the subcategories of NGSO, while
                preserving a separate fee category for small satellites. The
                alternative methodology would have a single category for ``Space
                Stations (Per Call Sign in Geostationary Orbit or Per System in Non-
                Geostationary Orbit),'' which would be tiered, with a single GSO space
                station or a NGSO system with up to 100 authorized space stations
                constituting the first tier and being counted as one unit for
                assessment of space station regulatory fees, and additional tiers added
                to account for NGSO systems with more than 100 authorized space
                stations, with the possibility of 500 or 1,000 additional space
                stations per NGSO system per tier. Each tier would be counted as an
                additional unit for assessment of space station regulatory fees.
                Accordingly, GSO payors and NGSO systems of 100 authorized space
                stations or fewer would be assessed the lowest regulatory fees, while
                payors with multiple authorized GSO space stations, or with NGSO
                systems with more than 100 authorized space stations would be assessed
                higher regulatory fees, with the highest regulatory fees assessed to
                payors with a large number of GSO space stations, and to payors with
                NGSO systems consisting of thousands of authorized space stations. The
                Commission believes this alternative methodology could be more
                administrable, fair, and sustainable than the existing methodology, and
                the NPRM seeks comment on all aspects of this alternative methodology
                for assessing space station regulatory fees.
                [[Page 20603]]
                F. Federal Rules That May Duplicate, Overlap, or Conflict With the
                Proposed Rules
                 122. None.
                Federal Communications Commission.
                Marlene Dortch,
                Secretary.
                [FR Doc. 2024-05996 Filed 3-22-24; 8:45 am]
                BILLING CODE 6712-01-P
                

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT