Central Vermont Public Service Corporation; Notice of Authorization for Continued Project Operation

Federal Register, Volume 77 Issue 73 (Monday, April 16, 2012)

Federal Register Volume 77, Number 73 (Monday, April 16, 2012)

Notices

Page 22568

From the Federal Register Online via the Government Printing Office www.gpo.gov

FR Doc No: 2012-9016

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

Project No. 2558-000

Central Vermont Public Service Corporation; Notice of Authorization for Continued Project Operation

On August 1, 2011, the Central Vermont Public Service Corporation, licensee for the Otter Creek Hydroelectric Project, filed an Application for a New License pursuant to the Federal Power Act (FPA) and the Commission's regulations thereunder. The Otter Creek Hydroelectric Project is located on Otter Creek in Addison and Rutland counties, Vermont.

The license for Project No. 2558 was issued for a period ending March 31, 2012. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. If the project's prior license waived the applicability of section 15 of the FPA, then, based on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 18 CFR 16.21(a), if the licensee of such project has filed an application for a subsequent license, the licensee may continue to operate the project in accordance with the terms and conditions of the license after the minor or minor part license expires, until the Commission acts on its application. If the licensee of such a project has not filed an application for a subsequent license, then it may be required, pursuant to 18 CFR 16.21(b), to continue project operations until the Commission issues someone else a license for the project or otherwise orders disposition of the project.

If the project is subject to section 15 of the FPA, notice is hereby given that an annual license for Project No. 2558 is issued to the Central Vermont Public Service Corporation for a period effective April 1, 2012 through March 31, 2013, or until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. If issuance of a new license (or other disposition) does not take place on or before March 31, 2013, notice is hereby given that, pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is renewed automatically without further order or notice by the Commission, unless the Commission orders otherwise. If the project is not subject to section 15 of the FPA, notice is hereby given that the Central Vermont Public Service Corporation is authorized to continue operation of the Otter Creek Hydroelectric Project, until such time as the Commission acts on its application for a subsequent license.

Dated: April 9, 2012.

Kimberly D. Bose,

Secretary.

FR Doc. 2012-9016 Filed 4-13-12; 8:45 am

BILLING CODE 6717-01-P