Environmental Impact Statements; Availability, etc.: Crystal River Unit 3 Nuclear Generating Plant

Federal Register: April 6, 2009 (Volume 74, Number 64)

Notices

Page 15523-15525

From the Federal Register Online via GPO Access [wais.access.gpo.gov]

DOCID:fr06ap09-124

NUCLEAR REGULATORY COMMISSION

Docket No. 50-302; NRC-2009-0039

Crystal River Unit 3 Nuclear Generating Plant; Notice of Intent

To Prepare an Environmental Impact Statement and Conduct Scoping

Process

Florida Power Corporation (FPC) has submitted an application for renewal of Facility Operating License No. DPR-72 for an additional 20 years of operation at the Crystal River Unit 3 Nuclear Generating Plant

(CR-3). CR-3 is located approximately 35 miles southwest of Ocala,

Florida.

Page 15524

The operating license for CR-3 expires on December 3, 2016. The application for renewal, dated December 16, 2008, was submitted pursuant to Title 10 of the Code of Federal Regulations (10 CFR) part 54. A notice of receipt and availability of the application, which included the environmental report (ER), was published in the Federal

Register on February 4, 2009 (74 FR 6060). A notice of acceptance for docketing of the application for renewal of the facility operating license was published in the Federal Register on March 9, 2009. The purpose of this notice is to inform the public that the U.S. Nuclear

Regulatory Commission (NRC) will be preparing an environmental impact statement (EIS) related to the review of the license renewal application and to provide the public an opportunity to participate in the environmental scoping process, as defined in 10 CFR 51.29. In addition, as outlined in 36 CFR 800.8, ``Coordination with the National

Environmental Policy Act,'' the NRC plans to coordinate compliance with

Section 106 of the National Historic Preservation Act in meeting the requirements of the National Environmental Policy Act of 1969 (NEPA).

In accordance with 10 CFR 51.53(c) and 10 CFR 54.23, FPC submitted the ER as part of the application. The ER was prepared pursuant to 10

CFR part 51 and is publicly available at the NRC Public Document Room

(PDR), located at One White Flint North, 11555 Rockville Pike,

Rockville, Maryland 20852, or from the NRC's Agencywide Documents

Access and Management System (ADAMS). The ADAMS Public Electronic

Reading Room is accessible at http://adamswebsearch.nrc.gov/ dologin.htm. The Accession Number for the ER is ML090080053. Persons who do not have access to ADAMS, or who encounter problems in accessing the documents located in ADAMS, should contact the NRC's PDR reference staff by telephone at 1-800-397-4209, or 301-415-4737, or by e-mail at pdr.resource@nrc.gov. The ER may also be viewed on the Internet at http://www.nrc.gov/reactors/operating/licensing/renewal/applications/ crystal-river.html. In addition, the ER is available for public inspection near the CR-3 at the public library: Coastal Region Library, 8619 W. Crystal St., Crystal River, FL 34428-4468.

This notice advises the public that the NRC intends to gather the information necessary to prepare a plant-specific supplement to the

Commission's ``Generic Environmental Impact Statement (GEIS) for

License Renewal of Nuclear Plants,'' (NUREG-1437) related to the review of the application for renewal of the CR-3 operating license for an additional 20 years. Possible alternatives to the proposed action

(license renewal) include no action and reasonable alternative energy sources. The NRC is required by 10 CFR 51.95 to prepare a supplement to the GEIS in connection with the renewal of an operating license. This notice is being published in accordance with NEPA and the NRC's regulations found in 10 CFR part 51.

The NRC will first conduct a scoping process for the supplement to the GEIS and, as soon as practicable thereafter, will prepare a draft supplement to the GEIS for public comment. Participation in the scoping process by members of the public and local, State, Tribal, and Federal government agencies are encouraged. The scoping process for the supplement to the GEIS will be used to accomplish the following: a. Define the proposed action which is to be the subject of the supplement to the GEIS. b. Determine the scope of the supplement to the GEIS and identify the significant issues to be analyzed in depth. c. Identify and eliminate from detailed study those issues that are peripheral or that are not significant. d. Identify any environmental assessments and other ElSs that are being or will be prepared that are related to, but are not part of, the scope of the supplement to the GEIS being considered. e. Identify other environmental review and consultation requirements related to the proposed action. f. Indicate the relationship between the timing of the preparation of the environmental analyses and the Commission's tentative planning and decision-making schedule. g. Identify any cooperating agencies and, as appropriate, allocate assignments for preparation and schedules for completing the supplement to the GEIS to the NRC and any cooperating agencies. h. Describe how the supplement to the GEIS will be prepared, and include any contractor assistance to be used.

The NRC invites the following entities to participate in scoping: a. The applicant, Florida Power Corporation. b. Any Federal agency that has jurisdiction by law or special expertise with respect to any environmental impact involved, or that is authorized to develop and enforce relevant environmental standards. c. Affected State and local government agencies, including those authorized to develop and enforce relevant environmental standards. d. Any affected Indian tribe. e. Any person who requests or has requested an opportunity to participate in the scoping process. f. Any person who has petitioned or intends to petition for leave to intervene.

In accordance with 10 CFR 51.26, the scoping process for an EIS may include a public scoping meeting to help identify significant issues related to a proposed activity and to determine the scope of issues to be addressed in an EIS. The NRC has decided to hold public meetings for the CR-3 license renewal supplement to the GEIS. The scoping meetings will be held at the Plantation Inn, 9301 W Fort Island Trail, Crystal

River, FL 34429, on April 16, 2009. There will be two sessions to accommodate interested parties. The first session will convene at 2 p.m. and will continue until 5 p.m., as necessary. The second session will convene at 7 p.m. with a repeat of the overview portions of the meeting and will continue until 10 p.m., as necessary. Both meetings will be transcribed and will include: (1) An overview by the NRC staff of the NEPA environmental review process, the proposed scope of the supplement to the GEIS, and the proposed review schedule; and (2) the opportunity for interested government agencies, organizations, and individuals to submit comments or suggestions on the environmental issues or the proposed scope of the supplement to the GEIS.

Additionally, the NRC staff will host informal discussions one hour prior to the start of each session at the same location. No formal comments on the proposed scope of the supplement to the GEIS will be accepted during the informal discussions. To be considered, comments must be provided either at the transcribed public meetings or in writing, as discussed below. Persons may register to attend or present oral comments at the meetings on the scope of the NEPA review by contacting the NRC Project Manager, Elaine Keegan, by telephone at 1- 800-368-5642, extension 8517 or by e-mail at elaine.keegan@nrc.gov no later than April 9, 2009. Members of the public may also register to speak at the meeting within 15 minutes of the start of each session.

Individual oral comments may be limited by the time available, depending on the number of persons who register. Members of the public who have not registered may also have an opportunity to speak, if time permits. Public comments will be considered in the scoping process for the supplement to the GEIS. Elaine Keegan will need to

Page 15525

be contacted no later than April 9, 2009, if special equipment or accommodations are needed to attend or present information at the public meeting, so that the NRC staff can determine whether the request can be accommodated.

Members of the public may send written comments on the environmental scope of the CR-3 license renewal review to: Chief,

Rulemaking and Directives Branch, Division of Administrative Services,

Office of Administration, Mailstop TWB 5B-01M, U.S. Nuclear Regulatory

Commission, Washington, DC 20555-0001, and should cite the publication date and page number of this Federal Register notice. To be considered in the scoping process, written comments should be postmarked by May 15, 2009. Electronic comments may be sent by e-mail to the NRC at crystalrivereis@nrc.gov, and should be sent no later than May 15, 2009, to be considered in the scoping process. Comments will be available electronically and accessible through ADAMS at http:// adamswebsearch.nrc.gov/dologin.htm.

Participation in the scoping process for the supplement to the GEIS does not entitle participants to become parties to the proceeding to which the supplement to the GEIS relates. Notice of opportunity for a hearing regarding the renewal application is also included in this

Federal Register. Matters related to participation in any hearing are outside the scope of matters to be discussed at this public meeting.

At the conclusion of the scoping process, the NRC will prepare a concise summary of the determination and conclusions reached, including the significant issues identified, and will send a copy of the summary to each participant in the scoping process. The summary will also be available for inspection in ADAMS at http://adamswebsearch.nrc.gov/ dologin.htm. The staff will then prepare and issue for comment the draft supplement to the GEIS, which will be the subject of separate notices and separate public meetings. Copies will be available for public inspection at the above-mentioned addresses, and one copy per request will be provided free of charge. After receipt and consideration of the comments, the NRC will prepare a final supplement to the GEIS, which will also be available for public inspection.

Information about the proposed action, the supplement to the GEIS, and the scoping process may be obtained from Elaine Keegan at the aforementioned telephone number or e-mail address.

Dated at Rockville, Maryland, this 31st day of March, 2009.

For the Nuclear Regulatory Commission.

David J. Wrona,

Chief, Projects Branch 2, Division of License Renewal, Office of

Nuclear Reactor Regulation.

FR Doc. E9-7653 Filed 4-3-09; 8:45 am

BILLING CODE 7590-01-P