Approval and Promulgation of Implementation Plans: South Carolina; Approval of Section 110(a)(1) Maintenance Plan for the 1997 8-Hour Ozone Standard for Cherokee County; Correcting Amendment

Federal Register: January 25, 2010 (Volume 75, Number 15)

Rules and Regulations

Page 3870-3871

From the Federal Register Online via GPO Access [wais.access.gpo.gov]

DOCID:fr25ja10-7

ENVIRONMENTAL PROTECTION AGENCY 40 CFR Part 52

EPA-R04-OAR-2008-0797-200824(c); FRL-9099-9

Approval and Promulgation of Implementation Plans; South

Carolina; Approval of Section 110(a)(1) Maintenance Plan for the 1997 8-Hour Ozone Standard for Cherokee County; Correcting Amendment

AGENCY: Environmental Protection Agency (EPA).

ACTION: Final rule; Correcting amendment.

SUMMARY: On June 1, 2009, EPA published a direct final rule approving the Clean Air Act (CAA) Section 110(a)(1) Maintenance Plan for the 1997 8-hour ozone standard for Cherokee County as a revision to the South

Carolina State Implementation Plan (SIP). In EPA's direct final rule, there was an inadvertent error in the format of the Cherokee County entry in table (e) which contains South Carolina's Non-Regulatory

Provision in the Code of Federal Regulations. This action corrects that formatting error.

DATES: This action is effective January 25, 2010.

ADDRESSES: Copies of the documentation used in the action being corrected are available for inspection during normal business hours at the following location: U.S. Environmental Protection Agency, Region 4, 61 Forsyth Street, SW., Atlanta, Georgia 30303-8960. The Regional

Office's official hours of business are Monday through Friday, 8:30 to 4:30, excluding Federal holidays.

FOR FURTHER INFORMATION CONTACT: Zuri Farngalo, Regulatory Development

Section, Air Planning Branch, Air, Pesticides and Toxics Management

Division, U.S. Environmental Protection Agency, Region 4, 61 Forsyth

Street, SW., Atlanta, Georgia 30303-8960. Mr. Farngalo's telephone number is 404-562-9152. He can also be reached via electronic mail at farngalo.zuri@epa.gov.

SUPPLEMENTARY INFORMATION: EPA is making a correction to the Cherokee

County CAA 110(a)(1) Maintenance Plan entry that appears in table (e), of the South Carolina Non-Regulatory provisions section at 40 CFR 52.2120(e). This revision to South Carolina's SIP was published in the

Federal Register on June 1, 2009 (74 FR 26099), effective August 1, 2009. However, when the direct final rule approving this SIP revision was published, table (e) did not include the correct table format. EPA is correcting this inadvertent error by inserting the correctly formatted table (e) into South Carolina's Identification of Plan section of the Code of Federal Regulations at 40 CFR 52.2120(e).

EPA has determined that today's action falls under the ``good cause'' exemption in section 553(b)(3)(B) of the Administrative

Procedure Act (APA) which, upon finding ``good cause,'' authorizes agencies to dispense with public participation where public notice and comment procedures are impracticable, unnecessary, or contrary to the public interest. Public notice and comment for this action are unnecessary because today's action to correct a formatting error in the

Code of Federal Regulations has no substantive impact on EPA's June 1, 2009, approval of this regulation. The incorrectly formatted text in table (e) in EPA's final rule published on June 1, 2009, makes no substantive difference to EPA's analysis as set out in that rule. In addition, EPA can identify no particular reason why the public would be interested in being notified of the correction of this revision, or in having the opportunity to comment on the formatting correction prior to this action being finalized, since this formatting correction action does not change the meaning of the regulation at issue or otherwise change EPA's analysis of South Carolina's submittal (74 FR 26099). EPA also finds that there is good cause under APA section 553(d)(3) for this formatting correction to become effective on the date of publication of this action. Section 553(d)(3) of the APA allows an effective date less than 30 days after publication ``as otherwise provided by the agency for good cause found and published with the rule.'' 5 U.S.C. 553(d)(3). The purpose of the 30-day waiting period prescribed in APA section 553(d)(3) is to give affected parties a reasonable time to adjust their behavior and prepare before the final rule takes effect. Today's rule, however, does not create any new regulatory requirements such that affected parties would need time to prepare before the rule takes effect. Rather, today's rule merely corrects an inadvertent error of omission in the regulatory text of a prior rule by adding a correctly formatted table (e) for the South

Carolina regulation which EPA approved on June 1, 2009. For these reasons, EPA finds good cause under APA section 553(d)(3) for this correction to become effective on the date of publication of this action.

Statutory and Executive Order Reviews

Under the CAA, the Administrator is required to approve a SIP submission that complies with the provisions of the Act and applicable

Federal regulations 42 U.S.C. 7410(k); 40 CFR 52.02(a). Thus, in reviewing SIP submissions, EPA's role is to approve state choices, provided that they meet the criteria of the CAA. Accordingly, this action merely approves state law as meeting Federal requirements and does not impose additional requirements beyond those imposed by state law. For that reason, this action:

Is not a ``significant regulatory action'' subject to review by the Office of Management and Budget under Executive Order 12866 (58 FR 51735, October 4, 1993);

Does not impose an information collection burden under the provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.);

Is certified as not having a significant economic impact on a substantial number of small entities under the Regulatory

Flexibility Act (5 U.S.C. 601 et seq.);

Does not contain any unfunded mandate or significantly or uniquely affect small governments, as described in the Unfunded

Mandates Reform Act of 1995 (Pub. L. 104-4);

Page 3871

Does not have Federalism implications as specified in

Executive Order 13132 (64 FR 43255, August 10, 1999);

Is not an economically significant regulatory action based on health or safety risks subject to Executive Order 13045 (62 FR 19885, April 23, 1997);

Is not a significant regulatory action subject to

Executive Order 13211 (66 FR 28355, May 22, 2001);

Is not subject to requirements of Section 12(d) of the

National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 note) because application of those requirements would be inconsistent with the CAA; and

Does not provide EPA with the discretionary authority to address, as appropriate, disproportionate human health or environmental effects, using practicable and legally permissible methods, under

Executive Order 12898 (59 FR 7629, February 16, 1994).

In addition, this rule does not have tribal implications as specified by Executive Order 13175 (65 FR 67249, November 9, 2000), because the

SIP is not approved to apply in Indian country located in the state, and EPA notes that it will not impose substantial direct costs on tribal governments or preempt tribal law.

The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the

Small Business Regulatory Enforcement Fairness Act of 1996, generally provides that before a rule may take effect, the agency promulgating the rule must submit a rule report, which includes a copy of the rule, to each House of the Congress and to the Comptroller General of the

United States. EPA will submit a report containing this action and other required information to the U.S. Senate, the U.S. House of

Representatives, and the Comptroller General of the United States prior to publication of the rule in the Federal Register. A major rule cannot take effect until 60 days after it is published in the Federal

Register. This action is not a ``major rule'' as defined by 5 U.S.C. 804(2).

Under section 307(b)(1) of the CAA, petitions for judicial review of this action must be filed in the United States Court of Appeals for the appropriate circuit by March 26, 2010. Filing a petition for reconsideration by the Administrator of this final rule does not affect the finality of this action for the purposes of judicial review nor does it extend the time within which a petition for judicial review may be filed, and shall not postpone the effectiveness of such rule or action. This action may not be challenged later in proceedings to enforce its requirements (See section 307(b)(2)).

List of Subjects in 40 CFR Part 52

Environmental protection, Air pollution control, Intergovernmental relations, Incorporation by reference, Nitrogen dioxide, Ozone,

Reporting and recordkeeping requirements, Volatile organic compounds.

Dated: December 14, 2009.

J. Scott Gordon,

Acting Regional Administrator, Region 4. 0 40 CFR part 52 is amended as follows:

PART 52--[AMENDED] 0 1. The authority citation for part 52 continues to read as follows:

Authority: 42 U.S.C. 7401 et seq.

Subpart PP--South Carolina 0 2. Section 52.2120(e) is amended by revising the entry for the

``Cherokee County 110(a)(1) Maintenance Plan for the 1997 8-hour ozone standard'' to read as follows:

Sec. 52.2120 Identification of plan.

* * * * *

(e) * * *

EPA-Approved South Carolina Non-Regulatory Provisions

State effective

Provision

date

EPA approval date

Explanation

* * * * * * *

Cherokee County 110(a)(1) Maintenance

12/13/2007 7/31/09, 74 FR 26099............. ................

Plan for the 1997 8-Hour Ozone Standard.

* * * * *

FR Doc. E9-31172 Filed 1-22-10; 8:45 am