Permanent program and abandoned mine land reclamation plan submissions: Wyoming,

[Federal Register: July 29, 1998 (Volume 63, Number 145)]

[Proposed Rules]

[Page 40384-40386]

From the Federal Register Online via GPO Access [wais.access.gpo.gov]

[DOCID:fr29jy98-18]

DEPARTMENT OF THE INTERIOR

Office of Surface Mining Reclamation and Enforcement

30 CFR Part 950

[WY-028-FOR]

Wyoming Regulatory Program

AGENCY: Office of Surface Mining Reclamation and Enforcement, Interior.

ACTION: Proposed rule; public comment period and opportunity for public hearing on proposed amendment.

SUMMARY: The Office of Surface Mining Reclamation and Enforcement (OSM) is announcing receipt of a proposed amendment to the Wyoming regulatory program (hereinafter, the ``Wyoming program'') under the Surface Mining Control and Reclamation Act of 1977 (SMCRA). The proposed amendment consists of revisions to rules and statutes pertaining to: fish and wildlife habitat and resource information, shrub density, certification of maps by a registered professional engineer, geologic descriptions, topsoil substitutes, special bituminous coal mines, archaeological and historic resources, permit transfers, civil penalties, and miscellaneous changes to Appendix A, which concerns vegetation sampling methods and reclamation success standards for surface coal

[[Page 40385]]

mining operations. The amendment is intended to revise the Wyoming program to be consistent with the corresponding Federal regulations, to clarify ambiguities, and to improve operational efficiency.

DATES: Written comments must be received by 4:00 p.m., m.d.t. August 28, 1998. If requested, a public hearing on the proposed amendment will be held on August 24, 1998. Requests to present oral testimony at the hearing must be received by 4:00 p.m., m.d.t. on August 13, 1998.

ADDRESSES: Written comments should be mailed or hand delivered to Guy Padgett at the address listed below.

Copies of the Wyoming program, the proposed amendment, and all written comments received in response to this document will be available for public review at the addresses listed below during normal business hours, Monday through Friday, excluding holidays. Each requester may receive one free copy of the proposed amendment by contacting OSM's Casper Field Office.

Guy Padgett, Field Office Director, Casper Field Office, Office of Surface Mining Reclamation and Enforcement, 100 East ``B'' Street, Federal Building, Room 2128, Casper, Wyoming 82601-1918 Rick Chancellor, Administrator, Land Quality Division, Department of Environmental Quality, Herschler Building--3rd Floor West, 122 West 25th Street, Cheyenne, Wyoming 82002, Telephone: 307-777-7046.

FOR FURTHER INFORMATION CONTACT: Guy Padgett, 307/261-6550; Internet: GPADGETT@OSMRE.GOV.

SUPPLEMENTARY INFORMATION:

  1. Background on the Wyoming Program

    On November 26, 1980, the Secretary of the Interior conditionally approved the Wyoming program. General background information on the Wyoming program, including the Secretary's findings, the disposition of comments, and the conditions of approval of the Wyoming program can be found in the November 26, 1980, Federal Register (45 FR 78637). Subsequent actions concerning Wyoming's program and program amendments can be found at 30 CFR 950.12, 950.15, and 950.16.

  2. Proposed Amendment

    By letter dated July 13, 1998, Wyoming submitted a proposed amendment (administrative record No. WY-32-1) to its program pursuant to SMCRA, 30 U.S.C. 1201 et seq. Wyoming submitted the proposed amendment in response to the required program amendments at 30 CFR 950.16 (b), (c), (g), (v), (x), (ii)(1), and (kk), and at its own initiative. The provisions of the Wyoming Coal Rules and Regulations that Wyoming proposed to revise were: (1) Chapter 1, section 2(ac), revises the definition of ``eligible land'' in the definitions section by adding the exact date of approval of the shrub density rule, August 6, 1996; (2) Chapter 2, Section 1(e), revises the section delineating the contents of permit applications by deleting reference to the defunct State Conservation Commission; (3) Chapter 2, Section 2(a)(vi)(G)(II), requires notification of the U.S. Fish and Wildlife Service by the Wyoming Administrator of the Land Quality Division if critical or crucial habitat disruption is likely; (4) Chapter 2, Section 2(a)(vi)(H), requires in the permit application a description of the areal and structural geology of the permit area and, by extrapolation, adjacent areas; (5) Chapter 2, Section 2(a)(vi)(J), corrects incorrect references to the Wyoming Statutes; (6) Chapter 2, Section 2(a)(vi)(J)(II), requires maps submitted in a permit application to depict the strike and dips of coal seams; (7) Chapter 2, Section 2(b)(iv)(C) revises the subsection on revegetation by deleting reference to the defunct State Conservation Commission; (8) Chapter 2, Section 2(b)(vi)(C), requires the submission of resource information when requested by the U.S. Fish and Wildlife Service; (9) Chapter 4, Section 2(c)(ix), allows the use of selected spoil material as a topsoil or subsoil substitute; (10) Chapter 4, Section 2(d)(x)(E)(I), revises the rule on shrub density to add the exact date of the approval of the rule, August 6, 1996; (11) Chapter 4, Section 2(d)(x)(E)(III), revises the rule to be consistent with the Wyoming Statute because the rule did not clarify that the Wyoming Game and Fish Department only has approval authority for revegetation standards on crucial habitat declared as such prior to the submittal of a permit application or any subsequent amendment; (12) Chapter 8, Section 3-4, revises the rules on special bituminous coal mines by establishing special alternative standards for new special bituminous surface coal mines; (13) Chapter 12, Section 1(a)(v)(B), requires that the effect on properties on the National Register of Historic Places must be taken into account prior to permit approval; (14) Chapter 12, Section 1(a)(v)(C), revises the rule on permitting procedures by adding the word, ``any'' in front of ``properties listed or eligible for listing on the National Register of Historic Places''; (15) Chapter 12, Section 1(b)(ii), revises the rule on permitting procedures by deleting, for permit transfers, the reference to the public participation requirements in Wyoming Statute 35-11-406(g); (16) Chapter 16, Section 3 (c) and (f), corrects the reference to the Wyoming Statute concerning civil penalties; (17) Appendix A, Appendix IV, revises the rules by adding additional plants to the List of Threatened and Endangered Species in Wyoming; (18) Appendix A, Options I-IV, makes 11 minor changes to the shrub density option tables; (19) Appendix A, Section II.C.2.c, corrects the cross- reference to the rule on cropland, hayland or pastureland; (20) Appendix A, Section II.C.3, removes the language referring to the approval of the shrub density rule and replaces it with the exact date of approval of that rule, August 6, 1996; (21) Appendix A, section VIII.E, removes the language referring to the approval of the shrub density rule with the exact date of the approval of that rule, August 6, 1996.

  3. Public Comment Procedures

    In accordance with provisions of 30 CFR 732.17(h), OSM is seeking comments on whether the proposed amendment satisfies the applicable program approval criteria of 30 CFR 732.15. If the amendment is deemed adequate, it will become part of the Wyoming program.

    1. Written Comments

      Written comments should be specific, pertain only to the issues proposed in this rulemaking, and include explanations in support of the commenter's recommendations. Comments received after the time indicated under DATES or at locations other than the Casper Field Office will not necessarily be considered in the final rulemaking or included in the administrative record.

    2. Public Hearings

      Persons wishing to testify at the public hearing should contact the person listed under FOR FURTHER INFORMATION CONTACT by 4:00 p.m., m.d.t. on August 13, 1998. Any disabled individual who has need for a special accommodation to attend a public hearing should contact the individual listed under FOR FURTHER INFORMATION CONTACT. The location and time of the hearing will be arranged with those persons requesting the hearing. If no one requests an opportunity to testify at the public hearing, the hearing will not be held.

      [[Page 40386]]

      Filing of a written statement at the time of the hearing is requested as it will greatly assist the transcriber. Submission of written statements in advance of the hearing will allow OSM officials to prepare adequate responses and appropriate questions.

      The public hearing will continue on the specified date until all persons scheduled to testify have been heard. Persons in the audience who have not been scheduled to testify, and who wish to do so, will be heard following those who have been scheduled. The hearing will end after all persons scheduled to testify and persons present in the audience who wish to testify have been hear.

    3. Public Meeting

      If only one person requests an opportunity to testify at a hearing, a public meeting, rather than a public hearing, may be held. Persons wishing to meet with OSM representatives to discuss the proposed amendment may request a meeting by contracting the person listed under FOR FURTHER INFORMATION CONTACT. All such meetings will be open to the public and, if possible, notices of meetings will be posted at the locations listed under ADDRESSES. A written summary of each meeting will be made a part of the administrative record.

  4. Procedural Determinations

    1. Executive Order 12866

      This rule is exempted from review by the Office of Management and Budget (OMB) under Executive Order 12866 (Regulatory Planning Review).

    2. Executive Order 12988

      The Department of the Interior has conducted the reviews required by section 3 of Executive Order 12988 (Civil Justice Reform) and has determined that this rule meets the applicable standards of subsections (a) and (b) of that section. However, these standards are not applicable to the actual language of State regulatory programs and program amendments since each such program is drafted and promulgated by a specific State, not by OSM. Under sections 503 and 505 of SMCRA (30 U.S.C. 1253 and 1255) and the Federal regulations at 30 CFR 730.11, 732.15, and 732.17(h)(10), decisions on proposed State regulatory programs and program amendments submitted by the States must be based solely on a determination of whether the submittal is consistent with SMCRA and its implementing Federal regulations and whether the other requirements of 30 CFR Parts 730, 731, and 732 have been met.

    3. National Environmental Policy Act

      No environmental impact statement is required for this rule since section 702(d) of SMCRA (30 U.S.C. 1292(d)) provides that agency decisions on proposed State regulatory program provisions do not constitute major Federal actions within the meaning of section 102(2)(C) of the National Environmental Policy Act (42 U.S.C. 4332(2)(C)).

    4. Paperwork Reduction Act

      This rule does not contain information collection requirements that require approval by OMB under the Paperwork Reduction Act (44 U.S.C. 3507 et seq.).

    5. Regulatory Flexibility Act

      The Department of the Interior has determined that this rule will not have a significant economic impact on a substantial number of small entities under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.). The State submittal that is the subject of this rule is based upon counterpart Federal regulations for which an economic analysis was prepared and certification made that such regulations would not have a significant economic effect upon a substantial number of small entities. Accordingly, this rule will ensure that existing requirements previously promulgated by OSM will be implemented by the State. In making the determination as to whether this rule would have a significant economic impact, the Department relied upon the data and assumptions for the counterpart Federal regulations.

    6. Unfunded Mandates

      This rule will not impose a cost of $100 million or more in any given year on any governmental entity or the private sector.

      List of Subjects in 30 CFR Part 950

      Intergovernmental relations, Surface mining, Underground mining.

      Dated: July 22, 1998. Peter A. Rutledge, Acting Regional Director, Western Regional Coordinating Center.

      [FR Doc. 98-20262Filed7-28-98; 8:45 am]

      BILLING CODE 4310-05-M