ACTION: Notice of temporary deviation from regulations.

SUMMARY: The Commander, First Coast Guard District, has issued a temporary deviation from the regulation governing the operation of the

Upper Hack Bridge at mile 6.9, across the Hackensack River, at

Secaucus, New Jersey. Under this temporary deviation the bridge may remain in the closed position for two days in November to facilitate bridge repairs.

DATES: This deviation is effective from 8 a.m. on November 18, 2010 through 6 p.m. on November 19, 2010.

ADDRESSES: Documents mentioned in this preamble as being available in the docket are part of docket USCG-2010-0977 and are available online at http://www.regulations.gov, inserting USCG-2010-0977 in the

``Keyword'' and then clicking ``Search''. They are also available for inspection or copying at the Docket Management Facility (M-30), U.S.

Department of Transportation, West Building Ground Floor, Room W12-140, 1200 New Jersey Avenue, SE., Washington, DC 20590, between 9 a.m. and 5 p.m., Monday through Friday, except Federal holidays.

FOR FURTHER INFORMATION CONTACT: If you have questions on this rule, call or e-mail Mr. Joe Arca, Project Officer, First Coast Guard

District, telephone (212) 668-7165. If you have questions on viewing the docket, call Renee V. Wright, Program Manager, Docket Operations, telephone 202-366-9826.

SUPPLEMENTARY INFORMATION: The Upper Hack Bridge, across the Hackensack

River at mile 6.9 has a vertical clearance in the closed position of 8 feet at mean high water and 13 feet at mean low water. The existing drawbridge operation regulations are listed at 33 CFR 117.723(d).

The waterway has seasonal recreational vessels, and commercial vessels of various sizes.

The owner of the bridge, New Jersey Transit, requested a temporary deviation to facilitate necessary electrical system upgrades and asbestos removal at the bridge.

Under this temporary deviation the Upper Hack Bridge, mile 6.9, across the Hackensack River may remain in the closed position from 8 a.m. on November 18, 2010 through 6 p.m. on November 19, 2010. Vessels that can pass under the bridge without a bridge opening may do so at all times.

In accordance with 33 CFR 117.35(e), the bridge must return to its regular operating schedule immediately at the end of the designated time period. This deviation from the operating regulations is authorized under 33 CFR 117.35.

Dated: October 27, 2010.

Gary Kassof,

Bridge Program Manager, First Coast Guard District.

FR Doc. 2010-28204 Filed 11-8-10; 8:45 am