Fort Dodge Hydroelectric Development Company; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions

November 7, 2006.

Take notice that the following hydroelectric license application has been filed with the Commission and is available for public inspection.

  1. Type of Application: Original Minor License.

  2. Project No.: P-12447-001.

  3. Date Filed: March 21, 2006.

  4. Applicant: Fort Dodge Hydroelectric Development Company.

  5. Name of Project: Fort Dodge Mill Dam Hydroelectric Project.

  6. Location: Located on the Des Moines River in Webster County, Iowa. This project would not occupy Federal lands.

  7. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).

  8. Applicant Contact: Thomas J. Wilkinson, Jr., Fort Dodge Hydroelectric Development Company, 1800 1st Ave. NE., Ste. 200, Cedar Rapids, IA 52402; (319) 364-0171.

  9. FERC Contact: Patrick Murphy, (202) 502-8755, patrick.murphy@ferc.gov.

  10. Deadline for filing comments, recommendations, terms and conditions, and prescriptions: 60 days

    [[Page 66515]]

    from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice.

    All documents (original and eight copies) should be filed with: Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426.

    The Commission's Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

    Comments, recommendations, terms and conditions, and prescriptions may be filed electronically via the Internet in lieu of paper. The Commission strongly encourages electronic filings. See CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site (http://www.ferc.gov) under the ``eFiling'' link.

  11. This application has been accepted, and is ready for environmental analysis at this time.

  12. The Fort Dodge Mill Dam Project would consist of: (1) The existing 342-foot-long by 18-foot-high concrete dam with a 230-foot- long spillway and 5 Tainter gates; (2) an existing 90-acre reservoir with a normal full pond elevation of 990 feet above mean sea level; (3) an existing 40-foot-wide concrete intake structure with trash rack and stop log guides; (4) an existing powerhouse to contain two proposed turbine generating units with a total installed capacity of 1,400 kW; (5) a proposed 2,400-foot-long, 13.8-kV transmission line; and (6) appurtenant facilities. The applicant estimates that the total average annual generation would be about 7,506 MWh.

  13. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the ``eLibrary''

    link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1- 866-208-3676, or for TTY, (202) 502-8659. A copy is also available for inspection and reproduction at the address in item h. above.

    All filings must: (1) Bear in all capital letters the title ``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS'', ``TERMS AND CONDITIONS'', or ``PRESCRIPTIONS''; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person submitting the filing; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions, or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. Each filing must be accompanied by proof of service on all persons listed on the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b), and 385.2010.

    You may also register online at http://www.ferc.gov/docs-filing/esubscribenow.asp to be notified via e-mail of new filings and

    issuances related to this or other pending projects. For assistance, contact FERC Online Support.

  14. Procedural schedule: The Commission staff proposes to issue an Environmental Assessment (EA) rather than issuing a draft and final EA. Staff intends to allow at least 30 days for entities to comment on the EA, and will take into consideration all comments received on the EA before final action is taken on the license application. The application will be processed according to the following schedule, but revisions to the schedule may be made as appropriate:

    Issue Notice of availability of the EA: April 2007.

    Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis.

  15. A license applicant must file no later than 60 days following the date of issuance of this notice: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification.

    Magalie R. Salas, Secretary.